Mod 1 Proj Mgmt Foundations (30) Flashcards
1) What is one advantage of a functional organization structure?
a. Timely responses to changes
b. Team members report to one manager
c. Rapid reaction to changes
d. Flexible resource scheduling
d. Flexible resource scheduling
Advantages of a functional organization structure include a broad specialist base, shared knowledge of latest technology, and flexible resource scheduling.
2) Which of the following describes an individual in a management role within a functional area of the organization that has their own permanent staff responsible for the ongoing work?
a. Project manager
b. Program manager
c. Functional manager
d. Portfolio manager
c. Functional manager
The best answer choice is C. The functional manager has a permanent staff responsible for carrying out the ongoing work of the organization.
3) You work for a commercial roofing contractor. You are asked to do a job in Barrow, Alaska. Which EEF do you need to pay closest attention to?
a. Company culture
b. Infrastructure
c. Weather
d. Availability of resources
c. Weather
In Alaska, weather is always an EEF!
4) `What is an input?
a. Something tangible used in performing an activity to produce a product or result
b. A defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service
c. A systematic series of activities directed toward causing an end result
d. Any item, whether internal or external to the project, that is required by a process before that process proceeds
d. Any item, whether internal or external to the project, that is required by a process before that process proceeds
An input is any item, whether internal or external to the project, that is required by a process before that process proceeds. It may also be an output from a predecessor process.
5) The Project Management Knowledge Areas include which of the following?
a. Cost management
b. Initiating
c. Executing
d. Planning
a. Cost management
The best answer choice is A because it is the only option that represents a knowledge area. The other options are process groups.
6) The custom homebuilder you work for has a contract to build a home. The customer wants marble from Florence, Italy. To work with the tile, you need extremely skilled craftspeople with special tools. This EEF is an example of
a. Company culture
b. Infrastructure
c. Weather
d. Availability of resources
d. Availability of resources
The material and the labor to work with it are constraints associated with the availability of resources.
_7) Standards, codes, and regulations are examples of
a. Company culture
b. Ethical considerations
c. Enterprise environmental factors
d. Professional conduct factors
Note: Need complete answer explanation
c. Enterprise environmental factors
Enterprise environmental factors are conditions not under the immediate control of the team, that influence, constrain, or direct the project, program, or ______
All answers below are incorrect b/c:
a. Company culture
b. Ethical considerations
d. Professional conduct factors
8) You are tasked with completely updating your organization’s communication infrastructure. You decide to break this into several components: one each for telephones, IT, and radio communication. Each will have its own manager. This is an example of
a. A project
b. A portfolio
c. A program
d. Operations
c. A program
This is a program. Each component is a project.
9) Which of the following is NOT one of the PMI‐identified competing constraints?
a. Market conditions
b. Quality
c. Schedule
d. Resources
a. Market conditions
Market conditions might be an enterprise environmental factor, but they’re not one of the competing constraints.
10) Sequence Activities is part of the ______ process group and correlates to the Project ________ Management knowledge area
a. Planning; Time
b. Initiating; Scope
c. Executing; Stakeholder
d. Initiating; Risk
a. Planning; Time
Sequence Activities is a process categorized under the Planning process group. This process correlates to the knowledge area of Project Time Management.
11) Which describes a controlling PMO?
a. Requires compliance with the project management methodology
b. Serves as a project repository for project management resources
c. Manages large and specific projects
d. Has a high degree of control
a. Requires compliance with the project management methodology
A controlling PMO develops policies, procedures, templates, forms, and reports for project management and requires compliance with the project management methodology.
12) You are planning a small construction project. What will be one of your first tasks?
a. Identify your suppliers
b. Hire the necessary personnel
c. Identify the competing constraints
d. Prepare a schedule
c. Identify the competing constraints
Part of your job as a project manager is to first identify the competing constraints and then manage your project to balance them appropriately.
13) You’re setting up your project and need to manage it so that you complete one phase and get customer sign‐off before beginning the next phase. What type of project life cycle should you use?
a. Overlapping
b. Sequential
c. Fast tracking
d. Iterative
b. Sequential
A sequential project life cycle requires you to complete one phase before initiating the next phase.
14) Which of the following is NOT an organizational process asset?
a. Risk database
b. Information from past projects
c. Change control policies
d. Risk tolerance
d. Risk tolerance
Risk tolerance is an enterprise environmental factor (EEF).
15) Your team has completed the first phase of a project, which produced a small batch of the finished product. You sent this to the client for review and based on the feedback, you may need to make some changes. This is an example of a(n) ________ life cycle.
a. Adaptive
b. Iterative and incremental
c. Predictive
d. Directive
a. Adaptive
Adaptive life cycles solicit client review and feedback at each iteration. One of the benefits of the adaptive life cycle is that making changes earlier in the life cycle is much easier.