Level 3 - Cashflow Forecasting Flashcards

1
Q

How did you go about preparing your cashflow forecast ?

A

I used indicative stage 3 programme from the EA

Split the cost plan (formal cost plan 2) works elementally across the programme which indicated a ‘S curve’ in expenditure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What would you advise the Client on a project where actual payments are behind the anticipated forecast?

A

Could be a number of things - I would discuss with the contractor first to find out reasons and report back to the client

This happened on Devonshire Row, I advised the client that this indicated the project was in delay and a potential risk to the overall completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are some other causes of contractor being behind on cashflow?

A

The cashflow was wrong in the first place

  1. Works being omitted
  2. Resequencing of the Works
  3. Lots of variations Changes
  4. Inaccurate Cashflow
  5. Materials not being delivered in time
  6. Materials behind stored offsite and not claimed for
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If the cash flow was ahead of schedule what could this indicate?

A
  1. Ahead of programme
  2. Contractor front loading costs
  3. Resequencing (higher value works carried out earlier)
  4. Inaccurate cashflow
  5. Advanced payments
  6. Materials offsite not taken into account when preparing cashflow
  7. Materials being stored on site way before they’re required
  8. Variations
  9. Acceleration (to complete works earlier
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of a cash flow forecast?

A

Pre contract Tells client how much money they will be spending on a monthly basis.

Post contract Helps the client drawdown funds from funders / creditors. Helps the client to understand whether the contractor is ahead or behind the programme. Helps the client understand how much money is being spent in relation to anticipated cash flow.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why is it important to have a cash-flow?

A

Outlines anticipated expenditure

Gives an indicated of when funds are required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How was the cash flow produced post contract?

A

The contractor produced the cashflow post contract using their programme and CSA and splitting works into the appropriate months. They then deducted the retention each month to give a net cumulative total. I then reviewed it and agreed it with them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did you update the cashflow forecast in every monthly cost report?

A

Cumulative net amount paid till date and then minus the retention

Updated the cashflow forecast taking this into account

Continuously compared actual cash flow to predicted cash flow to predicted cashflow forecast in every updated cost report using a line graph.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When might you adjust the cash flow forecast?

A
to reflect EAIs
reflect anticipated variations
reflect loss and expense
reflect prov sums
reflect risk allowances
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What’s the risk of using a PM programme when preparing a cashflow?

A

Inaccurate sequencing of the works, contractor might have different methodology.

Cash flow forecast should be updated when entering in to contract and based on the contractors programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why is it important that the contractor prepared the cashflow rather than you preparing one?

A

They are more aware of how works will be sequenced and therefore should be more accurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How often was the cashflow updated?

A

Monthly to reflect actual expenditure and post contract changes

Should also be updated to reflect any large variations / provisional sums

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

You mentioned you advised the client that the contractor was delayed due to cashflow indicating they was behind, would this be your first action / advise to the client if cashflow is behind?

A

I would discuss with the contractor before making any assumptions
Could be number of things
1. Works may be omitted
2. Sequenced
3. Lot of changes Variations
4. Inaccurate baseline cashflow
On this project it was clear the contractor was progressing much slower than anticipated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the issue for the client is actual payments are ahead of cashflow?

A

Potential funding issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

You had a variations tracker, was variations included in the cashflow?

A

Yes, I would ask the contractor to update cashflow if:
• They wasn’t progressing diligently – ie behind programme
• To reflect EAI
• To reflect Anticipated Changes
• Loss & Expense
• Changes to provisional sums

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

On Devonshire row, why was the cashflow falling behind?

A

Performance of the contractor (labour shortages)
Instructions to carry out additional works
Contractor not being able to access landlord areas where they were working in

17
Q

How would you allow for risk when preparing a cash flow?

A

Depends what stage:
Early stages – would be a % on the construction cost and fed into S curve
Later Stages – ideally a priced risk register which feeds into the cash flow

18
Q

How did you include and provisional sums in the cashflow?

A

Include as provisional value and update when agreed cost

Undefined is difficult to understand when it will be expended

Risk of provisional sum should being over (or under) should be included in the risk register and factored into the risk spend profile

19
Q

What are some events on site that you may need to adjust the cashflow?

A
  1. Actual progress (in front or behind)
  2. Variations
  3. Change in sequencing
  4. Formally awarded EOT
  5. Acceleration in the event of falling behind
  6. Partial possession
20
Q

How would you deal with EOT or L&E in cashflows?

A

When EOT is granted cashflow should be updated to reflect new completion date

L&E should be reported at the earliest opportunity (if it hasnt been agreed yet I would let the client know about the accuracy of the cash flow and provide them with best and worst case assessment so the client understands their potential liability

21
Q

How accurate was the stage 3 cashflow you prepared against the contractors?

A

It was similar and spread across them same time period and showed and S curve