L2 - Contract Administration Flashcards
What are the standard contract forms and when might each be appropriate? (5)
1) Lump Sum – Building where design is complete
2) Measured – Infrastructure work or ongoing work where the scope is known but not quantity
3) Cost Reimbursable – Early start required e.g. emergency works
4) Design and Build – Partial design where contractor takes over responsibility
5) Management – Trade packages are managed directly (no MC) – early start
- What obligations does the quantity surveyor have under D&B?
Only EA (no QS role D&B) Undertake valuations L&E Final Account Value variations
- What obligations does a CA/EA have?
Only EA D&B Chair meetings Instructions EoT Issue Certificates Certify Completion
- What is the difference between CA & EA?
CA – SBC EA – D&B
EA typically also undertakes QS duties but this is not assumed contractually i.e. could be different party but no formal QS role under D&B
- Why is it important to take meeting minutes?
Clearly outlines key discussion; agreements or issues, actions by when and by who
- What is the order of a typical progress meeting?
Intro’s actions from previous contractor report progress & issues change future meetings
- What certificates might be issued and why?
Completion certificate – ensure time is not at large
Interim valuation certificate – Confirm agreed valuation between EA and MC
- What is the RfP/valuation?
Gross valuation, less retention, less previous payments.
Agreed with the contractor and issued as “RfP” to the client (only “advice”) by EA/CA.
- What are the implications of completion?
Implications; Rectification period begins - Half retention released - Client insures - LDs are not applicable
Employer must accept building early if it is actually complete
- What impact does the Local Development Economic Co Act impose on a contract?
- Payment notice must be issued 5 days after due date
- If no payment notice after 5 days, then contractor can issue their own
- Pay less notice must be issued if employer is to pay less than the the notice
- Entitled to Adjudication
- What were your duties on the EA contract?
Take meeting minutes
Issue Instructions
Issue Certificates
Certify Completion
- Was there not a QS on the project?
I undertook QS duties as well
- What change requests did you receive? Park
Re-fitting of guttering pipes to adjacent delipated building as water was seaping onto the site and not into drain
- What was included in your change request form?
Outline of works inc. rates & quantity#
Any impact on programme . date for instructions
- Give an example of when you priced a variation?
UPS steps
- How long does a contractor have to respond to a variation request?cD&B
D&B 14 days of instruction
Employer has 10 days to instruct
Contractor can object e.g. H&S issue
Employer pays for design work if not instructed
- Does the time change for a contractor to respond to a variation request on SBC differ?
21 days SBC (14 days D&B)
Employer 7 days to instruct (10 D&B)
- What happens if they do not respond or refuse?
The employer can employ someone else to undertake the work:
- Employer must give written notice to comply
- 7 days must elapse after this notice to commence works
- What did you issue when the contractor failed to achieve the completion date and why did you do this?
Non- completion notice – ensure time was not at large to allow the client to issue LD’s if needed
- What was stated in the non completion notice?
States that on the date of the contract completion the works was had not satisfied the completion requirements
- There was a dispute between the client and the contractor as progress was slow and the contract completion date had passed? How did you deal with the issue?
I considered both parties perspectives:
Contractor representative was faced with a difficult situation as it was clear he was not being provided with sufficient resource to complete project
Client – Had not issued LD’s and had aided the MC with the project but was not seeing much improvement
- I suggested that parties work together on a completion countdown programme to completion that could be agreed.
- If works continued to not progress then further action would have to be considered.
How does D&B differ to SBC contractually?
Contractor responsible for design No listed subcontractors, No architect/CA/QS (EA only), No clerk of works, No payment certification – contractor applies and employer decides how much
Roles/Responsibilities of: Client COntractor QS CA EA
Client - Pay, Possession, Insure, Not obstruct, Pay Less if does not agree/LDs
Contractors – Complete Work & Design, Comply, Inform EA of discrepancies
QS – Only EA (no QS role D&B), Undertake valuations, Confidential, L&E, Final Account, Value variations
CA – Only EA D&B), Chair meetings, Inspect work, Instructions, EoT, Issue Certificates, Certify Completion
EA – As CA but for D&B, typically QS but contractually is assumed as different party
Contractors Estimate - D&B process?
- Contractor must provide a quotation within 14 days of the instruction (SBC 21)
- Employer then has 10 days to accept the quotation or withdraw instruction (7 days SBC)
- Contractor can object on reasonable grounds within 10 days of instruction
- Employer will pay for specific design work required to produce the estimate if rejected
When are you supposed to have Employer Liability insurance?
Required by all firms employing staff, Pays out if employee is injured or ill
Public Liability;
Covers injury or death to public, also covers loss or damage to 3rd parties