L2 - Contract Administration Flashcards

1
Q

What are the standard contract forms and when might each be appropriate? (5)

A

1) Lump Sum – Building where design is complete
2) Measured – Infrastructure work or ongoing work where the scope is known but not quantity
3) Cost Reimbursable – Early start required e.g. emergency works
4) Design and Build – Partial design where contractor takes over responsibility
5) Management – Trade packages are managed directly (no MC) – early start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. What obligations does the quantity surveyor have under D&B?
A
Only EA (no QS role D&B)
Undertake valuations
L&E
Final Account
Value variations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. What obligations does a CA/EA have?
A
Only EA D&B
Chair meetings
Instructions
EoT
Issue Certificates
Certify Completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. What is the difference between CA & EA?
A

CA – SBC EA – D&B
EA typically also undertakes QS duties but this is not assumed contractually i.e. could be different party but no formal QS role under D&B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Why is it important to take meeting minutes?
A

Clearly outlines key discussion; agreements or issues, actions by when and by who

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. What is the order of a typical progress meeting?
A
Intro’s
actions from previous
contractor report
progress & issues
change
future meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. What certificates might be issued and why?
A

Completion certificate – ensure time is not at large

Interim valuation certificate – Confirm agreed valuation between EA and MC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. What is the RfP/valuation?
A

Gross valuation, less retention, less previous payments.

Agreed with the contractor and issued as “RfP” to the client (only “advice”) by EA/CA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. What are the implications of completion?
A

Implications; Rectification period begins - Half retention released - Client insures - LDs are not applicable
Employer must accept building early if it is actually complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. What impact does the Local Development Economic Co Act impose on a contract?
A
  • Payment notice must be issued 5 days after due date
  • If no payment notice after 5 days, then contractor can issue their own
  • Pay less notice must be issued if employer is to pay less than the the notice
  • Entitled to Adjudication
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. What were your duties on the EA contract?
A

Take meeting minutes
Issue Instructions
Issue Certificates
Certify Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Was there not a QS on the project?
A

I undertook QS duties as well

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. What change requests did you receive? Park
A

Re-fitting of guttering pipes to adjacent delipated building as water was seaping onto the site and not into drain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. What was included in your change request form?
A

Outline of works inc. rates & quantity#

Any impact on programme . date for instructions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Give an example of when you priced a variation?
A

UPS steps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. How long does a contractor have to respond to a variation request?cD&B
A

D&B 14 days of instruction
Employer has 10 days to instruct
Contractor can object e.g. H&S issue
Employer pays for design work if not instructed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. Does the time change for a contractor to respond to a variation request on SBC differ?
A

21 days SBC (14 days D&B)

Employer 7 days to instruct (10 D&B)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  1. What happens if they do not respond or refuse?
A

The employer can employ someone else to undertake the work:

  • Employer must give written notice to comply
  • 7 days must elapse after this notice to commence works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  1. What did you issue when the contractor failed to achieve the completion date and why did you do this?
A

Non- completion notice – ensure time was not at large to allow the client to issue LD’s if needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  1. What was stated in the non completion notice?
A

States that on the date of the contract completion the works was had not satisfied the completion requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q
  1. There was a dispute between the client and the contractor as progress was slow and the contract completion date had passed? How did you deal with the issue?
A

I considered both parties perspectives:
Contractor representative was faced with a difficult situation as it was clear he was not being provided with sufficient resource to complete project

Client – Had not issued LD’s and had aided the MC with the project but was not seeing much improvement

  • I suggested that parties work together on a completion countdown programme to completion that could be agreed.
  • If works continued to not progress then further action would have to be considered.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How does D&B differ to SBC contractually?

A
Contractor responsible for design 
No listed subcontractors, 
No architect/CA/QS (EA only), 
No clerk of works, 
No payment certification – contractor applies and employer decides how much
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q
Roles/Responsibilities of:
Client
COntractor
QS
CA
EA
A

Client - Pay, Possession, Insure, Not obstruct, Pay Less if does not agree/LDs
Contractors – Complete Work & Design, Comply, Inform EA of discrepancies
QS – Only EA (no QS role D&B), Undertake valuations, Confidential, L&E, Final Account, Value variations
CA – Only EA D&B), Chair meetings, Inspect work, Instructions, EoT, Issue Certificates, Certify Completion
EA – As CA but for D&B, typically QS but contractually is assumed as different party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Contractors Estimate - D&B process?

A
  • Contractor must provide a quotation within 14 days of the instruction (SBC 21)
  • Employer then has 10 days to accept the quotation or withdraw instruction (7 days SBC)
  • Contractor can object on reasonable grounds within 10 days of instruction
  • Employer will pay for specific design work required to produce the estimate if rejected
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

When are you supposed to have Employer Liability insurance?

A

Required by all firms employing staff, Pays out if employee is injured or ill

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Public Liability;

A

Covers injury or death to public, also covers loss or damage to 3rd parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Professional indemnity insurance;

A

Professional services –
Negligence –
assurance against bankruptcy in case of claim,
run off cover for retirement/ winding down

28
Q

What is Terrorism insurance? Is it higher in certain regions?

A

Contract requirement
Damage or loss by terrorism
Pool re-insurance back by UK gov. should losses be too large, premium for high-risk areas e.g. London

29
Q

Non-negligent insurance –

A

Contractor acquires.

Insurer may not pay if non-negligent, i.e. contractor is not to blame!

30
Q

Contractor’s all risk –

A

Joint policy with employer,
protects against loss or damage to works,
machinery,
materials

31
Q

Contract Option Insurance:

What is

A

Option A - New Building - Contractor – Full reinstatement plus Fees, Risk of underinsurance with contractor
Option B - New Building – Employer - Full reinstatement plus Fees, Employer must cover any insurance shortfall
Option C – Existing structure – Employer – Replacement schedule required (Expert required) (Insurance covered by Landlord not party to contract if tenant is Employer). Employer must cover any insurance shortfall
Either party can terminate the contract following extensive damage with a 28-day notice

32
Q

What is a Performance Bond?
When does it expire?
Which bonds are there? (2)

A

Surety to Employer of Contractor non-performance
Worth 10% of Contract value (delay & re-tendering)
Expires at PC/EoD
On Demand as with a
Conditional Bond proof of non performance and loss is required – JCT 2016 option to include

33
Q

What is a Parent Company Guarantee? How is it incorporated?

A

Contractor procures in Employers favour
No Cost
Parent Company assume responsibility for Contractor obligations should they become insolvent
Lasts the limitation period of contract (6/12 years)

L2 - Wrexham ECE - Mark Wakefield Demolition

34
Q

What are 3rd Party Rights? How do they differ to CW’s?

A
  • Rights of third parties Act 1999 allows the enforcement of terms of a contract that confer a benefit upon them

Can only apply if written into contract prior to execution
e.g. Sub Contractors’s are identified
SC’s must be known early on
(typically they are not appointed until post MC appointment)
Less favourable than CW’s as not tested in court

35
Q

Collateral Warranties –

A

Creates contractual link where otherwise would not exist
e.g. Funder to MC or Employer to SC
Protects against defective work should a party become insolvent
e.g. MC ceased trading but Employer has benefit of CW with SC
Usually a completion requirement for CW’s to be executed.

36
Q

Change Process D&B

A

Change from ER’s; Design, Quality or Quantity or Imposition (site access, working hours, reduced working area)

Employer makes EA aware – Instruction/EAI (if immediate) or
Estimate – Employer Proceed? – Change Proposal to Contractor – Contractor Price – Accepted or Negotiated

Instruction by EA – Contractor confirms within 7 days – takes effect from 7 days of confirmation
If Contractor does not comply Employer/EA can give notice – 7 days post notice 3rd party can be appointed

37
Q

Practical Completion typical requirements?

A
H&S file, 
Testing & Commissioning, 
Work Practically Complete, 
O&M, 
CW’s, 
Building Certificate, 
Planning Compliance, 
Structural Warranty, 
As Built DWGs, 
Keys.
38
Q

Sectional Completion –

A

Contract provision
As Practical COmpletion but Pro Rata
Value of Section must be stipulated e.g. 50% of contract value if two sections of same value

39
Q

Partial Possession –

A

Post contract variation
Contractor cannot unreasonably withhold
Detail to clarify extent of area, implications as SC

L2 - UPS Conveyor contractor

40
Q

Early Use –

A

Employer may use part of the site early for storage or otherwise with contractors consent
contractor responsible
notify insurers as likely to attract premium (third party use)

L2 - UPS; Considered but dismissed due to potential claims from Main Contractor

41
Q

What are Named Subcontractors?
WHat is the process?
Which type is no longer used?
Would you recommend this?

A

Client can influence the selection of sub-contractors - MC responsibility for SC performance

  1. Client short-list SC’s in the tender documents for the main construction contract.
  2. MC has opportunity to reasonably object to any firm on the list.
  3. MC leads the tender process for each named SC package.
  4. After appointment, the named subcontractor becomes a domestic subcontractor.

Nominated no longer included in JCT

Good if a component of work is specialist and client has relationship with trade contractor. Takes away from Main Contractor

42
Q

Domestic Subcontractor –

A

A contractor the MC sub-contracts to carry out part of the works.
SC domestic if freely selected by a list of at least three
Named sub-contractors become domestic sub-contractors once they are appointed by the MC.

43
Q

Outline what an Extension of Time is and how to review one?

A

Preserve right to issue LD’s
Contractor must give notice:
Cause of delay (Relevant Event) & expected delay to completion date.

Employer has 12 weeks to assess the EoT (if less time to completion endeavour to assess prior)
Must be attributed to a Relevant Event or Matter
Employer must establish:
1. Has the delay been caused by the event?
2. Will the delay disrupt the programme?
3. What is the delay likely to be?
Contractor should endeavour to prevent delay

L2 - Wrexham
Material issue - not deemed a RE- Contractor cashflow main cause of delay (resource issues)
UPS - act or ommission - HV power delay

44
Q

What is a Concurrent delays?

A

Usual to grant an EoT for the dominant delay (begins before and finishes after the other delay)

Where 1 concurrent event is due to contractor and 1 due to employer,
Usual (and backed up in case law) that the contractor may receive an EoT to cover the employer caused delay, despite being partly to blame for its own delay.

Example -

45
Q

Is the employer required to pay for Materials off site? How can they be included in a valuation?

A

Off Site:

  • Employer not obliged to pay for any materials off site unless ‘listed items’ within the contract
  • Listed items e.g. bespoke cladding or steelwork, lift

In order to to be included in valuation:

  • Listed (in contract)
  • Vesting certificate (in the employer)
  • Insurance (against specified perils until delivery to site then covered under all risk insurance)
  • Set apart, clearly marked, identified and properly protected

L2 - Wrexham

46
Q

Can On Site Materials be included in a valuation?
Who’s property are the materials?
Who takes responsibility for damage>

A

Can be included in a valuation if:

  • Not delivered prematurely
  • Suitably protected from weather (insulation not covered to prevent water ingress)
  • The materials become property of the employer once they are paid for but the contractor is still responsible for any damage and/or theft.
47
Q

What is Termination?

A

-Events may occur on site which are so serious that the other party may prefer not to continue with the contract
o Provision allowing the termination of the employment of the contractor

  • Termination is of the contractor’s employment under the contract rather than termination of the contract itself

o Parties will remain bound by the contract and can bring losses associated with it. If the contract is terminated, this cannot happen.

  • Termination can be initiated by the employer or contractor.

Example

48
Q

Termination by the Employer: How would you implement?

A

Notice of default of 14 days
Notice of termination 21 days then Employer can employ others
Reasonable time for final account

49
Q

Contractor Default

A
  • Suspends work with no cause
  • Fails to proceed
  • Refuses to comply
50
Q

What would happen if the Contractor became insolvent?

A
  • If the Contractor becomes insolvent the Employer can terminate the Contract.
  • The Contractor to notify the Employer of any insolvency matters arising.

When the Contractor becomes insolvent (regardless of any notices):

  • No further sum shall become due to the Contractor (except final date for payment subject to any Pay Less Notices).
  • Contractor’s obligations to complete the works shall be suspended.
  • The Employer to protect and secure the site and the site materials.
51
Q

What is Contractor corruption?

A
  • Any person employed by the Contractor (this Contract or others) if they have carried out an act of corruption under the Bribery Act 2010.
  • If the Employer is a Local Authority and been given a fee or reward of which is an offence under the Local Government Act 1972.
52
Q

If the Contractor becomes insolvent the Employer may appoint a new contractor to complete the works but may require the contractor to:

A
  • Remove temporary site buildings and plant
  • Provide copies of all contractor’s designs
  • Assign benefit of subcontractors to employer
  • A notional final account must be put together by the employer within 3 months of the completion of the works (establish loss)
  • Contractor becomes liable for the amount required to the employer
53
Q

Process for Termination by the contractor?

A
Notice of default 14 days
Notice of termination 21 days
Employment terminated
Reasonable time for final account
28 day payment
54
Q

The contractor can terminate its own employment under the contract due to:

A

Employer default:
- Does not pay
- Fails to comply with CDM
Employer insolvency
- Termination by the contractor is optional
- Contractor must issue notice and termination will take effect from receipt of notice

55
Q

Termination by either party (suspension what)?

A

Either party has the right to terminate the contract if the works are suspended for the period noted in the contract particulars

2 months suspension: 
Warning notice 7 days 
Termination 
Reasonable time for final account 
28 day payment
  • Force majeure – Negligence of statutory undertaker – loss/ damage by insurance – terrorism – UK government
    -Final account;
    Value
    loss & damage
    removal
    protection/security

e.g. Covid (potential but government allowed construction works to continue)

56
Q

What are Liquidated Damages?
Can additional claims be made? what are they called?
How could you calculate LD’s?
How are they included in the contract?

A
  • Failure to comple the project by the completion date = Employer make deduction:
  • Pre-determined estimates of loss to the employer (not penalties which are unenforceable). The loss must flow from the contract breach and not be remote
  • If losses are significantly different to the estimate in the contract, the employer can claim unliquidated damages (actual loss) through the courts

Examples of the calculation of LDs include:

  • Loss of rent
  • Loss of income
  • Fees
  • Storage costs
  • Rental costs
  • Finance costs

This amount is inserted into the contract per day or week
-Following completion of a Section, the rate for the works will reduce pro-rata unless the amounts per Section are specifically included

57
Q

Process for issuing LDs

A
  • Practical completion not achieved:
  • Employer fulfilled all duties in awarding any EoTs
  • Issue a non-completion notice for the works (to ensure that time is not at large)
  • Employer must notify the contractor before due date for the final payment that they may withhold liquidated damages for the period between the completion date and the date of PC
  • Employer may withhold amount in LDs section or a lesser amount
  • Employer must issue a Pay Less Notice including detail of calculation
  • Further EoT will cancel out any non-completion notice although a new notice can then be issued if necessary
58
Q

What does issuing a Completion notice provide for the contractor?

A
  • Fixed point/date for damages if applicable
59
Q

What is the Defects/rectification period?
How does the process work?
What is a latent defect vs patent?
Example of typical defects

A
  • Contractor is required to make good any defects as notified by the employer for the Rectification Period
  • Default period for JCT is 6 months but commonly amended to 12 months (allow for a full season of weather)
  • Employer should provide a schedule of defects within:
    14 days of the end of the Rectification Period e.g. 12 months +14 days
  • If contractor refuses to undertake rectification of the defects and suitable notice is given to the contractor, the employer may use the retention monies to undertake the works and deduct any allowances from any further money due to the contractor
  • Once complete -
    1. Notice of Completion of Making Good is issued (pre-condition of the final payment)
    2. Retention released upon issue of Notice of Completion of Making Good.
  • Latent defect (remember Later) – defects which arise in future that could not be seen (rectification dependent on limitation period – 6 or 12 years)
  • Patent defect (remember Present) defects discovered upon inspection during rectification period.
60
Q

Final account statements/certificates

A
  • Following practical completion, monthly payment notices must still be issued up to the final payment, whether or not there is any sum due – there may be payments for loss and expense etc.
  • Final statement (D&B)
  • Following PC, the contractor must send a final statement with supporting information
  • Contract sum adjustments, sums already paid and the balance to be paid
61
Q

How have you adjusted a Final account statement?

A

Provisional sums – Instructions - Loss and expense

  • Contractor must provide within 3 months of PC
  • If not, employer must issue a 2-month notice stating intention to complete it
  • Employer may issue their own statement after that 2 months
  • Final statement can be positive or negative (e.g. Provisional Sum omission)
  • Final date for payment is 14 days from the due date: one month after either final statement, end of defects or notice of making good
  • If the matter of agreement goes to adjudication, arbitration or other, then the time period is frozen until completion of those proceedings, so long as relevant notices are issued
62
Q

Novation and consultant switch

A
  • Normally, the contractor will employ their own design team to take the Employer’s Requirements and develop these into the works on site – during this time, the contractor may look at ways to reduce more expensive details from the original design having quoted a price to build all the works
  • Under D&B, the client may wish to ensure that the design style undertaken by the architect pre-contract is carried through into post-contract.
63
Q

What is Novation?

A
  • Contract between the employer and architect will be replaced by a contract on identical terms between architect and contractor
  • Contractor replaces the employer as he accepts all obligations and liabilities formerly as the employer’s e.g. pay for the services
  • The architect will have no liability to the employer.
  • A deed of variation to the appointment is required to reflect this change (a novation agreement).
64
Q

Consultant switch

A
  • Original appointment (employer and architect) is brought to an end and new appointment (contractor and architect) is entered into (with agreement between all 3 parties).
  • Architect is still liable to the employer for breaches made during that time but not after the switch (with the exception of warranties).
  • This process is not the same as novation as the contractor could claim against the employer for pre-novation design team mistakes.
  • Employer hopes to retain control over the developing design – however the architect is no longer in contract with the employer
  • Communication between these parties should now go through the contractor
  • The quality is heavily dependent on how much the architect stands up to the contractor
  • Often it is better to retain the architect as an advisor for the employer to comment on the design submission process
65
Q

Typical requirements of completion?

A
Must be confirmed in contract; 
H&S file, 
Testing & Commissioning, 
Work Practically Complete, 
O&M, 
CW’s, 
Building Certificate, 
Planning Compliance, 
Structural Warranty, 
As Built DWGs, 
Keys.