L- Case Study Flashcards
How did you ensure a ‘fair and reasonable price’ was received?
A fair and reasonable price was achieved by scrutinising rates against industry standards. Internal data base of rates, conversations with suppliers and checks on measures were conducted to ensure the Client received a fair price.
Why was the Client’s preference to negotiate a tender? (3)
1) Positive previous projects experience
2) Early contractor involvement
3) Speed of programme
How did you advise you could ensure the tender was ‘fair and reasonable’? (5)
1) Checks against the PTE
2) Check against the previous projects rates, costs etc.
3) Test the market for certain elements such as MEP.
4) Request sufficient substantiation from the sub-contractors and suppliers.
5) Specialist areas such as catering equipment, lifts etc. request prices are obtained via consultants and include as a prime cost sum.
Who led the design process and generation of the ER’s?
Project Manager
Who set the budget of £16.6m?
Developed from early stage cost plans and design.
Did you have an understanding of this budget’s calculation?
Yes, from the earlier stage Cost Plans developed.
Apart from negotiation, did you consider any other ‘tender’ process?
I advised we should go competitive for cost reasons but the Client did not agree as programme was the main driver.
How did you ensure the tender reflected the required level of quality? (7)
There was a schedule of quality requested issued with the tender documents as if it were a competitive tender requesting certain documentation to be returned:
1) Key personnel and CV’s for the works.
2) Hotel project experience.
3) Risk registers
4) Programme of works
5) Traffic Management Plan
6) Modern Slavery Act
7) Insurance’s
Option 1 - On what basis did you advise the client the project would be delayed by a minimum of 3 months?
Working with the Project Manager we:
1) Listed out the activities required
2) reviewed previous programmes against actual time frames
3) Built a mini-programme of works should this option be viable.
Option 1 - What was the basis of advising 2% inflation increase?
Delaying the tender period for 3 months would mean the mid-point of construction would be delayed by 3 months. Reviewing the BCIS All in TPI I recalculated the inflation forecast, increasing costs by 2%.
Option 1 - How could you keep the contractor engaged in the process? (2)
- Piece-meal the tender process
- Involve them in the design (& pay the a fee to advise)
Option 1 - Did you consider an ECI with the contractor as part of this option?
No. I have learnt this could be an option next time.
Option 1 - How did you calculate the professional fee increase?
I had vision of the appointment documents and fee build up for each consultant. I estimated the additional time required for the delay and multiplied it by the day rates stated in the appointments.
Option 1 - What is the build up to the £25-£30K increase?
1) Interior Design team - £10,000
2) Architects - £5,000
3) PM - £3,500
4) QS - £4,000
5) Catering - £2,000
Option 2 - If you omitted this works, was there any enabling works that could have been retained in the package?
Yes - we could have retained screed works, partitioning works and some elements of the MEP first fix. This was considered but deemed to carry too higher risk of abortive works should these change.