Legal/Regulatory Compliance Flashcards

1
Q

What are the main sections of the Party Wall etc Act 1996?

A

Section 1 applies where it is proposed to erect a new wall at a boundary that is not already built on.

Section 2 concerns existing party structures, which include party walls, floors and partitions (that separate buildings or parts of buildings), party fence walls (essentially a boundary wall between lands in separate ownership which is built astride a boundary) and, in some instances, a neighbour’s independent property.

Section 6 can apply to excavations up to 6 m away from a building or structure on neighbouring land, subject to depth criteria which the Act sets out.

The three types of Notice are known, respectively as:

Section 1: Line of Junction Notice
Section 3 (for S2 works): Party Structure Notice
Section 6: Notice of Adjacent Excavation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Section 1 Notice / Line of Junction Notice ?

A

If you are planning to build a new wall either as a Party Wall or a Party fence wall (astride a boundary) subject to your neighbour’s consent, or up to the line of junction and wholly on your own land, a Section 1 Notice must be served.

One month notice must be given before the works commence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Section 3 Notice / Party Structure Notice?

A

If you are planning to cut into a Party Wall to insert flashings or a damp proof course, cut away chimney breasts or projections, raise, rebuild repair, underpin, expose the Party Wall to the weather.
or enclose upon a wall on or at the line of junction turning it into a Party Wall, in such cases a Section 3 Notice must be served.

Two months notice must be given for a section 3 Notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Section 6 Notice / Notice of Adjacent Excavation?

A

If you are planning to excavate within 3m of neighbour’s foundations to a lower depth, or within 6m to a lower depth than a line struck at 45 degrees down from the underside of the neighbour’s foundations, then a section 6 notice must be served.

One month notice must be given before work commences and in addition, plans and sections of the proposed works must be provided with the notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a build over agreement ?

A

A Build Over Agreement is required where building work is to take place close to (within 3 metres of) or over the route of an existing public sewer or drain.

Any work involving new foundations, underpinning, piling or basements requires approval of the Water Company prior to work commencing on site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the timescales attached to planning permission ?

A

Normally within 8 weeks however this can be requested to be extended. Which can be appealed but is a lengthy process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the timescales attached to building control ?

A

Normally 5 weeks but can be extended to 8 weeks by agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the timescales attached with a building notice ?

A

Works can start when the application has been accepted. This normally takes 2 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the time frame to make an appeal when a planning application is rejected?

A

3 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Are you aware of any new approved documents ?

A

Part O - Overheating

Part S - Electrical Car Charging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the main types of Building Regulations applications ?

A

Full plans
Building notice
Regularisation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of The Town and Country Planning Act 1990?

A

Takes account of the policies at national and regional level insofar as they affect the physical and environmental planning of its area; and. Provides the framework for local plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an enforcement notice ?

A

Enforcement Notices are legal documents that require certain action be taken to remedy a breach of planning control. They are issued where development has taken place without the correct planning permission or outside the conditions of a planning permission.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the aim of permitted development ?

A

Permitted development rights are a national grant of planning permission which allow certain building works and changes of use to be carried out without having to make a planning application. Permitted development rights are subject to conditions and limitations to control impacts and to protect local amenity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a lawful development certificate ?

A

Proof that the project/works do fall under permitted development and does not require planning permission. This can be useful for when the property is sold as proof the works were lawfully completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Approved Document L1A and L1B

A

Approved Document L1A is for the conservation of fuel and power in NEW dwellings.

Approved Document L1B is for the conservation of fuel and power in EXISTING dwellings.

17
Q

What are the advantages/disadvantages of using a Building Notice compared to a Full Plans Application?

A

There is no requirement for plans

Works can start within 48 hours of notice.

You do not receive the protection and reassurance that an approved notice would give you.

Complying with the Building Regulations is on your own shoulders.

Builder must be familiar with all the relevant regulations.

18
Q

What is the difference between an Approved Inspector vs. Building Control ?

A

Approved Inspectors are businesses which work in the private sector as an alternative to Local Authority Building Control (LABC).

19
Q

What is the main aim of the Party Wall Act?

A

To prevent delays to construction.
To enable an owner to undertake specific work
Protects neighbours

20
Q

When do the CDM Regulations apply?

A

The CDM regulations apply to every construction project.

21
Q

Under CDM, is a Principal Designer required on all projects?

A

No, a principle designer only needs to be appointed on construction projects involving more than one contractor.

22
Q

Who are the duty holders under the Control of Asbestos Regulations ?

A

The duty holder is the owner/ managing agent/ asset manager of the domestic premises Leaseholder depends on the extent of maintenance and repair obligations.

23
Q

What is a licence to alter ?

A

A legal agreement between the landlord and tenant in relation to amendments proposed to be carried out by the tenant that affects the demised parts of the property.

Consent cannot be unreasonably withheld from the tenant and should be provided in a written format. This is called a Licence To Alter (or Licence For Alterations) and it protects both the landlord and the tenant’s rights under the terms of the lease.

Once agreed, the LTA is appended to the lease.

24
Q

What is deemed to constitute building work under the Act?

A

Building work is defined as:

The erection or extension of a building.

The installation or extension of a service or fitting which is controlled under the regulations.

An alteration project that would affect the ongoing compliance relating to structure, fire or access and use of buildings.

The insertion of insulation into a cavity or the underpinning of the foundations.

25
Q

Who is responsible for ensuring compliance with the Building Regulations?

A

Ultimately it is the client. However, if a builder is appointed they will usually be responsible for ensuring works are carried out in line with the regulations.

But it is still the client that would be served with an enforcement notice.

26
Q

Why would you opt to use an approved inspector?

A

They are generally seen to be more responsive and open to giving advice than local authorities.

27
Q

Are there any time frames involved with the appointment of an approved inspector?

A

Approved inspectors need to serve an initial notice on the council and that has to be vaildated 5 days before the project commences.

28
Q

What enforcement options are available under building regulations?

A

Court and a fine.
Enforcement notice to alter or remove.
LA has authority to undertake the work itself and recover costs.

29
Q

What are the policies behind the NPPF?

A

Sustainable development.
Community decision making.
Town centre renewal.
Housing.

30
Q

What is a listed building?

A

A building with special architectural or historic interest.

31
Q

When would you need to apply for listed building consent?

A

A listed building may not be demolished, extended or altered without special permission from the local planning authority.