Contract Administration Flashcards
When would there be a requirement for a performance bond and what does it mean?
Performance bonds and guarantees are commonly used to ensure that contractors fulfil their obligations, offering a level of protection against risk and uncertainties.
The bond typically covers a percentage of the contract value. It is a common requirement for most major construction contracts, especially for public sector projects, as it provides reassurance to the project developer that the contractor can fulfil its contractual obligations.
What is a collateral warranty and how does it work?
A collateral warranty creates a contractual link between the two parties that are not linked via the contract. They are used as a supporting document to a primary contract where an agreement needs to be put in place with a third party outside of the primary contract.
Sometimes an contractor, or sub-contractor will need to warrant to a funder, tenant or purchaser that it has fulfilled its duties under a building contract.
Collateral warranties often contain obligations that affect the contractor, such as using materials of an appropriate quality, and carrying out work in a professional, workmanlike manner. It can also provide the third-party contractual rights enabling it to claim for losses which would not otherwise be recoverable.
Can you please expand on what the role of a Contract Administrator is?
Their responsibility is to administer construction contract between client and contractor, and carry out activities such as site visits, reports, variations, issue instructions, valuations and certificates etc.
Can you expand on your knowledge of the JCT Intermediate contract?
The intermediate contrcat allows for a number of additional elements in comparison to the JCT MW including:
Clerk or works
Sectional completion
Partial possession
The use of bonds.
Can you expand on your knowledge of the JCT Standard Building Contract?
The JCT SBC allows for additional elements to the intermediate contract such as:
Employers representative, listed sub contractors, retention bonds, variation and acceleration quotations, third party rights.
What contract allow for sectional completion and named sub contractors ?
Intermediate and standard building contract.
What JCT contracts allow for a clerk of works ?
JCT Standard building contract
JCT Intermediate Contract
Not JCT MW
What is a traditional lump sum contract ?
A lump sum contract is the traditional means of procuring construction, and involves a single ‘lump sum’ price for all the works being agreed before the works begin.
This means that the contractor is able to accurately price the works they are being asked to carry out.
What is a contract instruction and how would you deal with it ?
In simple terms, a contract variation occurs when the parties agree to do something differently from the way they originally agreed, whilst the remainder of the contract otherwise operates unchanged.
Such an agreement, if valid, would amount to a variation of the existing contract.
What is a letter of intent?
A letter of intent is a document outlining the understanding between two or more parties which they intend to formalise in a legally binding agreement.
Under JCT MW does the programme form part of the contract?
No however the contract promotes the use of one for reference generally.
What is the base date?
Base date: the base date is usually set at around the time of return of tenders.
It is a reference date from which changes in conditions can be assessed.
Does JCT MW make reference to a possession date?
MW16 does not refer to the contractor being given ‘possession’ of the site, but states simply that ‘The Works may be commenced’ on the date stated in the contract
What are the grounds for termination?
Insolvency
CDM breaches
Corruption of the contractor
Contractor failing to proceed regally and diligently
Employer failing to pay amounts
Either party can terminate is the works are suspended for a period of more than one month due to neutral events
Does JCT MW require a contract programme?
MW16 does not require the contractor to produce a programme.
Although there would be nothing to prevent such a requirement being included in the specification; a programme might be very useful to the contract administrator, particularly when monitoring progress and assessing extensions of time.