Contract Administration Flashcards

1
Q

When would there be a requirement for a performance bond and what does it mean?

A

Performance bonds and guarantees are commonly used to ensure that contractors fulfil their obligations, offering a level of protection against risk and uncertainties.

The bond typically covers a percentage of the contract value. It is a common requirement for most major construction contracts, especially for public sector projects, as it provides reassurance to the project developer that the contractor can fulfil its contractual obligations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a collateral warranty and how does it work?

A

A collateral warranty creates a contractual relationship between two parties that are not linked via the contract.

They are used as a supporting document to a primary contract where an agreement needs to be put in place with a third party outside of the primary contract.

It can also provide the third-party contractual rights enabling it to claim for losses which would not otherwise be recoverable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can you please expand on what the role of a Contract Administrator is?

A

Their responsibility is to administer construction contract between client and contractor, and carry out activities such as site visits, reports, variations, issue instructions, valuations and certificates etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can you expand on your knowledge of the JCT Intermediate contract?

A

The intermediate contract allows for a number of additional elements in comparison to the JCT MW including:
Clerk or works
Sectional completion
Partial possession
The use of bonds.
Nominated sub-contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can you expand on your knowledge of the JCT Standard Building Contract?

A

The JCT SBC allows for additional elements to the intermediate contract such as:

Employers representative, listed sub contractors, retention bonds, variation and acceleration quotations, third party rights.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What contract allow for sectional completion and named sub contractors ?

A

Intermediate and standard building contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What JCT contracts allow for a clerk of works ?

A

JCT Standard building contract
JCT Intermediate Contract
Not JCT MW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a traditional lump sum contract ?

A

A lump sum contract is the traditional means of procuring construction, and involves a single ‘lump sum’ price for all the works being agreed before the works begin.

This means that the contractor is able to accurately price the works they are being asked to carry out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a contract instruction and how would you deal with it ?

A

In simple terms, a contract variation occurs when the parties agree to do something differently from the way they originally agreed, whilst the remainder of the contract otherwise operates unchanged.

Such an agreement, if valid, would amount to a variation of the existing contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a letter of intent?

A

A letter of intent is a document outlining the understanding between two or more parties which they intend to formalise in a legally binding agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Under JCT MW does the programme form part of the contract?

A

No however the contract promotes the use of one for reference generally.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the base date?

A

Base date: the base date is usually set at around the time of return of tenders.

It is a reference date from which changes in conditions can be assessed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Does JCT MW make reference to a possession date?

A

MW16 does not refer to the contractor being given ‘possession’ of the site, but states simply that ‘The Works may be commenced’ on the date stated in the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the grounds for termination?

A

Insolvency
CDM breaches
Corruption of the contractor
Contractor failing to proceed regularly and diligently
Employer failing to pay amounts

Either party can terminate if the works are suspended for a period of more than one month due to neutral events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Does JCT MW require a contract programme?

A

MW16 does not require the contractor to produce a programme.

Although there would be nothing to prevent such a requirement being included in the specification; a programme might be very useful to the contract administrator, particularly when monitoring progress and assessing extensions of time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why is it important to define a completion date?

A

The significance of having a completion date is that it provides a fixed point from which damages may be payable in the event of non-completion.

Generally in construction contracts the damages are ‘liquidated’, and usually expressed as a rate per week of overrun.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the reason for an extension of time?

A

One important reason for an extension of time clause is to preserve the employer’s right to liquidated damages in the event that the contractor fails to complete on time due wholly or in part to some action for which the employer is responsible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

When must a contractor give written notice regarding an extension of time ?

A

Under MW16 the contractor must give written notice to the contract administrator - ‘If it becomes apparent that the Works will not be completed by the Date for Completion’ (cl 2.7)

The notice must be given regardless of the reason for the delay, i.e. whether it is caused by the employer, by a neutral event (such as bad weather) or by the contractor itself.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When would you issue a certificate of non completion?

A

If the completion date is not achieved, under JCT MW the certificate is not required but this failure should be recorded and circulated to all.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What triggers practical completion?

A

Under clause 2.9 the contract administrator is obliged to certify the date at which, in the contract administrator’s opinion, works have reached practical completion and the contractor has complied sufficiently with clause 3.9 (its CDM obligations, for example the supply of information required for the health and safety file).

It is implied that it will be a fair and reasonable exercise of professional judgment.

However, the contract administrator can certify practical completion where there are very minor items of work left incomplete, on de minimis principles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What does practical completion trigger?

A

Start of the rectification period.
release of half of the retention.
Employer takes responsibility of the site.
liability for liquidated damages ends.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is culpable delay ?

A

Culpable delay (sometimes referred to as ‘contractor delay’) on the other hand is a delay that is entirely the fault of the contractor. Where the contractor is culpable for a delay, they have no entitlement to an extension of time or loss and expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How and where would you process liquidated damages ?

A

May deduct damages from the amount due under the next certificate or reclaim the sum as a debt.

Under MW16 the contract administrator is not required to certify non-completion, but it may be prudent to record the failure in a letter to both the employer and the contractor.

Once the date for completion has passed, the contractor is said to be in ‘culpable delay’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What notice would you need to submit if you are planning to recoup liquidated damages form a payment?

A

A pay less notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are the key powers of the contract administrator JCT MW?

A

Agree variations
Issue a pay less notice on behalf of the client
issue certificates
certify practical completion making good defects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

At what point can you no longer issue variations under the contract?

A

Following practical completion/Final account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

How long does the contract administrator have to notify the contractor of the existence defects?

A

MW16 requires the contract administrator to notify the contractor of the existence of defects within 14 days of the end of the rectification period.

28
Q

What are prolongation costs?

A

Prolongation costs are the additional costs that a contractor has incurred as a result of the completion of the works being delayed by an event that is the responsibility of the other party (usually the Employer). Such events might include; failing to give the contractor possession of the site on the date specified in the contract; delays in giving instructions, and so on.

29
Q

Does JCT MW allow for advanced payments?

A

No, the contract would have to be amended to suite.

30
Q

What does a valuation include?

A

The value of the work properly executed and the value of materials and goods properly brought onto site.

31
Q

Can you allow for defective work to remain?

A

The contract administrator should obtain both parties’ agreement, and ensure that its proposed adjustment to the contract price is agreed and confirmed in writing.

The rates and prices for that work as set out in the contract can be used as a starting point for negotiation, but are not the only matters to be taken into consideration.

The contractor may prefer to correct the work, especially if the proposed reduction in the contract price is significant, and in general it cannot be denied the opportunity to do so.

32
Q

What risks are attached with including materials on site within interim payments?

A

The employer could be at risk, however, where materials have not yet been built in, even where the materials have been certified and paid for. The contractor might not actually own the materials paid for because of a retention of title clause in the sale of materials contract.

33
Q

What is a payment notice?

A

When the CA has not produced a payment certificate the contractor can produce a payment notice.

34
Q

What is direct loss and/or expense?

A

They are the additional costs or losses incurred by one of the parties, due to a default of the other party. In construction, this is normally the contractor claiming following a relevant matter that materially effects the progress of the works.

The contractor is entitled to recover that loss and expense in order to put him or herself back in the financial position that he or she would otherwise have been in.

35
Q

Why did you advise the client that time delays following receipt of tenders could result in contractors claiming increased costs?

A

Tenders generally come with a tender acceptance period, which can vary. Contractors may be willing to hold their price for an extended period.

However if a contractor is not appointed within the tender acceptance period, the client may face additional costs such as a percentage increase.

This was very common during covid, when costs of labour and materials were very volatile.

36
Q

What is the Construction Industy Scheme (CIS)?

A

The Construction Industry Scheme, or CIS, is a UK tax deduction scheme. It was designed to stop tax evasion among self-employed construction workers.

37
Q

What happens if a certificate is not paid, and a pay less notice is not served?

A

Interest - Interest accrues from the final date of payment, until payment is made. It is worked out as 5% over the Bank of England interest rate and can be recovered as a debt.

If payment is not made in line with the terms of the contract, the contractor can terminate the contract, after serving a default notice and waiting for a further failed payment window.

38
Q

Explain the the insurance provision 5.4A

A

5.4A refers to a joint names policy that is taken out by the contractor to cover all risks for the full reinstatement value of the works.

For use with new buildings.

39
Q

Explain the the insurance provision 5.4B and any issues you are aware of with this type of policy.

A

5.4B refers to a joint names policy taken out by the employer, to cover full costs of reinstatement, repair or replacement.

It is in respect of existing structures, contents and new works.

5.4B.1 Covers the existing structure and contents. - The employer essentially extends their existing policy to cover the contrator against any specific losses.

5.4B.2 Covers the works.

It can be difficult for employers to obtain insurance cover for 5.4B.1, especially if they are not the freeholder.

40
Q

Explain the the insurance provision 5.4C

A

5.4C is used when A or B are not suitable and parties agree to their own insurance policies.

It can be used for new and existing structures.

41
Q

Why is it important to include reference to Alternative 1 or 2?

A

It is a provision that prevents unofficial discussions in which people make agreements that provide both sides with advantages.

42
Q

What if the client tells you the LAD’s are to be £100,000 per week?

A

I would check the LAD figure is based on a genuine pre-estimate of financial loss and explain this would need to be substansiated.

I would explain that if the figure is not based on genuine financial loss, it is not likely to be enforced.

43
Q

What must have been in place before LD’s can be deducted?

A

A non-completion certificate.

A witholding notice.

44
Q

What happens when ‘time is at large’?

A

There is no set completion date and the contractor only has a duty to complete the works in a ‘reasonable time’.

LD’s cannot be claimed.

45
Q

What needs to be in place for you to include payments for materials on site?

A

The materials should be for the works.

They should be adequately protected.

Delivered to programme.

In a reasonable quantity.

46
Q

What is a retension of title clause?

A

Where the sub-contractor or supplier retains ownership of materials until they have been paid for.

47
Q

What is a fluctuating price contract?

A

Where the contract sum is adjusted for changes in the costs of materials and labour, as well as statutory contributions and taxes.

48
Q

What is the date for completion?

A

The date fixed and stated in the contract particulars.

49
Q

How is the date for completion, different to the completion date?

A

The completion date can be adjusted to take into account an EOT. The date for completion is the date mentioned in the contract.

50
Q

What is the difference between partial possession and sectional completion?

A

Sectional completion is a contractural obligation to hand over the section at the stated date, partial possession relies on the contractors consent to the employer to take possession of part of the works before practical or sectional completion.

51
Q

What are the consequences of a non-completion certificate?

A

The employer has the right to withold liquidated damages, as long as a witholding notice has been given.

52
Q

What are the different certificates you are aware of under the JCT contract?

A

Interim certificates.

Practical completion / sectional completion certificates.

Non completion certificates.

Certification of making good.

Final certificate.

53
Q

What are three ways that benefits can be transferred under JCT contracts?

A

Collateral warranties
Third party rights
Assignment

54
Q

What is assignment in contracts?

A

Where the rights and benefits of one contractural party are transferred to a third party.

55
Q

What is available to protect clients from sub-contractors failing?

A

Collateral warranties can:

Provide a direct link between the employer and subcontractor.

Give the employer a contractural remedy if subcontractors breach the contract.

56
Q

What is a bond?

A

A construction bond is a type of surety bond that protects against financial loss or disruptions that may occur if a contractor fails to complete a construction project or meet its specifications.

The three main types of construction bonds are bid, performance, and payment.

57
Q

What is insurance?

A

The transfer of risk in exchange for a premium.

58
Q

What does an LOI need to be legally binding?

A

It must have the basis of a simple contract (offer, acceptance and consideration) and both parties must intend to create legal relations.

59
Q

If an instruction was issued during the contract which involved the fabrication of a substantial amount of materials off site, would you pay for them as off site materials within the valuation?

A

There is no obligation for the client to pay for materials off site, unless it is identified in the contract.

However, in the scenario where the client wishes to pay for them, I would check with the client before including them in a certificate.

60
Q

What is your understanding of latent defects and what contractural issues are associated with them?

A

Latent defects are defects that are not readily identifiable upon inspection and only come to fruition some time after building completion, maybe years.

A claim for latent defects can only be brought if it is within the limitation period (so depends on how the contract was executed).

61
Q

What should the CA do if latent defects are discovered?

A

Issue an instruction as necessary to instruct the contractor what to do.

This can include compliance with a third party or opening up works to identify the defect.

62
Q

If the works or materials are found not to be in accordance with the contract, what options does the CA have available?

A

They can:

Instruct the contractor to remove all defective work, materials and goods at their own expense.

Notify the contrcator that the works and or materials can remain, subject to an appropriate deduction being made from the contract sum.

Issue instructions for variations that are necessary. If they are necessary, there should be no additional cost or extension of time given.

Instruct the contractor to open up and test further work to determine the extent of any non-compliance.

63
Q

What is a contractors deemed to have allowed for on the inclusion of a defined provisional sum?

A

Proper allowances for carrying out the work in their programme and preliminaries.

So are therefore not entitled to an EOT or extra prelims for carrying out the work.

64
Q

What is an undefined provisional sum?

A

As um included for work, where there is minimal of no information at the time of contract agreement.

65
Q

How can a provisional sum be expended?

A

The CA must issue an instruction for its expenditure.

66
Q

What is the event that does not allow a contractor to claim loss & expense?

A

If adverse weather delays the project, the contractor is usually entitled to an extension of time but not loss and expense.