Case Study Questions Flashcards
Given the last redecoration and repair were in 2012 what were the issues to contend with?
The main issues were the timber windows and the condition of the pointing. The windows at high level had been left for years, so has started to deteriorate significantly. A large number of sashes and cills required replacement, and an even greater number of windows required repair.
I also found that the pointing we in poor condition at high level, where in previous exercises, previous contractors had simply been overpointed. The pointing was failing, and I instructed for a large amount of raking out to a minimum 20mm depth and repointing.
What is a letter of intent?
A letter of intent is a document that outlines the intentions of parties involved in a construction project before they enter into a formal contract.
When and how are Letters on Intent used?
LOIs are often used as a precursor to an official contract.
They can be useful in situations where work needs to start urgently, but the contract wording is still being agreed.
They may be used to enable a supplier or contractor to pre-order materials or to create a site establishment.
However, parties should only use a Letter of Intent if they have no choice and should not use it as a way to avoid resolving negotiation hurdles.
Is a LOI binding?
Generally, a letter of intent is not binding in construction. They come in a variety of forms, with different clauses. A letter of intent only becomes binding if it meets certain conditions.
What are the implications if the contract falls through after the LOI?
Generally, If the works are cancelled at any stage prior to the execution of Contract Agreements, a letter of Inspection will often include the allowance for cancellation charges will be computed by the Contract Administrator on the basis that all reasonable abortive costs incurred can be substantiated and agreed will be reimbursed.
How did your inspection match up with the PMP report and costs?
Prior to undertaking my inspection, I reviewed the planned maintenance programme report that had been produced, previously.
Given the planned maintenance programme had been issued just over a year prior, the general condition of the building was very similar to what I had found during my inspection.
However, the timber windows and pointing, both appeared to have deteriorated between the planned maintenance inspection, and my inspection for the specification.
What is pre-construction information?
Pre-construction information is a vitally important part of construction planning, and is a legal requirement in the planning phase of every project.
At its core, pre-construction information involves collecting, collating, and communicating relevant and reasonably obtainable health and safety information before construction work begins.
The aim is to ensure that all parties involved in any project understand the risks and hazards associated with the work, enabling them to take steps to protect themselves and others.
They commonly include building plans and specifications, environmental assessments and safety assessments.
Why is Pre-construction information important?
A well compiled pre construction information pack will help to ensure safety by identifying potential risks and hazards, ensure compliance, allows for efficient planning and coordination, can help prevent costly delays by identifying risks and challenges and allows for effective risk management.
What is a Health and Safety file?
A Health and Safety File is a file full of health and safety information that serves as a legal record, benefiting both clients and end users.
It includes all of the information needed for future construction and maintenance work which includes cleaning, alteration, refurbishment and demolition. The information in the file is essential to those doing the work. It alerts them to the risks and helps them to decide how to work safely.
A Health and Safety File has to be prepared for all construction projects as part of CDM regulations.
Who is responsible for the Health and Safety file?
The responsibility for coordinating the File lies with the Principal Designer, but all duty holders are responsible for providing relevant information.
If the principal designer’s tenure finishes before the end of the project, the responsibility passes to the principal contractor. Once the project is complete, the file is passed to the client. However, health and safety should always be treated as a wider team effort, with everyone feeding into it where appropriate.
What is a section 20 notice?
A Section 20 notice (S20) is a notification from a landlord to leaseholders that they intend to carry out work or provide a service that the leaseholders will be responsible for paying towards.
Should you have allowed the two other contractors to submit tenders based upon your concerns?
I informed the client that I did not believe the contractors were suitable for the work at hand. However, the client insisted that they were included to satisfy the leaseholders who has recommended them.
On reflection, I would say that I should not have allowed the client to insist on their inclusion, as it was not beneficial.
Should you always accept the lowest tender?
No, accepting the lowest tender is not always the most suitable option, or one that provides the best value.
How do you keep contractors on side when submitting unsuccessful tenders?
I always inform contractors when they are unsuccessful and provide as much feedback as reasonably possible for them to consider.
I believe this helps to maintain a good relationship with the contractors, so they are not dissuaded from accepting tender invitations in the future.
How and when do you report to unsuccessful contractors on the tender bids?
Following an appointment of a contractor, I will write to each of the unsuccessful contractors informing them that they have not been successful on this occasion. I will be clear and respectful.
I provide some general feedback and try to be as positive as possible, as I believe this helps to maintain a good relationship with the contractors, so they are not dissuaded from accepting tender invitations in the future.
What information do you give unsuccessful tendering contractors?
I let the contractors know which areas of the tender, where they were competitive, and the areas where they were not. If they were particularly uncompetitive in any areas, I would also highlight this.