JCT contracts Flashcards

1
Q

liquidated damages notices

A

Under most JCT forms of building contract, before the employer can deduct or claim liquidated damages for delay, it must issue, first, a ‘WARNING NOTICE’.

To state that the employer may require payment of, or may withhold or deduct, liquidated damages;

and secondly a ‘DEDUCTION NOTICE’ confirming that it requires the contractor to pay liquidated damages and/or will withhold or deduct liquidated damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

CASE LAW

A

Grove Developments Ltd v S&T (UK) Limited

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Procurement type

A
  1. Traditional - client/designer & builder.
  2. Design and build - builder responsible for both design and building.
  3. Management.

NB: With management contracts, the client appoints a full professional team and a management contractor who is responsible for managing the carrying out of the works.
The management contractor does not directly undertake any of the construction work, which is broken down into packages and carried out by works contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

types of contract

A

Lump sum.
Measurement contracts.
Cost Plus contracts. (eg 20% on top for overheads and profit)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do I select contracts?

A

Depends on;
whether domestic or commercial
the cost of project.
LD’s to be applied?
Is there design, who is responsible?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Any amendments to JCT

A

Can have an impact on other sections, so beware and seek advise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

JCT contracts for smaller, more straightforward projects

A

seek to avoid, and DO NOT recognise, a need for any ancillary documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Are there any Resources to decide on type of contract?

A

Yes, JCT have a flowchart and document on appropriate selection of contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Intermediate Building Contract

A

This contract is more detailed and contains more extensive control procedures than the Minor Works Building Contract (MW).

Not suitable where the Contractor is to design discrete part(s) of the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Minor Works Building Contract

A

where the work involved is simple in character.

Not suitable where the Contractor is to design discrete part(s) of the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what is the extension of time clause?

A

Extension of time clauses are included in building contracts to prevent ‘time becoming at large’.

They give the CA power to extend time for delays which are the result of actions or inactions on the part of the employer or the architect as well as for other reasons for which neither employer nor contractor are responsible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

why would a contractor seek extension of time?

A

Limit LD’s & seek to recover loss of costs/expenses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who issues an extension of time?

A

The CA/ architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Issuing EOT

A

If there is a delay to completion caused by a Relevant Event, then the Architect/CA must give a notice in writing setting out a “fair and reasonable” extension of time.

The notice should be given as soon as the Architect/CA is able to estimate the length of the delay to the completion date.
If the Architect/CA does not consider that completion is delayed or that the cause was a Relevant Event, he does
not have to give a notice stating this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Reasons for an EOT?

A

Adverse weather conditions;
force majeure;
employer’s failure to give access to the site;
compliance with employer’s instructions;
acts of prevention by the employer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Record keeping?

A

Ensure good record keeping. ie minutes and information for stakeholders etc