F-1 Site Layout Flashcards
1
Q
Grading
A
surface of the ground on jobsite
- indicated by abbreviation NG
- finished grade marked by FG
*also means slope eg: 2%grade means earth drops 2mm for every 100mm
2
Q
Benchmark
A
randomly assigned and elevation of +100 meters
- points of jobsite higher then this benchmark are above 100m
- points lower are lower then 100 m
3
Q
Gridlines or Grid stakes
A
on sites where grading is required series of gridlines are set up to determine where soil must be removed or added
- levelled in one direction and numbered in the other
4
Q
Plumb down
A
measuring horizontal distances then using plumb bob to to set mark for stake
5
Q
Pythagorean theorem
A
A2 + b2 = c2 measure lengths then use this formula to find distances
6
Q
Site Layout method
A
- using setbacks determine two front corners of building
- from one front corner run tape length of building, then from other corner run tape diagonally tot hat point
- where the two tapes intersect is third corner
- measure both missing sides to find the fourth corner. use two tapes, one from third corner from back and second from the front corner mark where they intersect.
- measure diagonals and make sure its square.