ERP MM & PS Flashcards
MM module consists of 2 processes
- Procurement Process (Service/material)
- Inventory Management Process
Procurement Process deals with ___ procurement
1) centralized
2) decentralized
3) both
both
MM module master data
- Plants (SSA) & Storage locations – Name & Address
- Material Master (Maintained by MDM Centrally)
- Service Master – Maintained by MDM Team
New Requirement for Materials in Circle Inventory shall be created by ______ Team under Inventory Data Template.
MDM
MM module transactional data
- Inventory Data
- APO/PO Data
T-Code MMBE is for
1) Stock overview
2) Goods receipt/ Invoice Received
3) Display warehouse stock
4) Print out of Purchase order
Stock overview
T-Code MIGO
1) Stock overview
2) Goods receipt/ Invoice Received
3) Display warehouse stock
4) Print out of Purchase order
Goods receipt/ Invoice Received
T-Code MB52
1) Stock overview
2) Goods receipt/ Invoice Received
3) Display warehouse stock
4) Print out of Purchase order
Display warehouse stock
T-Code ME9F
1) Stock overview
2) Goods receipt/ Invoice Received
3) Display warehouse stock
4) Print out of Purchase order
Print out of Purchase order
Issue of materials from Store by
1) SDE(T)
2) SDE(store)
3) SDE (MM)
SDE (MM)
T-Code ME51N
1) Creating PR (Purchase Requisition)
2) Creating PO (Purchase Order)
Creating PR (Purchase Requisition)
T-Code ME21N
1) Stock overview
2) Creating PO (Purchase Order)
3) Display warehouse stock
4) Print out of Purchase order
Creating PO (Purchase Order)
T-Code F110
1) Stock overview
2) Goods receipt/ Invoice Received
3) Display warehouse stock
4) Invoice verification/ Vendor Payment
Invoice verification/ Vendor Payment
T-Code ME52N, T-Code ME53N
Create PR - [51N]
Modify PR - [52N]
Display PR - [53N]
While PR creation, after entering requisitioner name, system will ask for
1) profit center
2) cost center
3) tax code
4) vendor number
cost center
While PO creation, after entering vendor number, system will ask for
1) profit center
2) cost center
3) tax code
4) requisitioner name
Tax code
T-Code ME22N, T-Code ME23N
Create PO - [21N]
Modify/Amend PO - [22N]
Display PO - [23N]
Enter _____ in output device for printing
LOCL
For purchase of inventory materials, during MIGO, enter ______ for in where tab.
1) Location code
2) SLOC No.
SLOC No.
T-Code MB21
1) Creating reservations
2) Material Document List
3) Reservation List Inventory Management
4) Creation of Advance Purchase order or Contract
Creating reservations - INDENT in legacy system
T-Code MB51
1) Creating reservations
2) Material Document List
3) Reservation List Inventory Management
4) Creation of Advance Purchase order or Contract
Material Document List
T-Code MB90
1) Creating reservations
2) Material Document List
3) Reservation List Inventory Management
4) Print Material Document
Print Material Document
T-Code MB25
1) Creating reservations
2) Material Document List
3) Reservation List Inventory Management
4) Creation of Advance Purchase order or Contract
Reservation List Inventory Management
T-Code ME31K
1) Creating reservations
2) Material Document List
3) Reservation List Inventory Management
4) Creation of Advance Purchase order or Contract
Creation of Advance Purchase order or Contract
APO has three releases namely ______
R1,R2 and P1 releases.
APO P1 approval by _______
the accounts wing
T-Code ML81N
1) Creating reservations
2) Creation/Amendment of service Entry Sheet
3) Reservation List Inventory Management
4) Creation of Advance Purchase order or Contract
Creation/Amendment of service Entry Sheet
From the PS module we will get a _______ nunmber for issue of materials and a _____ number for external services for further processing in MM module.
Reservation No (RN),
Purchase Requisition number(PR)
From where __ Ends, MM starts
PS
From where PS Ends, ____ starts
MM
In SAP, WBS stands for __________
Work Breakdown Structure
In SAP, SES stands for ________
Service Entry Sheet
After PO is created, ______ is to be filled based on the Purchase order created
1) SES
2) WBS
3) Network
4) SKF
SES
_________ is a model of the Project that organizes Project tasks into a hierarchy. It forms the operative basis for planning Costs, Revenues, and Payments, as well as for Scheduling, and Budgeting.
1) SES
2) WBS
3) Network
4) SKF
WBS
A __________ represents the flow of Activities or Tasks in a Project.
1) SES
2) WBS
3) Network
4) SKF
Network
T-Code CN21,22,23
CN21: Create Project Network
CN22: Change Network
CN23: Display Network
T-Code CJ02
1) Change Network
2) Change WBS
3) Change PR
4) Change PO
Change WBS
T-Code CJ29
1) Project scheduling
2) Project Structure Overview
3) Post Actual SKF during the Project Execution phase
Project scheduling
T-Code CN41
1) Project scheduling
2) Project Structure Overview
3) Post Actual SKF during the Project Execution phase
Project Structure Overview
SKF stands for _____
Statistical Key Figure
T-Code KB31N
Post Actual SKF during the Project Execution phase
Status of a Network / WBS element is TECO means
Technically Complete
WBS status COMM means
Commissioning Done
WBS status PFC0 means
Provisionally fit for commissioning
WBS status DFC0 means
Declared fit for commissioning
WBS status MKOV means
Offered for taking over
WBS status TKOV means
Taken over
T-Code ZPS_CR
Attachment of Completion Report/ Management Certificate
T-Code CN41
1) Monitor Project Structure
2) Monitor Project Cost
3) Monitor Project Milestones
4) Project scheduling
Monitor Project Structure
T-Code CJI3
1) Monitor Project Structure
2) Monitor Project Cost
3) Monitor Project Milestones
4) Project scheduling
Monitor Project Cost
T-Code CN53
1) Monitor Project Structure
2) Monitor Project Cost
3) Monitor Project Milestones
4) Project scheduling
Monitor Project Milestones