EOP Terms Flashcards

1
Q

Large Oscillation Threshold

A

The peak-to-peak neutron flux oscillation amplitude which is equal to or less than 25%
Utilized to establish the condition beyond which boron injection must be initiated to provide reasonable assurance that rapidly growing oscillations are mitigated in a timely manner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Boron Injection Initiation Temperature
(Graph 5)
(BIIT)

A

The Boron Injection Initiation Temperature is defined to be the greater of either:

a. The highest Torus temperature at which initiation of boron injection will result in injection of the Hot Shutdown Boron Weight before Torus temperature exceeds the Heat Capacity Temperature Limit or,
b. The Torus temperature at which a Reactor scram is required by plant Technical Specifications.

Defines the point BEFORE which boron injected should be started, so that the Reactor will be shutdown prior to reaching the Heat Capacity Temperature Limit.

Upper left: For power less than decay heat (up to 2.21%) Torus heatup during Boron injection is independent of reactor power
Sloping: Torus heatup during boron injection is proportional to reactor power.
Bottom right: Torus Temperature of 110 F is when scram is required by Tech Specs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Maximum Subcritical Banked Withdrawal Position

MSBWP

A

The Maximum Subcritical Banked Withdrawal Position is defined to be the greatest banked rod position at which the Reactor will remain shut down under all conditions.

The Maximum Subcritical Banked Withdrawal Position for Hatch is: Position 02.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Hot Shutdown Boron Weight

HSBW

A

Defined to be the least weight of soluble boron which, if injected into the RPV and mixed uniformly, will maintain the Reactor shutdown under hot standby conditions.

This weight is utilized to assure the Reactor will be shut down irrespective of control rod position when RPV water level is raised to uniformly mix the injected boron.
Hot Shutdown Boron Weight for Hatch 2 is: 573 lbm or 44% SBLC Tank Level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cold Shutdown Boron Weight

CSBW

A

Defined to be the least weight of soluble boron which, if injected into the RPV and mixed uniformly, will maintain the Reactor shutdown under all conditions.

The weight is utilized to assure the Reactor will remain shut down irrespective of control rod position or RPV water temperature
The Cold Shutdown Boron Weight for Hatch 2 is: 1008 lbm or 30% SBLC Tank Level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Heat Capacity Temperature Limit
(Graph 2)
(HCTL)

A
  1. The Heat Capacity Temperature Limit (HCTL) is the highest Torus temperature from which emergency RPV depressurization will not raise:
    a. Torus temperature above the maximum temperature capability of the Torus and equipment within the Torus which may be required to operate when the RPV is pressurized, or
    b. Torus pressure above Primary Containment Pressure Limit,
    while the rate of energy transfer from the RPV to the containment is greater than the capacity of the containment vent.

Depressurizing the RPV when Torus temperature and RPV pressure cannot be maintained below the HCTL thus avoids failure of the containment and the equipment necessary for safe shutdown of the plant

98 inches: elevation of the bottom of the downcomer.
Pressure lines: Above these lines is unsafe. Torus cannot handle the head addition of the Reactor during a DB LOCA without exceeding PCPL.
193 inches: Elevation of the bottom of the ring header.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Primary Containment Pressure Limit

PCPL

A
  1. The Primary Containment Pressure Limit is defined by the EPG to be the lesser of either:
    a. The pressure capability of the containment, or
    b. The maximum containment pressure at which Vent Valves can be opened and closed to reject all decay heat from the containment, or
    c. The maximum containment pressure at which SRVs can be opened and will remain opened, or
    d. The maximum containment pressure at which valves can be opened and closed to vent the RPV.

The pressure capability of the containment is limiting at Hatch

Upper left hand slope: Slope caused by torus pressure instrument tap coverage at this torus level
Right hand vertical: Drywell level (103.5 ft) in which the highest containment vent (18 inch vents) capable of rejecting decay heat becomes covered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Maximum Pressure Suppression Primary Containment Water Level

MPSPCW

A

The highest primary containment water level at which the pressure suppression capability of the containment can be maintained.

Irrespective of the suppression chamber airspace volume, the pressure suppression feature of the primary containment can function as designed only when primary containment water level is below a certain limiting elevation. This elevation is a function of the containment type and is defined as is the primary containment water level corresponding to the bottom of the ring header.
For Plant Hatch - 193 inches for both Units.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Drywell Spray Initiation Limit
(Graph 8)
(DSIL)

A
  1. The Drywell Spray Initiation Limit is defined to be the highest Drywell temperature at which initiation of Drywell sprays will not result in a rapid pressure drop to below either:
    a. The Drywell below torus design differential pressure capability, or
    b. The high Drywell pressure scram setpoint.

This temperature is a function of Drywell pressure, and the Limit is utilized to preclude containment failure or
de-inertion following initiation of Drywell sprays.

Left hand up slope: Prevents de-inerting the DW through the Torus/Reactor building vacuum breakers.
Middle down slope: Prevent drywell failure by preventing exceeding the Drywell negative design pressure.
Flat line: The total mass of gasses that can be put into the Drywell is limited; above 25 psig the limit is constant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Minimum Drywell Spray Flow

MDSF

A

The Minimum Drywell Spray Flow (MDSF) is 5,000 gpm and is the lowest spray flow that assures uniform circumferential spray distribution within the drywell.

Utilized to provide direct cooling of core debris outside of the RPV and to delay or prevent containment failure once it has been determined that core debris has breached the RPV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Suppression Chamber Spray Initiation Pressure

SCSIP

A

The lowest suppression chamber pressure which can occur when 95% of the noncondensibles in the drywell have been transferred to the suppression chamber.

The SCSIP is utilized to preclude chugging which could cause failure of the downcomer vents.

  1. As steam collapses at the exit of the downcomers, the rush of water filling the void enters the downcomer pipe.
    a. This “chugging” of water in the downcomer places severe cyclic stresses at the junction of the downcomer and the vent header, and could cause cracks.
    b. Subsequently, any steam entering the vent header could leak freely into the suppression chamber airspace and pressurize the suppression chamber.
  2. Chugging can be avoided if noncondensibles are mixed with the steam. The
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Pressure Suppression Pressure
(Graph 7)
(PSP)

A

This pressure is a function of primary containment water level

Utilized to assure the pressure suppression function of the primary containment is maintained while the Reactor is at pressure or primary containment flooding is required.

Left vertical: Elevation of the bottom of the downcomer (98 inches)
Upward slope: Highest torus pressure that can occur without steam in the torus airspace. All the nitrogen is in the torus.
Right vertical: Elevation of the bottom of the ring header (193 inches)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

SRV Tail Pipe Level Limit
(Graph 6)
(SRVTPLL)

A

The SRV Tail Pipe Level Limit is the lesser of:

a. The Maximum Pressure Suppression Primary Containment Water Level
b. The highest Torus water level at which opening an SRV will not result in damage to the SRV tail pipe, tail pipe supports, quencher, or quencher supports.

The SRVTPLL is a function of RPV pressure. SRV operation with Torus water level above the SRVTPLL could damage the SRV discharge lines. This, in turn, could lead to containment failure from direct pressurization and damage to equipment inside the containment (ECCS piping, RPV water level instrument runs, torus-to-dry well vacuum breakers, etc.) from pipe-whip and jet-impingement loads.

Upper horizontal: Elevation of the bottom of th ring header (193 inches)
Right hand downslope: The highest torus water level at which opening an SRV will not result in damage to the SRV tail pipe, tail pipe supports, quencher, or quencher supports. If there is a break, the SRVs would discharge directly to primary containment air space

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Minimum RPV
Flooding Pressure
(MRPVFP)

A

The MRPVFP is defined to be the greater of:
a. The lowest differential pressure between the
RPV and the suppression chamber at which
steam flow through five SRVs is sufficient to
remove all decay heat from the core.
OR
b. The Minimum SRV Re-opening Pressure

Utilized to define the depressurized state of the RPV and to
assure sufficient liquid injection into the RPV to maintain
SRVs open and to flood the RPV to the elevation of the main
steam lines during the RPV flooding evolution when the
reactor is shutdown.
The Minimum SRV Re-opening Pressure is the greater value at
Hatch. Reactor pressure 50 psid above suppression chamber
pressure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Minimum Steam
Cooling Pressure
(MSCP)

A
1. This pressure represents one of the two
methods of steam cooling with or without
injection
a. It is used to assure adequate core
cooling when a cold shutdown rod
configuration cannot be assured and:
1) RPV Flooding is required, or
2) RWL cannot be maintained
above
-180 inches, or
3) Emergency depressurization is
required.
2. MSCP is defined to be the lowest RPV
pressure at which steam flow through open
SRVs is sufficient to preclude any clad
temperature from exceeding 1500°F even if the
Reactor core is not completely covered

Number of open SRVs and Minimum Steam Cooling pressure-
7 or more – 120 psig
6 – 140 psig
5 – 170 psig

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
Maximum Core
Uncovery Time
Limit
(Graph 4)
(MCUTL)
A

The Maximum Core Uncovery Time Limit
(MCUTL) is the greatest amount of time that the
clad temperature of the hottest fuel rod will not
exceed 1500°F with the core completely uncovered
and uncooled.

The MCUTL is a function of the time after reactor shutdown.
It is utilized to preclude fuel damage during recovery from the
RPV flooding evolution.
The limit is used to ensure fuel damage does not occur during
recovery from the RPV flooding evolution

Left vertical: Start time of 20 minutes after shutdown.
Up slope: Greatest amount of time that the clad temperature of
the hottest fuel rod will not exceed 1500 F with the core
completely uncovered and uncooled.
Horizontal line: Analysis complete 10 hours after S/D.

17
Q

Minimum Core
Flooding Interval
(MCFI)

A

The Minimum Core Flooding Interval is defined to
be the greatest amount of time required to flood the
RPV to the top of the active fuel with RPV pressure
at the Minimum RPV Flooding Pressure and at least
the Minimum Number of SRVs required for
emergency depressurization open.

The interval is used to assure that the Reactor core has been
covered before recovery from RPV flooding evolution is
initiated.

Number of Open SRVs with minimum core flooding interval
7 or more – 28 min
6 – 39 min
5 – 58 min

18
Q

End Flood Time

A

End Flood Time is a “clock” time that tells the
operator when the core should be covered during
RPV flooding.

The Minimum Core Flooding Interval is added to the time
flooding was started. The result is a time of day, as read on a
clock, which ensures flooding has gone on long enough to
cover the core.

19
Q

Level Restoration

Time

A

Level Restoration Time is the clock time equal to
the time injection was terminated plus the Maximum
Core Uncovery Time.

f RPV water level indication is not restored within the Level
Restoration Time Limit, injection to the RPV must be
reestablished to assure continued adequate core cooling.

20
Q

Minimum Steam
Cooling RPV
Water Level

A

Defined to be the lowest RPV water level at which
the covered portion of the Reactor core will generate
sufficient steam to preclude any clad temperature in
the uncovered portion of the core from exceeding
1500°F.

This water level is utilized to preclude fuel damage when RPV
water level is below the top of active fuel.
The Minimum Steam Cooling RPV Water Level for Hatch is:
-180 inches.

21
Q

Minimum Zero-
Injection RPV
Water Level
(MZIRWL)

A

Defined to be the lowest RPV water level at which
the covered portion of the Reactor core will generate
sufficient steam to preclude any clad temperature in
the uncovered portion of the core form exceeding
1800°F.

This Water Level is utilized to preclude significant fuel
damage and hydrogen generation for as long as possible.
The Minimum Zero-Injection RPV Water Level for Hatch is:
-195 inches.

22
Q
Minimum Debris
Retention Injection
Rate
(Graph 14)
(MDRIR)
A

The lowest RPV injection rate at which it is
expected that core debris will be retained in the RPV
when RWL cannot be determined to be above the
bottom of active fuel.

It is utilized to ensure that injection into the RPV is sufficient
to remove decay heat from core debris.

23
Q

RCIC and ECCS NPSH
(Graph 11)
(Graph 12)

A

The NPSH (Net Positive Suction Head) Limit is defined to be the highest Torus temperature which provides adequate net positive suction head for an RCIC or an ECCS pump taking suction on the Pool.

This temperature is a function of individual pump flow and Suppression Chamber overpressure (airspace pressure plus hydrostatic head over the RCIC or ECCS suction), and the limit is utilized to preclude pump damage due to cavitation.

Based on Suppression Chamber pressure, select appropriate curve.
At curve: Limit for the margin to saturation at the pump inlet
Right hand vertical: Max pump flow without cavitation.

24
Q

RCIC and ECCS Vortex Limits
(Graph 9)
(Graph 10)

A

The Vortex Limit is defined to be the lowest Torus water level above which air entrainment is not expected to occur in the RCIC or ECCS pump taking suction on the Pool.

This Torus water level is a function of RCIC or ECCS flow, and the limit is utilized to preclude RCIC or ECCS pump damage due to air entrainment. Separate limits are provided for RCIC and each ECCS suction/header, as appropriate.

Horizontal line: One pipe diameter above the elevation of the centerline of the pump suction inlet.
Slope up: threshold for air entrainment
Right hand vertical: Maximum possible flow through the suction.

25
Q

Maximum Normal Operating Temperature

A

The highest temperature expected to occur during normal plant conditions with all directly associated support and control systems functioning properly.

Plant Hatch limits are based on either Tech Spec isolation setpoints or maximum alarm setpoints of existing monitoring.

26
Q

Maximum Normal Operating Water Level

A

The highest water level expected to occur during normal plant operating conditions with all directly associated support and control systems functioning properly.

Plant Hatch limits are based on existing monitoring system alarm setpoints

27
Q

Maximum Normal Operating Radiation Level

A

The highest radiation level expected to occur during normal plant operating conditions with all directly associated support and control systems function properly.

Plant Hatch limits are based on existing monitoring system alarm setpoints plus a margin to prevent spurious alarms or to minimize required entries.

28
Q

Maximum Safe Operating Temperature

A

The maximum safe operating temperature level is defined to be the highest water level at which neither:

a. Equipment necessary for the safe shutdown of the plant will fail nor,
b. Personnel access necessary for the safe shutdown of the plant will be precluded.

These temperatures are utilized in establishing the conditions under which a Reactor shutdown, and possibly emergency depressurization, is required. Separate temperatures are provided for each secondary containment area.

29
Q

Maximum Safe Operating Water Level

A

The maximum safe operating water level is defined to be the highest water level at which neither:

a. Equipment necessary for the safe shutdown of the plant will fail nor,
b. Personnel access necessary for the safe shutdown of the plant will be precluded.

These water levels are utilized in establishing the conditions under which a Reactor shutdown, and possibly emergency depressurization, is required. Separate water levels are provided for each secondary containment area.

30
Q

Maximum Safe Operating Radiation Level

A

The maximum safe operating radiation level is defined to be the highest water level at which neither:

a. Equipment necessary for the safe shutdown of the plant will fail nor,
b. Personnel access necessary for the safe shutdown of the plant will be precluded.

This radiation level is utilized in establishing the conditions under which a Reactor shutdown, and possibly emergency depressurization, is required. Separate radiation levels are provided for each secondary containment area.

31
Q

Maximum Run Temperature (MRT).

A

The lowest value of the reference leg temperature that causes an instrument to start reading on scale when actual RPV level is at the instruments variable leg tap is called the MAXIMUM RUN TEMPERATURE.

32
Q

Minimum Indicated Level (MIL).

A

The highest indicated level attainable by raising reference leg temperature when actual level is at or below the variable leg tap is called the MINIMUM INDICATED LEVEL.

33
Q

What is the minimum number of SRVs required to emergency depress?

A

The Minimum Number of SRVs Required for Emergency Depressurization at Hatch is 5 SRVs (Both Units).

34
Q

What is the minimum SRV re-opening pressure/Decay Heat Removal Pressure?

A

The minimum SRV re-opening pressure/Decay Heat Removal Pressure for Hatch is 50 psig. (Both units)