List three functions of the GCU:
- Starter Cutoff
- Voltage Regulation
- Feeder Fault / Ground Fault Protection
To charge the aircraft battery with a ground power unit, the battery master switch must be in the BATT position: True/False
False
What is the minimum battery voltage required for a battery start?
24 volts minimum
What are the starter-generator start limitations:
Three starts in 30 minutes, with a 60 second rest between each start
List the items on the emergency busses for the CJ1:
- Nav / RMI 2
- Comm 1
- DG 2 (Compass) (internal invert)
- Cockpit Floodlights
What is the maximum amperage limitation for the starter-generators?
300 Amps
The crossfeed bus allows for logical grouping of items on the right and left main circuit breaker panels: True/False
Allow logical grouping of all CBs for a certain system together on one panel
(example: all engine instrument CBs on the right CB panel)
The battery disconnect switch located inside of the cockpit on the captain’s side oxygen panel can be utilize to disconnect the battery from the hot battery bus after shutdown: True/False
False
The BATT O’TEMP annunciator light will illuminate at what temperature?
145-160F on steady. +160, Flashing.
At what % N2 will the SG disconnect the start and begin generation?
At 45% N2, an integral tach-generator speed sensor circuitry will
discontinue starting and begin power generation.