Electrical Flashcards
How Many Switchboards are There?
10 Switchboards 1SG. 1SA, 1SB, 2SG, 2SA, 2SP, 2SB, 3SG, 3SA, 3SB.
SG and SA are located in Aux 1, Main 2, and 3 Gen
SB’s are in the GSE Shop, by the Post Office, and by 3MC’s Office
How Many Load Centers and How Would you Find Them?
22 Load Centers
First number is forward or aft. It goes from 1-5. If it’s 6, it’s on the ships superstructure
Second number, 1 and 3 are starboard, 2 and 4 are port
What are the Generators Rated at?
450 Volts
60Hz
3 Phases
4800 Amps
3000 Kw
0.8 Power Factor
What are ZEDS and why are they Important?
Zonal Electrical Distribution System. Lesson learned from the USS Cole. Allows the ship to take a hit on port side and transfer power load to starboard side.
What is the Function of the Automatic Load Shed?
Load Shed is designed to prevent overworking the generators.
Stage 1 occurs at 3000 Kw at 100 milli-seconds. Dumps all non-vital equipment.
Stage 2 occurs 5 seconds after stage 1 if the load does not decrease, this stage dumps A/C Units.
What Does EPCC Stand For and Where is it Located?
Electrical Plant Control Console. Located by PACC in CCS.
Where is 2SP Located?
Main 2, upper level.
How Many Shore Power Receptacles are There?
12
What is the Rating of the Shore Power Cables?
450 Volts
400 Amps
60 Hz
3 Phase
Where are the 400Hz Converters/Switchboards?
Fwd and Aft Power Conversion Rooms.
What is the Purpose of MBTs and ABTs?
Manual Bus Transfer and Automatic Bus Transfer allow the transfer of normal to alternate power.
What is the purpose of Degaussing?
Reduces the ships influence on earths magnetic field by sending direct current through cables wrapped around the ship. Keeps us magnetically invisible from magnetic seeking mines.
How Many Degaussing Coils are There?
4 Coils.
1) A-Coil 2) M-Coil 3) FP-QP Coil 4) FI-QI Coil
FI-QI: Forecastle Induced, Quarterdeck Induced
FP-QP: Forecastle Perm, Quarterdeck Perm
Where are the Degaussing Power Supply Units Located?
All 4 are in 2-240-0-Q, on the reefer deck.
Where are the Control Panels for Degaussing Located?
Main control is in CCS next to the EPCC
Remote control is on the bridge