Construction Operations Flashcards
Manday
Unit of work performed in 8 hours
Manday estimate formula
( MD= CSx WD x AF x DF)
Project Scope
a scope sheet includes general site info, description of the site and a environmental protection plan
Direct labor
labor that directly affects construction tasks
Indirect labor
Labor that supports construction.
Multiplier/ Delay factor
used to adjust the original MD estimate by taking production into account (DL=MDxWDxMExAF)
FAR
Field Adjustment Request
DCD
Design Change Directive
3 Phases for project Quality Control
Preparatory, Initial, Follow Up
CAS Sheet
Construction Activity Summary Sheet, outline of work to be done to include dates, mandays, description of work scope, and material needed, equipment needed.