Closeout - TASK 10: Participate in Facility Turnover/Project Closeout Flashcards

1
Q

List at least (5) examples of items that must be turned over to Public Works at or before BOD.

A

Typical items include, O&M Manuals, eOMSI data files, Record Drawings, extended warranty information, spare parts, extra material stock, keys, recorded training videos, turnover letters and others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

List at least (5) systems or equipment that the contractor provides training on for government
personnel.

A

Contractor is typically required to provide training for all types of mechanical and control systems, fire alarm and fire suppression systems, photovoltaic systems, generators, UPS systems, electronic security systems and others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

List the CPAR elements (evaluation areas) that the ET should provide input on when the COR is preparing the contractor’s evaluation.

A

The ET should provide input on the contractor’s performance with Safety, Quality, Schedule, and Management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly