Chapter 7 - Project Cost Management 8% Flashcards
The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.
Plan Cost Management
The process of developing an approximation of the monetary resources needed to complete project work.
Estimate Costs
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Determine Budget
The process of monitoring the status of the project to update the project costs and manage changes to the cost baseline.
Control Costs
Includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so the project can be completed within the approved budget.
Project Cost Management
An extension to the theory and practice of Earned Value Management (EVM).
It replaces the schedule variance measures used in traditional EVM (earned value - planned value) with ______ and actual time (AT). Using the alternate equation for calculating schedule variances ______ - AT, if the amount of ______ is greater than 0, then the project is considered ahead of schedule (the project earned more than planned at a given point in time).
Earned Schedule (ES)
A component of the project management plan and describes how the project costs will be planned, structured, and controlled.
Cost Management Plan
cE
Expected Cost
cE can be calculated with this triangular formula.
Triangular Distribution [cE = (cO + cM + cP) / 3]
cE can be calculated with this beta formula.
Beta Distribution [cE = (cO + 4cM + cP) / 6]
What two things make up the Work Package Cost Estimates?
Activity Contingency Reserve and Activity Cost Estimates
What two things make up the Control Accounts (amount)?
Contingency Reserve and Work Package Cost Estimates
What two things make up the Project Budget?
Management Reserve and Cost Baseline
Compares the performance measurement baseline to the actual schedule and cost performance.
Integrates the scope baseline with the cost baseline and schedule baseline to form the performance measurement baseline.
Develops and monitors 3 keys dimensions for each work package and control account.
- Planned Value (PV)
- Earned Value (EV)
- Actual Cost (AC)
Earned Value Analysis (EVA)
The authorized budget assigned to scheduled work to be accomplished for an activity or WBC component, not including management reserve.
Planned Value (PV)