Chapter 6 - Project Schedule Management 9% Flashcards
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Plan Schedule Management
The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Define Activities
The process of identifying and documenting relationships among the project activities.
Sequence Activities
The process of estimating the number of work periods needed to complete individual activities with the estimated resources.
Estimate Activity Durations
The process of monitoring the status of the project to update the project schedule and manage changes to the schedule baseline.
Control Schedule
This is a form of rolling wave planning based on adaptive life cycles, such as the agile approach for product development. The requirements are documented in user stories that are then prioritized and refined just prior to construction, and the product features are developed using time-boxed periods of work. This approach is often used to deliver incremental value to the customer or when multiple teams can concurrently develop a large number of features that have few interconnected dependencies.
Iterative Scheduling with a Backlog
This approach, typically used in a Kanban system, is based on the theory-of-constraints and pull-based scheduling concepts from lean manufacturing to limit a team’s work in progress in order to balance demand against the team’s delivery throughout. This does not rely on a schedule that was developed previously for the development of the product or product increments, but rather pulls work from a backlog or intermediate queue of work to be done immediately as resources become available.
On-Demand Scheduling
A component of the project management plans that describes how the project costs will be planned, structured, and controlled. It can establish the following:
- Units of measure: Each unit used in measurement is defined for each of the resources.
- Level of precision: The degree to which cost estimates will be rounded up/down (995.59 to 1000) based on the scope of the activities and magnitude of the project.
- Level of accuracy: The acceptable rant (+/-10%) used in determining realistic cost estimates is specified, and may include an amount for contingencies.
Cost Management Plan
A technique used for constructing a schedule model in which activities are represented by nodes and are geographically linked by one or more logical relationships to show the sequence in which the activities are to be performed. Consists of four types of dependencies or logical relationships:
- Finish-to-Start (FS)
- Finish-to Finish (FF)
- Start-to-Start (SS)
- Start-to-Finish (SF)
Precedence Diagramming Method (PDM)
A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start (FS)
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to Finish (FF)
A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-to-Start (SS)
A logical relationship in which a predecessor activity cannot finish until a successor activity has started.
Start-to-Finish (SF)
Legally or contractually required or inherent in the nature of the work. Sometimes referred to as hard logic or hard dependencies.
Mandatory Dependencies
Established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. Sometimes referred to as preferred logic, preferential logic, or soft logic.
Discretionary Dependencies
Involve a relationship between project activities and non-project activities (usually outside of the project team’s control).
External Dependencies
Involve a precedence relationship between project activities and are generally inside the project team’s control.
Internal Dependencies
The amount of time a successor activity can be advanced with respect to a predecessor activity. Often represented as a negative value for lag in scheduling software.
Lead
The amount of time a successor activity will be delayed with respect to a predecessor activity.
Lag
A graphical representation of the logical relationships, also referred to as dependencies, among the project schedule activities.
Project Schedule Network Diagram
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
Analogous Estimating
A technique for estimating in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Parametric Estimating