Chapter 23-Facility Design, Layout, And Organization Flashcards
WHat is the order of the four phases involved in designing a new strength and conditioning facility?
A. Pre design, construction, design
B. Pre design, design, construction, pre operation
B. Pre design, design, construction, pre operation
An operational plan should be created in which of the following phases?
A. Design phase
B. Construction phase
C. Pre design phase
C. Pre design phase
What is the recommended minimum distance between the floor and the bottom of mirrors on the walls?
A. 16 inches
B. 18 inches
C. 20 inches
C. 20 inches
WHich of the following is not a key consideration when determining the space requirements of a college strength and conditioning facility?
of athletic teams desiring to use the facility
What is the minimum recommended space between the ends of racks to provide room for spotters?
A.1 foot
B. 2 feet
C. 3 feet
C. 3 feet
The ___ phase is the first step in building a new facility. It should consist of a Need analysis, feasible study, and master plan.
Predesign phase
___ is the step in which the designers and experts collaborate and determine the needs of the program
Needs analysis
The second part of the pre design phase. Should analyze strengths, weaknesses and opportunities. SWOT
Feasibility study
The general plan for all phases of the new facility
Master plan
Last step of the pre design phase is hiring an
Architect
The ___ phase of the second phase in the process of building a new facility
Design
The period of time from the beginning of construction to the end. The longest phase of the process
Construction phase
Consist of the final steps before the facility can open . Interior decor and hiring staff
Preoperation phase
During the pre operation phase it is vital to create a plan that will make opening the facility easy, for example cleaning and maintenance duties.
True
FOrm committee
FEasilibility study
Needs analysis
FIrst steps
Create operational plan
Remodel or upgrade
FInalize design and decorations
Second steps
Arrange equipment
Create employee duties
Hire/keep staff
Third steps
How many athletes will be using the facility?
Size and scheduling depends on this
WHat are the training goals for the athletes coaches and administration?
Determines equipment chosen
What are the demographics of the athletes?
Determines type of equipment
What will the training experience of the athletes be?
Help with training plans
How will the athletes be scheduled?
More difficult parts. Determines number of staff scheduled layout and design
Ceiling height should be?
12-14 feet
Flooring should include?
Turf- ground based movements
Rubber
Wood
Lighting should be?
50-100 lumens, use natural light
Temp range 68-78 degrees
Mirrors
Should be placed at least 6 inches from eqipment
____ and __ are top priorities when one is deciding on placement of equipment in a facility.
Safety and function