Chapter 13 Flashcards

1
Q

Describe project stakeholder management.

A

It includes the processes required to identify the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe the identify stakeholders process.

A

This is the process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The process of developing approaches to involve project stakeholders based on their needs, expectations, interests and potential impact on the project.

A

Plan stakeholder engagement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The process of communicating and working with stakeholders to meet their needs, expectations, address issues, and foster appropriate stakeholder engagement involvement.

A

Manage stakeholder engagement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The process of monitoring project stakeholder relationships and tailoring strategies for engaging stakeholders through the modification of engagement strategies and plans.

A

Monitor stakeholder engagement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When should project stakeholder identification and engagement commence ?

A

As soon as possible after the project charter has been approved, the project manager has been assigned and the team begins to form.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are tailoring considerations for project stakeholder management?

A

Stakeholder diversity
Complexity of stakeholder relationships
Communication technology

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Describe agile/adaptive project stakeholder management.

A

Adaptive teams engage with stakeholders directly rather than going through layers of management.
There are regular interactions with the stakeholder community.
Aggressive transparency is promoted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding the interests, involvement, interdependencies, influence and potential impact on project success.

A

Identify stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Describe when the identify stakeholder process is occurs.

A

Prior to or at the same time the project charter is developed and approved.

At the start of each phase and when a significant change in the project or organization occurs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does the business case say about stakeholders?

A

It identifies an initial list of stakeholders affected by the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does the benefits management plan say about stakeholders?

A

It identifies the individuals and groups that will benefit from the delivery of the outcomes of the project and are thus considered as stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What’s unique about project document inputs for the identify stakeholder process?

A

It is unlikely that any project documents will be an input for the initial stakeholder identification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are data gathering techniques used in the identify stakeholders process?

A

Questionnaires and surveys

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Describe brain writing?

A

A refinement of brainstorming that allows individual participants time to consider the question(s) individually before the group creativity session is held. The information can be gathered in face-to-face groups or using virtual environments supported by technical.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are stakeholder “stakes”?

A

Their roles on the project

17
Q

What are some types of stakeholder stakes?

A
Interest
Rights
Ownership
Knowledge 
Contribution
18
Q

Power/interest grid
Power/influence grid
Impact/influence grid

Is an example of what type of data representation?

A

A type of stakeholder mapping

This is used for small or simple projects

19
Q

Describe a salience model.

A

This data representation stakeholder map describes classes of stakeholders based on assessments of their power, urgency, legitimacy/proximity.

Useful for large complex projects.

20
Q

Describe the directions of influence.

A

Upward ( senior management of the performing org or customer org, sponsor and steering committee)

Downward (the team or specialists contributing knowledge or skills in a temporary capacity)

Outward (stakeholder groups and their representatives outside the project team, such as suppliers, government departments, the public, end-users, and regulators)

Sideward (the peers of the project manager, such as other project managers or middle managers who are in competition for scarce project resources or who collaborate with the project manager in sharing resources or information)

21
Q

When is stakeholder prioritization used?

A

when stakeholders are changing frequently

when there is a large number of stakeholders

when relationships between the project team and stakeholders are complex.

22
Q

What is the main output of the identify stakeholders process?

A

The stakeholder register

23
Q

What is included on the stakeholder register ?

A

Identification information
(Name, org position, contact details, location, role on the project)

Assessment information (major requirements, expectations, potential for influencing project outcomes, and the phase of the project life cycle where the stakeholder as the most influence)

Stakeholder classification
(Internal/external, impact/influence/power/interest, upward/downward...)
24
Q

During the first iteration of identify stakeholders are there Change request?

A

No (I.e. the first iteration is when the project charter is being developed)

25
Q

Much of the information about the relative power, interest, and engagement of stakeholders is based on …. and is recorded onto the?

A

Assumptions

Assumption log

26
Q

The process of developing approaches to involve project stakeholders based on their needs, expectations, interests, and potential impact on the project.

A

Plan stakeholder engagement

27
Q

What data gathering technique might be used in the plan stakeholder engagement process?

A

Benchmarking

I.e. project is benchmarked against similar projects and orgs and world class projects and orgs.

28
Q

How might root cause analysis be used in the plan stakeholder engagement process ?

A

It can be used to identify underlying reasons for the level of support of the project stakeholders in order to select the appropriate strategy to improve their level of engagement.

29
Q

What decision making technique is used in the plan stakeholder engagement process?

A

Prioritization/ranking

30
Q

What data representation techniques are used in the stakeholder engagement process?

A

Mind mapping

Stakeholder engagement assessment matrix

31
Q

This supports comparison between the current engagement levels of stakeholders and the desired engagement levels required for successful project delivery.

A

Stakeholder engagement assessment matrix

32
Q

What are some ways stakeholder engagement levels might be classified?

A
Unaware 
Resistant
Neutral
Supportive 
Leading