Chapter 11 Flashcards

1
Q

What is the objective of project risk management?

A

Increase the probability and/or impact of positive risks and to decrease the probability and/or impact of negative risks, in order to optimize the chances of project success.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The process of defining how to conduct risk management activities for a project.

A

Plan risk management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The process of identifying individual project risks as well as sources of overall project risk, and documenting their characteristics.

A

Identify risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics

A

Perform qualitative risk analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The process numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objective.

A

Perform quantitative risk analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.

A

Plan risk responses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The process of implementing agreed-upon risk response plans.

A

Implement risk responses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.

A

Monitor risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In order to create value while balancing risk and reward organizations should choose to take project risk in what type of manner?

A

Controlled and intentional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the two different levels of project risks defined in projects?

A

Individual project risk

Overall project risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

An uncertain event or condition that if it occurs, has a positive or negative effect on one or more project objectives.

A

Individual project risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The effect of uncertainty on the project as a whole, arising from all sources of uncertainty including individual risks, representing the exposure of stakeholders to the implications of variations in project outcome, both positive and negative.

A

Overall project risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Individual risk and overall project risk can have both a positive and negative effect on project objectives? True or false.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What’s another name for negative risks?

A

Threats

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What’s another name for positive risks?

A

Opportunities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Describe management of overall project risks?

A

It aims to keep project risk exposure within an acceptable range by reducing drivers of negative variation, promoting drivers of positive variation and maximizing the probability of achieving overall project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

This aims to exploit or enhance positive risks while avoiding or mitigating negative risks.

A

Project risk management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

This expresses the degree of acceptable variation around a project objective.

A

Risk thresholds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How should project risk management processes be conducted?

A

Iteratively

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are two types of non-event risks?

A

Variability risks

Ambiguity risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are variability risks? What’s an example?

A

Uncertainty about some characteristics of a planned event, activity or decision.
I.e. errors found during tests might be higher lower, unseasonal weather conditions etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are ambiguity risks ? What’s an example?

A

When uncertainty exists about what might happen in the future.
I.e. future developments in regulatory frameworks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How can variability risks be addressed?

A

By using Monte Carlo analysis, with the range of variation reflected in probability distributions, followed by actions to reduce the spread of possible outcomes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How are ambiguity risks managed?

A

Defining areas where there is a deficit of knowledge or understanding, then filling the gap by obtaining expert external inout or benchmarking best practices.

Incremental development, prototyping, or simulation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are emergent risks?

A

The unknowable-unknowns

Risks that can only be recognized after they have occurred.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What can tackle emergent risks?

A

Project resilience

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What’s integrated risks management?

A

A coordinated approach to enterprise-wide risks management with alignment and coherence in the way risk is managed across all levels of an enterprise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What are some tailoring considerations for project risk management?

A

Project size
Project complexity
Project importance
Development approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

How is risk handled in agile/adaptive environments?

A

Risks are reviewed at each iteration and cross functional teams help to accelerate knowledge sharing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

The process of defining how to conduct risk management activities for a project.

A

Plan risk management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

When should the plan risk management process begin?

When should it be completed?

A

When the project is conceived.

Early in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

How does the various project management plans from different processes effect the plan risk management processes?

A

They need to be taken into consideration when making the project risk management plan to ensure consistency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

How does the stakeholder register effect plan risk management?

A

It provides stakeholders attitude toward risk on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What elements can be included in a risk management plan?

A
Risk strategy 
Methodology 
Roles & responsibilities 
Funding 
Timing 
Risk categories 
Stakeholder risk appetite 
Definitions of risk probability and impacts 
Probability and impact matrix 
Reporting formats 
Tracking
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

This defines specific approaches, tools, and data sources that will be used to perform risk management on the project.

A

Methodology

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What is RBS?

A

Risk break down structure: a hierarchical representation of potential sources of risk.
It helps to identify risks and categorize them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

How should stakeholder risk appetite be expressed?

A

As measurable risks thresholds around each project objective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

This matrix allows the relative priority of individual risks to be evaluated within each priority level.

A

Probability and impact matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

This documents how risk activities will be recorded and how risk management processes will be audited.

A

Tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

The process of identifying individual project risks as well as Sources of overall project risk, and documenting their characteristics.

A

Identify risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Who should be encouraged to identify individual project risk?

A

All stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

True or false a consistent format should be used for risk statements?

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What’s looked for in agreements when identifying risk?

A

If the project uses an external procurement of resources the agreement info can present threats or opportunities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Procurement documentation should be reviewed for risks as it is updated. True or false?

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

A list of items, actions, or points to be considered.

It is often used as a reminder.

A

Checklist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

What are data gathering techniques the identify risk process?

A

Brainstorming
Checklists
Interviews

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

What are data analysis techniques for the identify risk process?

A

Root cause analysis
Assumption and constraint analysis
SWOT Analysis
Document Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

This is used to discover underlying causes that lead to a problem, and develop preventive action.

A

Root cause analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

With this you can start with a problem statement to identify threats or a benefit statement to identify opportunities.

A

Root cause analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

This explores the validity of assumptions and constraints to determine which pose a risk to the project.

A

Assumptions and constraint analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

A predetermined list of risk categories that might give rise to individual project risks and that could also act as sources of overall project risk.

A

Prompt lists

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

What can be used as a prompt list for individual project risks?

A

The lowest level of the risk breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

What are some frameworks used for identifying sources of overall project risks?

A

Pestle ( political, economic,social, technological, legal, environmental)
Tecop (technical, environmental, commercial, operational, political)
Vuca (volatility, uncertainty, complexity, ambiguity)

54
Q

What is the name of the specialized meeting used to undertake risk identification.

A

Risk workshop

55
Q

This captures details of identified individual project risks.

A

Risk register

56
Q

Once the identify risk process is completed the content of the risk register may include?

A

List of identified risks
Potential risk owners
List of potential risk responses

57
Q

This may be used to distinguish risks from their causes and their effects.

A

A structured risk statement

58
Q

What is each individual project risk given on the risk register?

A

A unique identifier

59
Q

This presents information on sources of overall project risk, together with summary information on identified individual project risks.

A

Risk report

60
Q

The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.

A

Perform qualitative risk analysis

61
Q

The key benefit of this process is that it focuses efforts on high priority risks.

A

Perform qualitative risk analysis

62
Q

Are the perform qualitative risk analysis assessments subjective , if yes how so?

A

Yes they are subjective because they are based on perceptions of risk by the project team and other stakeholders.

Therefore if facilitators are used they must address biases of the team.

63
Q

When is the perform qualitative risk analysis process conducted in an agile development environment?

A

Before the start of each iteration

64
Q

What process establishes the relative priorities and risk owner of individual project risks for plan risk responses?

A

Perform qualitative risk analysis

65
Q

What are some data analysis techniques used in the perform qualitative risk analysis process?

A

Risk data quality assessment

Risk probability and impact assessment

Assessment of other risk parameters

66
Q

Describe what a risk data quality assessment does? What is it?

A

It evaluates the degree to which the data about individual project risks is accurate and reliable as a basis for qualitative risk analysis.

A questionnaire of various individual project risks characteristics are used.

67
Q

This data analysis technique considers the likelihood that a specific risk will occur.

A

Risk probability assessment

68
Q

This data analysis technique considers the potential effect on one or more project objectives.

A

Risk impact assessment

69
Q

How are risk probability and Impact assessments conducted?

A

Through interviews or meetings.

70
Q

How are risks with low probability and impact included within the risk register?

A

As part of a watch list for future monitoring

71
Q

What other risk parameters might be assessed when prioritizing individual project risks?

A
Urgency 
Proximity 
Dormancy 
Manageability 
Controllability 
Detectability
Connectivity 
Strategic impact 
Propinquity
72
Q

Risk may be categorized into what categories?

A

Source
Area of project affected
Common root causes

73
Q

How might data be represented in the perform qualitative risk analysis process?

A

Probability and impact matrix

Hierarchical charts

74
Q

A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.

A

Probability and impact matrix

75
Q

What is an example of a hierarchical chart?

A

A bubble chart

76
Q

This displays three dimensions of data, where each risk is plotted as a disk (bubble), and the three parameters are represented by the x-axis value, the y-axis, and the bubble size.

A

Bubble chart

77
Q

The process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives.

A

Perform quantitative risk analysis

78
Q

Is quantitative risk analysis required for every project?

A

No

79
Q

Describe the type of project that might use quantitative risk analysis.

A

Large or complex projects

80
Q

What does quantitative risk analysis usually require?

A

Specialized risk software

Expertise in the development and interpretation of risk models

81
Q

What are some tools and techniques used for perform quantitative risk analysis?

A

Expert judgement
Data gathering-Interviews
Interpersonal and team skills-facilitation
Representations of uncertainty
Data analysis -simulation, sensitivity analysis, decision tree analysis, influence diagrams

82
Q

What are some forms of probability distributions used for representations of uncertainty in quantitative risk analysis models?

A
Triangular 
Normal
Lognormal
Beta
Uniform
Discrete distributions
83
Q

The use of this in a model is when optional activities are added to the model to represent the time and /or cost impact of the risk should it occur, and the chance that these activities actually occur in a particular simulation run matches the risks probability.

A

Probabilistic branches

84
Q

What’s used in a model to represent when risk are related?

A

Correlation

85
Q

How are simulations typically performed?

A

Using a Monte Carlo analysis

86
Q

This type of analysis determines which element of the risk model have the greatest effect on the project critical path.

A

Criticality analysis

87
Q

This type of analysis helps to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes.

A

Sensitivity analysis

88
Q

This presents the calculated correlation coefficient for each element of the quantitative risk analysis model that can influence the project outcome.

A

Tornado diagram

89
Q

What’s a typical display of a sensitivity analysis?

A

Tornado diagram

90
Q

This is used to support selection of the best of several alternative courses of action.

A

Decision tree analysis

91
Q

This diagram represents a project or situation within the project as a set of entities, outcomes, and influences, together with the relationships and effects between them.

A

Influence diagrams

92
Q

What is included on the risk report after the performance of quantitative risk analysis?

A

Assessment of overall project risk exposure
Detailed probabilistic analysis of the project
Prioritized list of individual project risks
Trends in quantitative risk analysis results
Recommended risk responses

93
Q

What are the two key measures of overall project risk in the assessment of overall project risk exposure?

A

Chances of project success

Degree of inherent variability remaining within the project at the time the analysis was conducted

94
Q

The process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risk.

A

Plan risk responses

95
Q

Who should make plans to address individual project risk?

A

The nominated risk owner

96
Q

Risks that arise as a direct result of implementing a risk response.

A

Secondary risk

97
Q

What are the five alternative strategies considered for dealing with threats?

A
Escalate 
Avoid
Transfer
Mitigate 
Accept
98
Q

What type of threats are escalated?

A

Threats that are outside the scope of the project or that the proposed response would exceed the project manager’s authority.

99
Q

This is when the project team acts to eliminate the threat or protect the project from its impact.

A

Avoid

100
Q

What type of strategy could be appropriate for a high-priority threat with a high-probability of occurrence and a large negative impact.

A

An avoid strategy

101
Q
What are the following examples of?
Removing the cause of a threat
Extending the schedule
Changing the project strategy 
Reducing scope
A

The avoid strategy

102
Q

This involves shifting ownership of a threat to a third party to manage the risk and to bear the impact if the threat occurs.

A

Transfer

103
Q

This strategy for dealing with threats often involves payment of a risk premium to the party taking on the threat.

A

Transfer

104
Q

This type of risk strategy can be achieved by the use of insurance, performance bonds, warranties, guarantees, etc.

A

Transfer

105
Q

Describe what it Men’s to mitigate a risk.

A

Take action to reduce the probability of occurrence and/or impact of a threat.

106
Q

Adopting less complex processes, conducting more tests, or choosing a more stable seller are examples of what risk strategy?

A

Mitigation

107
Q

This happens when the existence of a threat is acknowledged, but no proactive action is taken.

A

Acceptance

108
Q

What type of threats and opportunities might be accepted?

A

Those of low priority

109
Q

What are the two types of acceptance and provide an example of each.

A

Active: contingency reserve

Passive:periodic review of the threat to ensure it does not change significantly

110
Q

What are the five alternative strategies that may be considered for dealing with opportunities?

A
Escalate 
Exploit 
Share 
Enhance 
Accept
111
Q

Are escalated opportunities monitored by the project team after escalation?

A

No, although they may be recorded in the risk register for information

112
Q

Describe the exploit strategy.

A

This strategy seeks to capture the benefit associated with a particular opportunity by ensuring that it definitely happens, increasing the probability to 100%. It is selected for high-priority opportunities where the organization wants to ensure that the opportunity is realized.

113
Q

This plan risk response strategy involves transferring ownership of an opportunity to a third party so that it shares some of the benefit if the opportunity occurs.

A

Share.

114
Q

What’s some ways a project might share a risk opportunity?

A
By Forming;
risk sharing partnerships 
Teams
Special-purpose companies
Joint ventures
115
Q

This plan risk response strategy is used to increase the probability and/or impact of an opportunity.

A

Enhance

116
Q

This risk response strategy acknowledges an opportunity exist but no proactive action is taken.

A

Accept

117
Q

Describe active and passive opportunity acceptance.

A

Active- establish a contingency reserve

Passive-periodic review of the opportunity to ensure it does not change significantly

118
Q

What do you call plans that are designed for use only if certain events occur?

They include identified triggering events that set the plans in effect.

A

Contingency plans aka fall black plans

119
Q

Can the same risk responses used to deal with individual project risks be applied to overall project risk ?

A

Yes

120
Q

Removal of high risk elements of scope from the project is an example f what?

A

Using the avoid strategy for overall project risk

121
Q

The process of implementing agreed-upon risk response plans.

A

Implement risk responses

122
Q

The process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.

A

Monitor risks

123
Q

In order to make sure the project team is aware of the current level of risk exposure what process is used?

A

Monitor risk

124
Q

What data analysis techniques can be used for the monitor risk process?

A

Technical performance analysis

Reserve analysis

125
Q

This requires the definition of objective, quantifiable measures of technical performance, which can be used to compare actual results against targets.

A

Technical performance analysis

126
Q

This compares technical accomplishments during project execution to the schedule of technical achievement.

A

Technical performance analysis

127
Q

This compares the amount of the contingency reserves remaining to the amount of risk remaining at any time in the project in order to determine if the remaining reserve is adequate.

A

Reserve analysis

128
Q

This may be used to consider the effectiveness of the risk management process.

A

Risk audit

129
Q

Describe a risk review.

A

They are scheduled regularly and should examine and document the effectiveness of risk responses in dealing with overall project risk and with identifies individual project risks.

130
Q

This includes information on how project risk management is performing by comparing the individual risks that have occurred with the expectation of how they would occur.

A

Work performance information