Ch8 - Closing Process Group Flashcards
What process group consists of the process(es) performed to formally complete or close a project, phase, or contract?
Closing Process Group
The key benefits of —– process are the project or phase information is archived, the planned work is completed, and organizational team resources are released to pursue new endeavors?
Close project or phase
When closing a project, the project manager reviews the project management plan to ensure ….. and …..?
2 things
- all project work is complete
- project has met its objective
What are the project management plan components used in the Close Project or Phase process?
All components of the project management plan may be inputs to this process.
Assumptions log, basis of estimates, change log, issue log, lessons learned register, milestone list, project communications, quality control measurements, quality reports, requirements documentation, risk register and risk report are all…
Examples of some (not all) project documents that may be inputs for the Close Project or Phase process
Any project documents that may be updated as a result of this process include but are not limited to:
worded oddly, just one document noted
lessons learned register