Ch5 - Planning / Estimate Activity Durations (5.9) Flashcards

1
Q

What is the key benefit of the Estimate Activity Durations Process?

A

It provides the amount of time each activity will take to complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the process of estimating the number of work periods needed to complete individual activities with estimated resources?

A

Estimate Activity Durations Process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When is the Estimate Activity Durations Process performed?

A

Throughout the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 4 general inputs to the Estimate Activity Durations Process?

A
  1. Project Management Plan
  2. Project Documents
  3. Enterprise Environmental Factors
  4. Organizational Process Assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The Schedule Management Plan and the Scope Baseline are included in what general input to the Estimate Activity Durations Process?

A

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity attributes, activity list, assumption log, lessons learned register, milestone list team assignments, resource breakdown structure, resource calendars, resource requirements and risk register are all part of what general input to the Estimate Activity Durations Process?

A

Project Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Name 4 estimating techniques are used in the Estimate Activity Durations Process?
(APTB)

A
  1. Analogous estimating
  2. Parametric estimating
  3. Three-point estimating
  4. Bottom-up estimating
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Alternative Analysis and Reserve Analysis are part of what general technique used in the Estimate Activity Durations Process?

A

Data Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the difference between Alternative Analysis and Reserve Analysis?

A

Alternative analysis is used to evaluate different options to meet an objective, while reserve analysis is used to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project to mitigate cost and/or schedule risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Duration Estimates, Basis of Estimates, and Project Document Updates are all — of Estimate Activity Durations Process?

A

Outputs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What project documents are updated as an output of the Estimate Activity Process?

A
  1. Activity attributes
  2. Assumptions log
  3. Lessons Learned register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What provides a clear and complete understanding of how an estimate was derived?

A

Basis of Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a technique used in project management to estimate the duration or cost of an activity or a project using historical data from a similar activity or project?

A

Analogous Estimating
* also known as top-down or macro estimating
* often used when a rough estimate is needed early on
* used for duration and cost estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is an estimating technique that uses statistical relationships between historical data and project parameters to calculate estimates for a project?

A

Parametric Estmating
* also known as bottom-up or detailed estimating
* often used when there is a large amount of data available and project parameters are well known
* can be used for duration and cost estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between Parametric Estimating and Bottom-Up Estimating?

A

parametric estimating uses statistical relationships between historical data and project parameters to calculate estimates, while bottom-up estimating estimates the cost of individual activities and summarizes them up to obtain a project total.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is an estimating technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates?

A

Three Point Estimating

17
Q

What estimating technique is used to better understand the range of possible outcomes for a project and to identify areas of uncertainty or risk?

A

Three Point Estimating

18
Q

Name 4 factors that can effect estimating durations of work?

A
  1. Law of diminishing returns
  2. Number of resources
  3. Advances in technology
  4. Motivation of staff
19
Q

A concept in economics that states that as more and more resources are added to a production process, the marginal increase in output will eventually decrease is called…

A

The law of diminishing returns
Example: farmer and field of crops

20
Q

How can the number of resources effect durations?

A

Increasing the number of resources to twice the original number of the resources does not always reduce the time by half, as it may increase extra duration due to risk, and at some point adding too many resources to the activity may increase duration due to knowledge transfer, learning curve, additional coordination, and other factors involved.

21
Q

What is the student syndrome?

A

When people start to apply themselves only at the last possible moment before the deadline.

22
Q

What is Parkinson’s Law?

A

When work expands to fill the time available for its completion.