Ch5 - Planning / Estimate Activity Durations (5.9) Flashcards
What is the key benefit of the Estimate Activity Durations Process?
It provides the amount of time each activity will take to complete.
What is the process of estimating the number of work periods needed to complete individual activities with estimated resources?
Estimate Activity Durations Process
When is the Estimate Activity Durations Process performed?
Throughout the project
What are the 4 general inputs to the Estimate Activity Durations Process?
- Project Management Plan
- Project Documents
- Enterprise Environmental Factors
- Organizational Process Assets
The Schedule Management Plan and the Scope Baseline are included in what general input to the Estimate Activity Durations Process?
Project Management Plan
Activity attributes, activity list, assumption log, lessons learned register, milestone list team assignments, resource breakdown structure, resource calendars, resource requirements and risk register are all part of what general input to the Estimate Activity Durations Process?
Project Documents
Name 4 estimating techniques are used in the Estimate Activity Durations Process?
(APTB)
- Analogous estimating
- Parametric estimating
- Three-point estimating
- Bottom-up estimating
Alternative Analysis and Reserve Analysis are part of what general technique used in the Estimate Activity Durations Process?
Data Analysis
What is the difference between Alternative Analysis and Reserve Analysis?
Alternative analysis is used to evaluate different options to meet an objective, while reserve analysis is used to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project to mitigate cost and/or schedule risk.
Duration Estimates, Basis of Estimates, and Project Document Updates are all — of Estimate Activity Durations Process?
Outputs
What project documents are updated as an output of the Estimate Activity Process?
- Activity attributes
- Assumptions log
- Lessons Learned register
What provides a clear and complete understanding of how an estimate was derived?
Basis of Estimates
What is a technique used in project management to estimate the duration or cost of an activity or a project using historical data from a similar activity or project?
Analogous Estimating
* also known as top-down or macro estimating
* often used when a rough estimate is needed early on
* used for duration and cost estimates
What is an estimating technique that uses statistical relationships between historical data and project parameters to calculate estimates for a project?
Parametric Estmating
* also known as bottom-up or detailed estimating
* often used when there is a large amount of data available and project parameters are well known
* can be used for duration and cost estimates
What is the difference between Parametric Estimating and Bottom-Up Estimating?
parametric estimating uses statistical relationships between historical data and project parameters to calculate estimates, while bottom-up estimating estimates the cost of individual activities and summarizes them up to obtain a project total.