CH5 - Planning / Define Activities Flashcards
What is the process of identifying and documenting the specific actions to be performed to produce the project deliverables?
Define Activities process
What is the key benefit of the define activities process?
It decomposes work packages into schedule activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.
When does the ‘define activities’ process occur?
This process is performed throughout the project.
The schedule managment plan and scope baseline are — to the ‘define activities’ process?
subsidiary plans to the project management plan that are used at inputs
What are 4 tools and techniques used in ‘define activities’ process?
- Expert judgement
- Decomposition
- Rolling wave planning
- Meetings
What is Rolling Wave Planning?
An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.
As more is known about the upcoming events in the near term, work packages can be decomposed into activities.
Activity list, attributes, milestones, change requests and updates to the schedule baseline and cost baseline are — of the ‘define activities’ process?
outputs