Ch5 - Planning / Dev PjM Plan (5.1) Flashcards
Develop Project Management Plan
What process group consists of those processes that establish the total scope of the effort, define and refine the objectives, and develop the course of action required to attain those objectives.?
Planning Process Group
What is the key benefit of the Planning Process Group?
(ES, DO, DAOO)
- Establish scope
- Define objectives
- Develop the course of action required to obtain objectives
What is the process of defining, preparing, and coordinating all
plan components and consolidating them into an integrated project management plan called?
Develop Project Management Plan
What is the key benefit of the Develop Project Management Plan process?
(CDDBPW)
The production of a comprehensive document that defines the basis of all project work and how the work will be performed.
Name 4 inputs of the Develop Project Management Plan process?
- Project charter
- Outputs from other processes
- Enterprise environmental factors (EEF)
- Organizational process assets (OPA)
What is a document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities called?
Project Charter
What are 2 standard ‘outputs from other processes’?
- Subsidiary plans
- Baselines
What is an EEF?
Enterprise Environmental Factor
Conditions, not under the immediate control of the
team, that influence, constrain, or direct the project, program, or portfolio
What is an OPA?
(P,P, D, T, KR)
Organizational Process Assets
The plans, processes, documents, templates, and knowledge repositories specific to and used by the performing organization. These assets influence the management of the project.
Name 4 Tools & Techniques used in the Develop Project Management Plan process?
- Expert judgement
- Data gathering
- Interpersonal and team skills
- Meetings
What is expert judgement when used as a technique in project planning?
A technique in which judgment is provided based upon a specific set of criteria and/or expertise that has been acquired in a specific knowledge area, application area, or product area, a particular discipline, an industry, etc.
Name 8 possible sources of Expert Judgement that can be used in project planning?
(TM, C, S, A, IG, SME, PMO, S)
- Team members
- Consultants
- Stakeholders - including customers and sponsors
- Professional and technical associations
- Industry groups
- Subject matter experts (SME)
- Project management office (PMO)
- Suppliers
Brainstorming, Checklists, Focus Groups and Interviews are 4 areas of what Tools & Techniques of the Develop Project Management Plan process?
Data gathering
Name 9 data gathering techniques used in project planning?
(Be, Br, CS, CL, SL, FG, I, MR, QS, SS)
- Benchmarking
- Brainstorming
- Check sheets
- Checklists
- Focus Groups
- Interviews
- Market Research
- Questionaires and surveys
- Statistical Sampling
Conflict Management, Facilitation, and Meeting Management are areas of what Tools & Techniques of the Develop Project Management Plan process?
Interpersonal and Team Skills