What were the key challenges in Port Said (Suez Canal) soil stabilization?

A
  • High groundwater table prevented compaction.
  • Soft soil caused excessive settlement when embankments were built.
  • Cement and lime stabilization failed due to high salt content.
  • Solution: Additives mixed with cement to create a flexible, crack-resistant material.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What were the lessons from the Tabasco flood-proof infrastructure case study?

A
  • Roads need reinforcement to prevent erosion.
  • Strategic maintenance of main roads ensures accessibility after floods.
  • Stabilization of major intersections is critical for emergency response.