AOP Tech Specs Flashcards
1
Q
What technical specification governs PCS leaks?
A
T.S. 3.4.13, PCS Operational LEAKAGE
PCS operational LEAKAGE shall be limited to:
- No pressure boundary LEAKAGE;
- 1 gpm unidentified LEAKAGE;
- 10 gpm identified LEAKAGE; and
- 150 gallons per day primary to secondary LEAKAGE through any one steam generator (SG).
Applicable in Modes 1-4
2
Q
What technical specification covers PCS Iodine testing?
A
T.S. 3.4.16 The specific activity of the primary coolant shall be within limits.
Applicable in MODES 1 and 2, MODE 3 with PCS average temperature (Tave) ≥ 500°F.
S.R. 3.4.16 Verify primary coolant DOSE EQUIVALENT I-131
specific activity ≤ 1.0 μCi/gm.
- Once every 14 days and
- Once between 2 and 6 hours after THERMAL POWER change of ≥ 15% RTP within a 1 hour period