6. Project time management Flashcards

1
Q

List the time management processes and their corresponding process groups!

A
  1. Plan schedule management (planning)
  2. Define activities (planning)
  3. Sequence activities (planning)
  4. Estimate activity resources (planning)
  5. Estimate activity durations (planning)
  6. Develop schedule (planning)
  7. Control schedule (planning)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does the network diagram show in its purestform? What can be seen on an “activity box”?

A

Just dependencies (logical relationships)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

List seven things to know about estimating for the exam, i.e. basis for estimating, who should do it, constraings, padding, etc.

A
  • Management plans are the basis for estimating
  • Estimating should be based on WBS
  • Estimating should be done by the person doing the work
  • Historical information is a means to improve estimates
  • PM should never just accept constraints from management
  • PM should periodically recalculate estimate to completion
  • Padding is not allowed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are leads and lags?

A

A lead indicates that an activity can start before its predecessor is completed

A lag is waiting time between two activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How is the standard diagramming method called?

A

Precedence diagramming method or activity on node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which four types of dependencies exist?

A
  • Mandatory (hard logic)
  • Discretionary (soft logic or preferred, i.e. how the organization has chosen to do work)
  • External (i.e. government)
  • Internal (i.e. needs of the project)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Explain the following estimation techniques:

  • One-Point estimating
  • Analogous (top-down) estimating
  • Parametric estimating (regression and learning curve)
  • Three-Point estimating (triangular and beta distribution)
A
  • One-Point estimating: uses only one estimate per activity
  • Analogous estimating: uses of historical information and expert judgement
  • Parametric estimating: uses math and various variables
    • learning curve: 100th rom painted will take less time than the first
  • Three point: uses optimistic, most likely and pessimitisc estimates
    • triangular: simple average
    • beta: weighted average
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Name the formulas for the triangular/simple/straight and beta/PERT distribution plus the formula for standard deviation!

A

Triangular: (P+M+O)/3

Beta: (P+4M+O)/6

Beta standard deviation: (P-O)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define float/slack in general and the following types

  • total float
  • free float
  • project float
A

Float and slack mean the same thing

  • Total float: Amount of time an activity can be delayed without delaying the project end date or milestones
  • Free float: Amount of time and activity can be delayed without delaying the early start date of its successor
  • Project float: Amount of time a project can be delayed without delaying completion date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How to calculate float via the start and finish formula?

A

Start: Float = Late start - early finish

Finish: Late finish - early finish

<add></add>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are fast tracking and crashing?

A

Fast tracking: Doing critical path activities in parallel (think of two cars driving side by side on the highway)

Crashing: Adding ressources to compress the schedule (think of a lot of people coming to help at a crash). Trade time for money!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are monte carlo analysis, resource leveling and resource smoothing?

A

Monte carlo analysis: Statistical technique to simulate project outcome based on three point estimate

Resource leveling: Technique to produce a smoothed schedule if resources are limited. Leveling lengthens the scheudle and increases cost in order to deal with limited resources

Resource smoothing: Modified form of leveling that does not delay completion dates of activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the critical chain method and what is its focus?

A

See the screenshot

Focus is on resources rather than on task order and regid scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly