12. Project procurement management Flashcards

1
Q

List the processes of the procurement management process and their corresponding process groups!

A
  1. Plan Procurement management (planning)
  2. Conduct procurements (executing)
  3. Control procurements (controlling)
  4. Close procurements (closing)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the difference between agreements and contracts?

A

A contract can be an agreement (read outline of internal or external intentions), but an agreement wouldn’t be a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is request for proposal, invitation for bid, request for quotation and request for information?

A

RFP: Request for a detailed proposal on how work will be accomplished, who will do it, etc.

IFB: Request total price to do all work

RFQ: Request price quote per item

RFI: Just information, might be used before procurement documents are created

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List six PMI-isms to remember about procurement!

A
  • Contracts require formality
  • All product and project requirements for procurement should be stated in the contract
  • If it’s not in the contract, it can only done via CR
  • PMs must be assigned on buyer and seller side before a contract is signed
  • Not including PM early in procurement management is a mistake!
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the procurement statement of work and which three types exist?

A

It is the work done on each procurement and must be as clear, complete and concise as possible.

Types

  • Performance: What should the final product be able to accomplish?
  • Functional: What is the purpose of the product?
  • Design: Which work exactly must be done?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do fixed price, time and material and cost-reimbursable contracts differ? Explain the follwing subtypes:

Fixed Price:

  • Fixed price incentive fee (FPIF)
  • Fixed price award fee (FPAF)
  • Fixed price economic price adjustment (FPEPA)
  • Purchase order

Cost-reimbursable:

Cost plus fee (CPF) or cost plus percentage of costs (CPPC)
Cost plus fixed fee (CPFF)
Cost plus incentive fee (CPIF)
Cost plus award fee (CPAF)

A

FP: lump sum, used with well definied specifications, less work for buyer to manage

Purchase order: simple form

Time & material: hourly rate, used for short durations, simple to set up, use for body leasing

Cost-reimbursable: Incurred cost + profit, simple procurement statements, more work to manage

  • CPF & CPPC: bad, don’t use it!
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are target price, sharing ratio and point of total assumption?

A

Target price: Price that was aimed for (Target costs + target fee = target price)

Sharing ratio: Describes how cost savings are distributed. First number to buyer, second number to seller!

Point of total assumption: Point above which seller bears all the loss of cost overrun

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How to calculate the point of total assumption

A

PTA = ((ceiling price - target price) / buyer’s share ratio) + target cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is meant by arbitration, force majeure, indemnification, liquited damages, retainage, waivers, privity and work for hire in procurement context?

A

Arbitration: Method to resolve issues outsides of courts

Force majeure: act of nature

Indemnification: Liability

Liquited damages: Estimated damages for defaults before they occur

Retainage: Amount held back from each payment as securement

Waivers: Some form of clause

Privity: Contractual relationship

Work for hire: Work provided under contract will be owned by buyer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What 5 things do you need to have a legal contract?

A
  • An offer
  • Acceptance
  • Consideration for something of value
  • Legal capacity
  • Legal purpose
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who is the only one with authority to change the contract?

A

Procurement or contract manager!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When is Make-or-buy analysis done and what factors need to be considered when doing it?

A

During Plan Procurement Management

For factors see screenshot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly