15. Misc to know for the exam Flashcards
What is included in the scope, schedule and cost baseline?
Scope: WBS, WBS dictionary, project scope statement
Schedule: Version of the project schedule
Cost: All budgets including contigency resevers but not management reserve
What ist the difference between the project management plan and project documents?
PM plan: Individual management plans, baselines, requirements, change management, configuration management and process improvement plan
Project documents: Any other documentation that can be used to manage a project
What is the difference between work peformance data, informaton and reports?
Data: Initial measurements gahthered during execution
Information: Analyzed measurement for conformance against PM plan during controlling
Reports: Information consolidated for delivery to stakeholders
Which three things can be included in CRs?
- Corrective acton
- Preventive action
- Defect repair
Name the formulas for present value, triangular- and beta distribution. earned value measurement (CV, SV,CPI,SPI,BAC,BTC,EAC,VAC), communication channels, point of total assumption
See screenshot!
It is benefical to invoke the iniating process several times
Yes, i.e. when a new phase is started
Who has authority to decide about changes to the project charter?
The sponsor!
When is documentation of lessons learned done?
During the entire project! Final documentation is done during the closing phase
What is configuration management often concerned with?
About the authorization, approval and documentation of changes!
Project objectives need to be S.M.A.R.T. - what does that mean?
Specific
Measurable
Agreed upon
Realistisc
Timed
Evaluation of reserves and compressiong of is necessary to complete which process?
Develop schedule!
What is mandatory to finalize developing the schedule?
Compressing it!
Which artefact is very benefical when developing the schedule?
Resource availability as found in resource calendars for example
The project schedule is an input to which process?
Develop budget
What is the schedule variance at the end of a project?
Zero