3. Project management processes Flashcards

1
Q

List the 25 processes in the planning column in the correct order! (Hints: P,R,S,PD,PT,WBS,AL,ND,RR,ETC,DCP,DS,DB,DQS,CPIP,RACI,PCM,Risk,GB,FPD,CCP,FPM,Realistisc,Approval,KO)

A
  1. Determine how you will plan for each knowledge area
  2. Determine detailed requirements
  3. Create project scope statement
  4. Assess what to purchase and create procurement documents
  5. Determine planning team
  6. Create WBS and WBS dictionary
  7. Create activity list
  8. Create network diagram
  9. Estimate resource requirements
  10. Estimate time and costs
  11. Determine critical path
  12. Develop schedule
  13. Develop budget
  14. Determine quality standards, processes and metrics
  15. Create process improvement plan
  16. Determine all roles and responsibilities
  17. Plan communications and stakeholder management
  18. Perform risk identification, qualitative/quantitative risk analysis and risk response planning
  19. Go back (iterations)
  20. Finalize procurement documents
  21. Create change management plan
  22. Finalize “hwo to execture and control” parts of all management plans
  23. Develop realistic and final PM plan and performance measurement baseline
  24. Gain formal approval of the plan
  25. Hold kickoff meeting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is progressive elaboration?

A

The process of continually refining estimates and scope!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When (in which phase) is high level planning done and why? Who is involved in the planning process?

A

High level planning is done in the iniating phase to see if the project has a chance of being sucessful. The project manager takes part in this phase.

Everybody is involved in the planning process!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the most important topics to talk about when the team comes together, i.e. in a meeting?

A

Risks and risk management!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name 4 words to summarize executing activties!

A
  • “work to the project management plan”
  • “be proactive”
  • “manage”
  • “guide”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How to deal with deviations from the plan?

A

Deviations should be made up, submitting a CR should be the very last resort!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which two activites MUST be done during project closing?

A
  • Creating lessons learned
  • Measuring customer satisfaction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

List the planning process until create activitiy list! Which process comes next?

A

Create network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

List the 10 planning processes after create network diagram until go back - iterations

A
  1. Estimate resource requirements
  2. Estimate time and cost
  3. Determine critical path
  4. Develop schedule
  5. Develop budget
  6. Determine quality standards, processes and metrics
  7. Create process improvement plan
  8. Determine all roles and responsbilities
  9. Plan communications management
  10. Perform risk identification, qualitative and quantiative risk analysis and risk response planning
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

List the 6 planning processes after go back - iterations!

A
  1. Finalize procurement documents
  2. Create change management plan
  3. Finalize “how to exectute and control” parts of management plans
  4. Develop realistic and final PM plan and performance measurement baseline
  5. Gain formal approval of the plan
  6. Hold kickoff meeting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly