13. Project stakeholder management Flashcards
1
Q
List the stakeholder management processes and their corresponding process groups!
A
- Identify stakeholders (initiating)
- Plan stakeholder management (planning)
- Manage stakeholder engagement (executing)
- Control stakeholder engagement (monitoring and controlling)
2
Q
What are power/interest grids and salience models?
A
See screenshot!
Power interest: think 4 by 4 matrix
Salience: think venn diagram
3
Q
What is the difference in focus between the communications and stakeholder management plan?
A
Communications management plan emphasizes the how (technology, methods and models of communication)
Stakeholder management plan explains why (why stakeholders need to receive information for example)
4
Q
What are the 5i’s to recall when thinking about stakeholder management?
A
See screenshot!