5C - Optimize the Project Schedule Flashcards
1
Q
The act of shortening the project schedule without affecting the project scope.
A
schedule compression
2
Q
The process of compressing the project duration by performing some activities concurrently that were originally scheduled sequentially.
A
fast tracking
3
Q
A schedule compression method that analyzes cost and schedule trade-offs to determine how to obtain the greatest schedule compression for the least incremental cost.
A
crashing
4
Q
Techniques for analyzing the crash costs by creating a graph or visual representation.
A
crash cost plotting methods
5
Q
A project scheduling process where activities are postponed to accommodate the availability of resources.
A
delaying