4C - Identify the Relationships Between Activities Flashcards
A logical relationship that exists between two project activities.
activity dependency
Inherent to the work itself. It is usually affected by physical constraints. Activities must be performed in a specific sequence for the work to be successful.
mandatory dependency (hard logic)
Defined by the project and the project management team at their discretion. It is defined based on the best practices followed in a specific application area or on specific requirements. If there is no mandatory or external dependency between two activities, the team has some flexibility in activity sequencing.
discretionary dependency (soft logic) (preferential logic) (preferred logic)
Contingent on inputs from outside the project activities.
external dependency
Contingent on inputs from within the organization.
internal dependency
The logical relationship between two activities that describes the sequence in which the activities should be carried out.
precedence relationship
When sequencing two activities, the activity that must take place prior to the other.
predecessor activity
When sequencing two activities, the activity that must take place after to the other and is driven by the relationship.
successor activity
The identification of the dependencies of one activity over the other. It involves establishing the precedence relationships among activities and creating logical sequences.
dependency determination
The precedence relationship between two activities where the predecessor activity must finish before the successor activity can start. It can be expressed as, “Activity A must finish before Activity B can begin.”
FS
What does FS stand for?
Finish-to-Start
The precedence relationship between two activities where the predecessor activity must finish before the successor activity can finish. It can be expressed as, “Activity A must finish before Activity B can finish.”
FF
What does FF stand for?
Finish-to-Finish
The precedence relationship between two activities where the predecessor activity must start before the successor activity can start. It can be expressed as, “Activity A must start before Activity B can start.”
SS
What does SS stand for?
Start-to-Start