15B - Control the Project Schedule Flashcards

1
Q

A methodology that measures project progress by comparing actual schedule and cost performance against planned performance as laid out in the schedule and cost baselines.

A

EVM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does EVM stand for?

A

Earned Value Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The budgeted portion of the approved cost estimate to be spent during a particular time period to complete the scheduled project work; previously known as the budgeted cost of work scheduled (BCWS).

A

PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does PV stand for?

A

Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A composite measurement of both cost and timer performance in relation to scheduled or planned cost and time performance. __ is calculated by multiplying the percentage of work completed by the budgeted cost for the activity as laid out in the cost baseline.

A

EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does EV stand for?

A

Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The total amount of costs incurred while accomplishing work performed, either during completion of a scheduled activity or during the completion of a WBS component.

A

AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does AC stand for?

A

Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The measured difference between the actual completion of an activity and the planned or scheduled completion of an activity. The formula for calculating __ is EV - PV = __.

A

SV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does SV stand for?

A

Schedule Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The ratio of work performed to work scheduled. The formula for ___ is ___ = EV / PV.

A

SPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does SPI stand for?

A

Schedule Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Used to illustrate trends in schedule performance.

A

Schedule control chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly