15B - Control the Project Schedule Flashcards
A methodology that measures project progress by comparing actual schedule and cost performance against planned performance as laid out in the schedule and cost baselines.
EVM
What does EVM stand for?
Earned Value Management
The budgeted portion of the approved cost estimate to be spent during a particular time period to complete the scheduled project work; previously known as the budgeted cost of work scheduled (BCWS).
PV
What does PV stand for?
Planned Value
A composite measurement of both cost and timer performance in relation to scheduled or planned cost and time performance. __ is calculated by multiplying the percentage of work completed by the budgeted cost for the activity as laid out in the cost baseline.
EV
What does EV stand for?
Earned Value
The total amount of costs incurred while accomplishing work performed, either during completion of a scheduled activity or during the completion of a WBS component.
AC
What does AC stand for?
Actual Cost
The measured difference between the actual completion of an activity and the planned or scheduled completion of an activity. The formula for calculating __ is EV - PV = __.
SV
What does SV stand for?
Schedule Variance
The ratio of work performed to work scheduled. The formula for ___ is ___ = EV / PV.
SPI
What does SPI stand for?
Schedule Performance Index
Used to illustrate trends in schedule performance.
Schedule control chart