21 Resource Management Flashcards

1
Q

What are the four types of resources that can be used in a project?

A

People
Materials
Facilities
Plant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What considerations are required when determining the amount of resources required for a project?

A

Life cycle approach
Activities and tasks
Types of resources
Skillsets
How long
External resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How does one create a RACI

A

By using an OBS - details organisation and resources available - tasks can be allocated to these resources. For each task,

Responsible
Accountable
Consulted
Informed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference in resourcing between linear and iterative lifecycles?

A

Linear - resources are available when required.
Iterative - requirements prioritised and delivered within time box. Resources pre-allocated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the differences between resource smoothing and resource levelling?

A

Resource levelling - resource constraint.
Resource smoothing - time constrained.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly