Week 6: Simulator Morning Questions Flashcards

1
Q

Plant is at 100% power. Turbine trips. What are your immediate actions? What if the trip is from 40% power?

A

After a turbine trip at 100% power, operators will enter E-0, as a Rx trip will have also occurred due to P-9.

After a turbine trip at 40% power, operators will enter into the associated Off-Normal procedure for a turbine trip, as the Rx will not have automatically tripped.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

While at 100% power, rods unexpectedly begin stepping in at high speed. What are your actions?

A

RO will verify with BOP whether or not a load rejection is occurring; if not, the RO will take manual control of the rods to halt the spurious motion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Draw Pressurizer Pressure Channel 1 High pressure trip from transmitter to Rx trip breaker.

A

The pressure transmitter feeds process control instrumentation, ultimately ending up with an associated bistable for the High Pressure Rx trip. This bistable compares the current value of the transmitter to the trip setpoint and determines if the trip criteria is met. If so, that bistable deenergizes its line to the SSPS. The both trains of the SSPS receive the output of the CH1 bistable and compares it to the trip coincidence logic associated with that particular trip. If the criteria is met, each SSPS train will open its associated Rx trip breaker, deenergizing the CRDMs and dropping the rods into the core.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Plant is in Mode 3. PZR spray valve sticks open. Describe plant response and immediate operator actions.

A

PZR pressure will begin to fall, all heaters will energize. Rx trip is blocked as we are below the P-7 setpoint; instead, SI setpoint of 1849 will be reached, tripping the reactor. E-0 will be entered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Describe the configuration of the RCCAs into banks and groups.

A

Control Banks:
A - 4, 2 groups of 2
B - 8, 2 groups of 4
C - 8, 2 groups of 4
D - 5, 2 RCCAs in Group 1, 3 RCCAs in Group 2

SD Banks:
SA - 8, 2 groups of 4
SB - 8, 2 groups of 4
SC - 4, 1 group
SD - 4, 1 group
SE - 4, 1 group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is SI termination?

A

SI termination is halting the operation of the SI system as actuated by the ESFAS, specifically securing Charging, SI, and RHR pumps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What conditions must be met to Reset SI?

A

P-4, 60 second timer (See Drawing #008)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What gives Phase A isolation? Phase B isolation?

A

SI, CTMT Hi-3 at 27 psig, manual for both

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

List 5 possible causes of a Load Rejection.

A

Offsite Load Transient
Generator Breakers TRIPPED
Exciter Field Breaker TRIPPED
Malfunction of Turbine EHC
Turbine Runback/Setback
Turbine TRIP when less than 50% power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

List 10 indications of a Load Rejection.

A

Control Rods AUTOMATICALLY inserting if in AUTO
Increased Tavg
Condenser Steam Dump Valves OPEN
Increased Pressurizer Level
Increased Steam Header Pressure
Atmospheric Steam Relief Valves OPEN
Decreased Steam Generator Level
Decreased Turbine Impulse Pressure
Pressurizer Power-Operated Relief Valves OPEN
Decreased Steam Flow indication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Explain the response of the following to a load rejection:
1. Rod Control
2. PZR Pressure Control
3. PZR Level Control
4. SG Level Control
5. Steam Dumps

A
  1. Rods step in
  2. Will increase, Sprays and PORVs will actuate in response
  3. Will increase, charging flow will reduce in response
  4. Will decrease, FW increases in response
  5. Opens with a C-7 in conjunction with a C-9 to control Tavg to program
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Rods are below the RIL. What are your actions? When do you stop this action?

A

Emergency borate until the Lo-Lo RIL alarm clears, then terminate emergency boration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Plant is at 100%, all systems in auto. PT506 (Impulse Pressure) fails low. What happens?

A

Rod control thinks that Rx power is higher than Turbine power and begins to insert rods, reducing Tavg. Rods will continue to insert until the power term in Rod Control decays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Draw the Reactor Control Unit (Rod Control Logic).

A

Inputs: Thot, Tcold, Tref, PR NI Power, Turbine Impulse Pressure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

List the first 4 steps of E-0 and explain why they are required.

A

Verify Rx trip; all emergency systems are designed for decay heat only, so if we aren’t tripped yet nothing else matters
Verify Turbine trip; otherwise we are excessively cooling down the Rx
Verify power to NB buses; need this to power safety-related systems
Verify SI actuation; procedure handles both Rx trip and SI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

List the SI termination criteria.

A

PZR level greater than 4% NR
PZR pressure stable
30 degrees of subcooling margin
260,000 lbm/hr of AFW flow or >4% NR level in 1 intact SG

17
Q

Explain how the pressurizer works thermodynamically.

A

As RCS temperature increases, the RCS coolant becomes less dense, and therefore expands. This additional volume goes to the PZR, increasing level. As the coolant level in the PZR rises, the steam bubble at the top of the PZR is compressed, raising RCS pressure.

18
Q

What are the entry conditions for emergency boration?
When can each condition be terminated?

A

Control rod bank below the RIL with reactor; Rods Bank Lo-Lo alarm cleared
Failure of two or more RCCAs to fully insert following Rx trip; when 100ppm/stuck rod has been added to RCS.
Unexplained/Uncontrolled reactivity increase; 100 ppm past the point of observed reactivity decrease
Reactor makeup control system failure; when desired RCS boron concentration reached or operator judgement

19
Q

What are the emergency boration pathways?

A

Through BG HIS-8104
Through BG HIS-110A and -110B
Through V-177
Using RWST

20
Q

Describe subcritical multiplication.

A

The presence of a neutron source in a fissile material will produce a steady-state neutron population greater than that of the source via fission reactions; however, the fission neutrons produced cannot support a self-sustaining chain reaction.

21
Q

List all protective functions produced by Tavg and dT.

A

OTDT
OPDT
P-4
P-12
C-3
C-4

22
Q

What is (1+tau_1 * s)/(1+tau_2 * s)? Draw response to step input.

What is (tau * s)/(1+tau * s)? Draw response to step input.

A

Lead-Lag; rises to a point above the initial input and then decays to match the initial input.

Rate Lag; initially matches the initial input, then decays away to 0.

23
Q

List the 6 preemptive actions.

A

Reduction of AFW flow
Isolation of a faulted SG
Mitigate Thot/Tcold increase after SG dryout
Isolation of a ruptured SG
Transfer steam dump control to Pressure mode
Stopping RCPs for failed-open pressurizer spray valve

24
Q

What is the purpose of the delay tank in the CVCS?

A

To allow for N-16 decay.

25
Q

What is the purpose of the preemptive action to reduce AFW flow?

A

To prevent an uncontrolled cooldown of the RCS below 557F.

26
Q

What is the purpose of the preemptive action to isolate a faulted SG?

A

If the break is downstream of the MSIVs, the closure stops the leak and protects personnel and equipment.
If the break is upstream of the MSIVs, the closure isolates the intact SGs from the faulted one, reducing break flow.

27
Q

What is the purpose of the preemptive action to mitigate Thot/Tcold increase after SG dryout?

A

During the blowdown of a faulted SG, the ECCS adds water to the RCS. When blowdown ends, the RCS cooldown ends as well. Decay heat then starts a RCS heatup, raising PZR level. This plus the additional mass added by SI can lead to a solid plant condition unless the heatup is controlled.

28
Q

What is the purpose of the preemptive action to isolate a ruptured SG?

A

Isolating the ruptured SG accomplishes 2 things: first, isolating the steam from the ruptured SG stops the flow of contaminated steam into the environment, reducing dose to the public. Second, trapping the steam in the ruptured SG increases pressure in said SG, reducing the dP between the RCS and the SG at the U-Tube rupture, slowing the flow of primary coolant into the SG.

29
Q

What is the purpose of the preemptive action to transfer steam dump control to Pressure mode?

A

Post-trip, the steam dumps will be in Rx trip Tavg mode, controlling Tavg to 557F. Accurate indication of Tavg depends on forced flow in the RCS; therefore, if RCPs trip, accurate Tavg indication will be lost. Switching to Pressure mode for the steam dumps will allow for more accurate temperature control in that condition.

30
Q

What is the purpose of the preemptive action to stop RCPs for failed-open pressurizer spray valve?

A

If a PZR spray valve is stuck open, RCS pressure will continue to decrease post-trip to the point where SI will be initiated. In order to prevent an unnecessary SI, the RCPs supplying the spray and surge lines for the impacted spray valve (either loops 1 and 4 or 2 and 4) should be tripped to slow spray flow.

31
Q

List all control functions produced by Tavg and dT.

A

Auctioneered Hi Tavg; Rod Control, PZR Level Control, Steam Dumps, RIL
Auctioneered Hi dT; RIL

32
Q

What are critical safety functions?

A

Subcriticality (S)
Core Cooling (C)
Heat Sink (H)
Integrity (P)
Containment (Z)
Inventory (I)

33
Q

What 5 things are verified by the RO to determine if SI is not required?

A

SL pressure greater than 615
Subcooling greater than 30
CTMT pressure less than 3.5
PZR level greater than 4% level
PZR pressure greater than 1849

34
Q

What are indications of being at the Point of Adding Heat?

A

Steam dumps opening, Tavg changing, PZR Level, SUR begins decreasing

35
Q

What 3 things are verified by the RO to determine if the reactor is tripped?

A

All DRPI lights on bottom
Rx trip breakers open
Power on IR dectectors decreasing