Week 5: GEN-N-UP Flashcards

1
Q

What is the purpose of GEN-N-01?

A

To heat up the plant from a refueling condition or a cold shutdown condition to hot shutdown conditions (i.e. Mode 5 to Mode 4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What RCS pressure is required before placing an RCP into service?

A

320 psig to ensure a #1 seal differential pressure of 200 psid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

At what RCS temperature is at least 1 RCP required to be running?

A

Tcold above 160F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Describe the major steps to heat up the plant from a refueling condition or a cold shutdown condition to hot shutdown conditions.

A

PZR Solid
Raise RCS pressure to ~350 psig
Draw PZR bubble
Start RCPs
Throttle RHR - commence RCS heatup
At Tavg = 325F, place Steam Dumps in service
At Tavg = 345F, isolate RHR and align for ECCS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of GEN-N-02?

A

To take the plant from hot shutdown to hot standby; i.e. NOP/NOT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Describe the major steps to take the plant from hot shutdown to hot standby; i.e. NOP/NOT.

A

Continue RCS Heatup & Pressurization
Between 700-1000 psig RCS pressure, place Accumulators in service
When RCS pressure is greater than 1970, verify P-11 clears
When Tavg is greater than 550F, verify P-12 clears

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the purpose of GEN-N-03?

A

To take the reactor from NOP/NOT and subcritical to NOP/NOT and critical at 2% power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the maximum SURs allowed during the approach to criticality?

A

1 dpm steady-state
1.5 dpm transient

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Describe the approach to criticality.

A

The RO will withdraw the rods in 50 step increments while in overlap and observe the resulting count and startup rates. Using an ICRR and/or a Startup Doubling Curve, a predicted critical position will be obtained and compared to the ECP supplied by RXE. The rod withdrawals will continue until a constant positive startup rate is achieved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

After the reactor is declared critical, where will the RO level off power? What will need to be done before that?

A

The RO will level off power at 10^-8 amps on the IR NIs.

Prior to reaching 10^5 counts on the SR NIs, the SR High Flux trip will need to be blocked once P-6 is reached (10^-10 amps on the IR).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What steps must be taken before blocking the SR Hi flux trip?

A

P-6 in
SR and IR overlapped 1 decade
SR and IR SUR approximately equal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of GEN-N-04?

A

To start the MFW system (removing the S/U FWP from service), starting the main turbine/generator, sync the generator with the grid, raise power to 100%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What GEN-N-04 steps will be taken at 1% RTP?

A

Start 2nd Condenser Pump
Start MFWP
Remove S/U FW Pump

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What GEN-N-04 steps will be taken at 10% RTP?

A

Verify P-10 and P-7 are in
Block IR High flux trip
Block PR High flux trip (low setpoint)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What GEN-N-04 steps will be taken at 15% RTP?

A

Roll Turbine
Sync Generator to grid
Transfer house loads to Unit Aux Xfmr
Steam Dumps to Tavg mode
Rod control to auto
Transfer SG level control to MF reg valves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What GEN-N-04 steps will be taken at 20% RTP?

A

Start 2nd Circ water pump
Add one condensate demin (2 in service)

17
Q

What GEN-N-04 steps will be taken at 40% RTP?

A

Start both heater drain pumps
Add one condensate demin (3 in service)

18
Q

What GEN-N-04 steps will be taken at 50% RTP?

A

Verify P-8/P-9
Perform heat balance
Start 3rd cond pump
Start 2nd MFW pump
Start 3rd Circ water pump
Start 2nd SW pump

19
Q

What GEN-N-04 steps will be taken at 60% RTP?

A

Add one condenser demin (4 in service)

20
Q

What GEN-N-04 steps will be taken at 80% RTP?

A

Perform a heat balance
Add one condenser demin (5 in service)

21
Q

What GEN-N-04 steps will be taken at 100% RTP?

A

Perform heat balance