WBS Flashcards

1
Q

deliverables-oriented

decomposition of the project scope

A

WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

WBS based on a previous project is called this

A

WBS Template or WBT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What 5 activities in the WBS needed for?

A
  1. Defining project activities
  2. Cost estimating
  3. Cost budgeting
  4. Identifying the project risks
  5. Qualitative risk analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

comprised of the project scope statement, the WBS, and the WBS Dictionary

A

Scope Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

an accounting system to track project costs by category (labor, specific materials, contractor rates).

A

Chart of Accounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

numbering system to identify the deliverables down to the work package within a WBS. The PMBOK® Guide uses a type 5.3.3.2

A

Code of Accounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

defines all of the project deliverables, resources, cost and time estimates, and associated information for each work package

A

WBS Dictionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly