Time Facts and Task Relationships Flashcards

1
Q

This relationship is unusual and is rarely used. It requires Task A to start so that Task B may finish. It is also known as just-in-time (JIT) scheduling.

A

Start-to-finish (SF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

This relationship means Task A must start before Task B can start. This relationship allows both activities to happen in tandem.

A

Start-to-start (SS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

This network diagramming approach is based on the availability of project resources to determine project completion. It is more accurate than the traditional network diagram, but is more complex to create.

A

Critical chain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

An opportunity to delay an activity. Also called slack

A

Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Activities are moved closer together or even overlap (negative time).

A

Lead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Waiting time between activities (positive time).

A

Lag

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Allows project phases to overlap to reduce the project duration. This adds risk to the project

A

Fast tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Adding resources to reduce the project duration. This adds costs to the project

A

Crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The amount of time an activity can be delayed without delaying the next activity’s start date

A

Free float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

This relationship means Task A must complete before Task B can begin. This is the most common relationship.

A

Finish-to-start (FS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The amount of time an activity can be delayed without delaying the project’s end date

A

Total float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

This relationship means Task A must complete before Task B does. Ideally, two tasks must finish at exactly the same time, but this is not always the case.

A

Finish-to-finish (FF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly