Time Facts and Task Relationships Flashcards
This relationship is unusual and is rarely used. It requires Task A to start so that Task B may finish. It is also known as just-in-time (JIT) scheduling.
Start-to-finish (SF)
This relationship means Task A must start before Task B can start. This relationship allows both activities to happen in tandem.
Start-to-start (SS)
This network diagramming approach is based on the availability of project resources to determine project completion. It is more accurate than the traditional network diagram, but is more complex to create.
Critical chain
An opportunity to delay an activity. Also called slack
Float
Activities are moved closer together or even overlap (negative time).
Lead
Waiting time between activities (positive time).
Lag
Allows project phases to overlap to reduce the project duration. This adds risk to the project
Fast tracking
Adding resources to reduce the project duration. This adds costs to the project
Crashing
The amount of time an activity can be delayed without delaying the next activity’s start date
Free float
This relationship means Task A must complete before Task B can begin. This is the most common relationship.
Finish-to-start (FS)
The amount of time an activity can be delayed without delaying the project’s end date
Total float
This relationship means Task A must complete before Task B does. Ideally, two tasks must finish at exactly the same time, but this is not always the case.
Finish-to-finish (FF)