Estimate & Cost Types Flashcards

1
Q

Reversed

Simple, early estimate. Range of variance is -25% to +75% for the project completion.

A

Rough order of magnitude

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Reversed

Early planning estimate and/or top-down approach. Range of variance is -10% to +25% for the project completion.

A

Budget estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Reversed

Most accurate estimate, but takes longest to complete; uses the bottom-up approach. Range of variance is -5% to +10% for the project completion.

A

Definitive estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Reversed

Requires a WBS and accounts for each work package

A

Bottom-up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Reversed

Creates an analogy between projects; also known as a top down estimate

A

Analogous

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Reversed

Uses a parameter (cost per ton, cost per unit) for the estimate.

A

Parametric

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Reversed

The cost of the deliverable, service, or materials can fluctuate based on varying factors

A

Variable costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Reversed

A cost that does not change with an increase or decrease in the amount of goods or services produced or sold

A

Fixed costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Reversed

An expense that can be shared with other projects or the organization, such as rent, phone, or equipment.

A

Indirect costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Reversed

Costs that are directly tied to the project.

A

Direct costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Reversed

monies that have been invested into a project. Cost that has already been incurred and cannot be recovered.

A

Sunk costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Reversed

The loss of potential gain from other alternatives when one alternative is chosen.Consider: Project A is worth $55,000 and Project B is worth $89,000, you’d choose Project B to do. The opportunity is $55,000—the amount of Project A that you can’t do because of the opportunity of Project B.

A

Opportunity cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly