EVM - Earned Value Management (& Other Formulas) Flashcards

1
Q

Cost Performance Index (CPI)

A

CPI=EV/AC (Hint: Index is something divided by something) < 1 Over budget = 1 On budget > 1 Under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

To-Complete Performance Index (TCPI) (Using EAC)

A

TCPI=(BAC-EV)/(EAC-AC) (Hint: What’s left to do divided by predicted amount of cash left) < 1 Under budget = 1 On budget > 1 Over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value (EV)

A

EV=% complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Float/Slack

A

LS-ES LS = Late start ES = Early start LF – EF LF = Late finish EF = Early finish = 0 On critical path < 0 Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Estimate at Complete (EAC)

A

EAC=BAC/CPI (Hint: Account for pennies lost on the dollar)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

To-Complete Performance Index (TCPI) (Using BAC)

A

TCPI=(BAC-EV)/(BAC-AC) (Hint: What’s left to do divided by what cash is left) < 1 Under budget = 1 On budget > 1 Over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Standard Deviation

A

(P-O)/6 O= Optimistic estimate P= Pessimistic estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Variance at Completion (VAC)

A

VAC=BAC-EAC < 0 Over budget = 0 On budget > 0 Under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate to Complete (ETC)

A

ETC=EAC-AC (Hint: How much more do you need?)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PERT Estimation

A

(O+4M+P)/6 O= Optimistic estimate M= Most Likely estimate P= Pessimistic estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Variance (SV)

A

SV=EV-PV (Hint: Variance is something minus something) < 0 Behind schedule = 0 On schedule > 0 Ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Planned Value (PV)

A

PV=% planned completion (Hint: someone always had to tell you where you are int he project)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost Variance (CV)

A

CV=EV-AC (Hint: EV always comes first) < 0 Over budget = 0 On budget > 0 Within budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Schedule Performance Variance (SPI)

A

SPI=EV/PV (Hint: Schedule always uses planned value. Costs are always actual costs) < 1 behind schedule = 1 on schedule > 1 ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Five EVM Rules to Memorize

A
  1. Always start with earned value.
  2. Variance means subtraction.
  3. Indexes are “something” divided by “something” and they show
    performance for the project objectives.
  4. When it comes to any index, the closer to 1 the better.
  5. Variances can be positive or negative.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Communication channels formula

A

N(N-1)/2, where N represents the number of stakeholders

17
Q

Future Value (FV)

A

FV = PV(1+i) Future Value(FV), in where: FV is the value to be determined PV is the current investment i is the interest rate n is the number of time periods