Vocabulary Flashcards

1
Q

Acceptance Criteria

A

A set of conditions that is required to be met before deliverables are accepted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Accepted Deliverables

A

Products, results, or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Accuracy

A

within the quality management system, accuracy is an assessment of correctness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Acquire Resources

A

The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Acquisition

A

Obtaining human and material resources necessary to perform project activities. Acquisition implies a cost of resources and is not necessarily financial

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity

A

a distinct, scheduled portion of work performed during the course of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activity Attributes

A

Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, suppressor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activity Duration

A

The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in process or the actual finish date if the schedule activity is complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Activity Duration Estimates

A

the quantitive assessment of the likely number of time periods that are required to complete an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Activity List

A

A documented tabulation of schedule activities that shows the activity description, activity identifier and a sufficiently detailed scope of work description so project team members understand what work is to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Activity on Node

A

Precedence Diagramming Method (PDM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Actual Cost (AC)

A

The realized Cost incurred for the work performed on an activity during a specific time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Actual Duration

A

The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the scheduled activity is complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Adaptive Life Cycle

A

A project life cycle that is iterative or incremental

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Affinity Diagrams

A

A technique that allows large numbers of ideas to be classified into groups for review and analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Agreements

A

Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum on understanding (MOU), letters of agreement, verbal agreements, email etc.

17
Q

Alternative analysis

A

A technique used to evaluate identified options in order to select the options or approached to use to execute and perform the work of the project

18
Q

Analogous Estimating

A

A technique for estimating the duration or cost of an activity or a project using historical data from a similar project or activity

19
Q

Analogous

A

Comparable

20
Q

Analytical Techniques

A

Various techniques used to evaluate, analyze or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables

21
Q

Assumption

A

a factor in the planning process that is considered to be true, real or certain, without proof or demonstration.

22
Q

Assumption log

A

A project document used to record all assumptions and constraints through the project life cycle

23
Q

Attribute Sampling

A

Method of measuring quality that consists of noting the presence ( or absence) of some characteristic (attribute)in each of the units under consideration

24
Q

Authority

A

The right to apply project resources, expend funds, make decisions or give approvals

25
Q

Backward pass

A

A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.

26
Q

Bar Chart

A

A graphic display of schedule related information. In the typical bar chart, schedule activities or work breakdown structure components are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars. See also Gantt Chart

27
Q

Baseline

A

The approved version of a work product that can be changed through formal change control procedures and is used as a basis for comparison to actual results

28
Q

Basis of Estimates

A

Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges and confidence levels

29
Q

Benchmarking

A

The comparison of actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.

30
Q

Benefits Management Plan

A

The documented explanation defining the processes for creating, maximizing, and sustaining the benefits provided by a project or program

31
Q

Bid Documents

A

All documents used to solicit information, quotations, or proposals from prospective sellers

32
Q

Bidder Conference

A

The meetings with perspective sellers prior to the preparation of a bid or a proposal to ensure all prospective vendors have a clear and common understanding of the procurement action. Also know as contractor conferences, vendor conferences or pre- bid conferences

33
Q

Contractor Conference

A

meeting with prospective sellers

34
Q

Vendor Conference

A

meeting with prospective sellers

35
Q

Pre bid conference

A

meeting with prospective sellers