All Terms/ Definitions Flashcards

1
Q

Activity

A

A distinct, scheduled portion of work performed during the course of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity Code

A

An alphanumeric value assigned to each activity that enables classifying, sorting, and filtering. See alsoactivity identifierandactivity label.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activity Identifier

A

A unique alphanumeric value assigned to an activity and used to differentiate that activity from other activities. See alsoactivity codeandactivity label.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activity Label

A

A phrase that names and describes an activity. See alsoactivity codeandactivity identifier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Actual Cost (AC)

A

The realized cost incurred for the work performed on an activity during a specific time period. See alsobudget at completion (BAC),earned value (EV), estimate at completion (EAC), estimate to complete (ETC),andplanned value (PV).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Analogous Estimating

A

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. See alsobottom-up estimating, parametric estimating, program evaluation and review technique (PERT),andthree-point estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Apportioned Effort

A

An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. [Note: Apportioned effort is one of three earned value management (EVM) types of activities used to measure work performance. See alsodiscrete effortandlevel of effort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Assumption

A

A factor in the planning process considered to be true, real, or certain, without proof or demonstration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Backward Pass

A

A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date. See alsoforward pass.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Baseline

A

The approved version of a work product that can be changed using formal change control procedures and is used as the basis for comparison to actual results. See alsocost baseline, performance measurement baseline, schedule baseline,andscope baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Bottom-Up Estimating

A

A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS). See alsoanalogous estimating, parametric estimating, program evaluation and review technique (PERT),andthree-point estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Budget at Completion (BAC)

A

The sum of all budgets established for the work to be performed. See alsoactual cost (AC), earned value (EV), estimate at completion (EAC), estimate to complete (ETC),andplanned value (PV).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Change Control

A

A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected. See alsochange control boardandchange control system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Change Control Board

A

A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions. See alsochange controlandchange control system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Change Control System

A

A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled. See alsochange controlandchange control board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Change Request

A

A formal proposal to modify a document, deliverable, or baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Code of Accounts

A

A numbering system used to uniquely identify each component of the work breakdown structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Communications Management Plan

A

A component of the project, program, or portfolio management plan that describes how, when, and by whom information will be administered and disseminated. See alsoproject management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Configuration Management System

A

A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Constraint

A

A factor that limits the options for managing a project, program, portfolio, or process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Contingency Plan

A

A document describing actions that the project team can take if predetermined trigger conditions occur.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Contingency Reserve

A

Time or money allocated in the schedule or cost baseline for known risks with active response strategies. See alsomanagement reserveandproject budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Control Account

A

A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Corrective Action

A

An intentional activity that realigns the performance of the project work with the project management plan. See alsopreventive action.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Cost Baseline

A

The approved version of work package cost estimates and contingency reserve that can be changed using formal change control procedures and is used as the basis for comparison to actual results. See alsobaseline, performance measurement baseline, schedule baseline,andscope baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Cost Management Plan

A

A component of a project or program management plan that describes how costs will be planned, structured, and controlled. See alsoproject management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Cost Performance Index (CPI)

A

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost. See alsoschedule performance index (SPI).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Cost Variance (CV)

A

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost. See alsoschedule variance (SV).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Crashing

A

A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources. See alsofast trackingandschedule compression.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Critical Chain Method

A

A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Critical Path

A

The sequence of activities that represents the longest path through a project, which determines the shortest possible duration. See alsocritical path activityandcritical path method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Critical Path Activity

A

Any activity on the critical path in a project schedule. See alsocritical pathandcritical path method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Critical Path Method

A

A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. See alsocritical pathandcritical path activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Data Date

A

A point in time when the status of the project is recorded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Decision Tree Analysis

A

A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Decomposition

A

A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Defect Repair

A

An intentional activity to modify a nonconforming product or product component.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Deliverable

A

Any unique and verifiable product, result, or capability to perform a service that is produced to complete a process, phase, or project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Discrete Effort

A

An activity that can be planned and measured and that yields a specific output. [Note: Discrete effort is one of three earned value management (EVM) types of activities used to measure work performance.] See alsoapportioned effortandlevel of effort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Duration

A

The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks. See alsoeffort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Early Finish Date

A

In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints. See alsoearly start date, late start date, late finish date,andschedule network analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Early Start Date

A

In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints. See alsoearly finish date, late finish date, late start date,andschedule network analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Earned Value (EV)

A

The measure of work performed expressed in terms of the budget authorized for that work. See alsoactual cost (AC), budget at completion, estimate at completion (EAC), estimate to complete (ETC),andplanned value (PV).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Earned Value Management

A

A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Effort

A

The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks. See alsoduration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Enterprise Environmental Factors

A

Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Estimate at Completion (EAC)

A

The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete. See alsoactual cost (AC), budget at completion (BAC), earned value (EV), estimate to complete (ETC)andplanned value (PV).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Estimate to Complete (ETC)

A

The expected cost to finish all the remaining project work. See alsoactual cost (AC), budget at completion (BAC), earned value (EV), estimate at completion (EAC)andplanned value (PV).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Fast Tracking

A

A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration. See alsocrashingandschedule compression.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Finish-to-Finish

A

A logical relationship in which a successor activity cannot finish until a predecessor activity has finished. See alsofinish-to-start, start-to-finish, start-to-start,andlogical relationship.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Finish-to-Start

A

A logical relationship in which a successor activity cannot start until a predecessor activity has finished. See alsofinish-to-finish, start-to-finish, start-to-start,andlogical relationship.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Fixed Formula Method

A

A method of estimating earned value in which a specified percentage of the budget value of a work package is assigned to the start milestone and the remaining percentage is assigned when the work package is complete. See alsoweighted milestone method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Forward Pass

A

A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time. See alsobackward pass.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Free Float

A

The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint. See alsototal float, critical path, near-critical activity,andnear-critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Functional Organization

A

An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resources. See alsomatrix organizationandprojectized organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Gantt Chart

A

A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Lag

A

The amount of time whereby a successor activity will be delayed with respect to a predecessor activity. See alsolead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Late Finish Date

A

In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints. See alsoearly finish date, early start date, late start date,andschedule network analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Late Start Date

A

In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints. See alsoearly finish date, late finish date, early start date,andschedule network analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Lead

A

The amount of time whereby a successor activity can be advanced with respect to a predecessor activity. See alsolag.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Lessons Learned

A

The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Level of Effort

A

An activity that does not produce definitive end products and is measured by the passage of time. [Note: Level of effort is one of three earned value management (EVM) types of activities used to measure work performance.] See alsoapportioned effortanddiscrete effort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Logical Relationship

A

A dependency between two activities or between an activity and a milestone. See alsofinish-to-finish, finish-to-start, start-to-finish,andstart-to-start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Management Reserve

A

Time or money that management sets aside in addition to the schedule or cost baseline and releases for unforeseen work that is within the scope of the project. See alsocontingency reserveandproject budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Matrix Organization

A

An organizational structure in which the project manager shares authority with the functional manager temporarily to assign work and apply resources. See alsofunctional organizationandprojectized organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Milestone

A

A significant point or event in a project, program, or portfolio.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Milestone Schedule

A

A type of schedule that presents milestones with planned dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Most Likely Duration

A

An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance. See alsooptimistic duration, andpessimistic duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Near-Critical Activity

A

An activity with a total float that is deemed to be low based on expert judgment. See alsocritical path, free float, near-critical path,andtotal float.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Near-Critical Path

A

A sequence of activities with low float which, if exhausted, becomes a critical path sequence for the project. See alsocritical path, free float, near-critical activity,andtotal float.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Network Logic

A

All activity dependencies in a project schedule network diagram. See alsoearly finish date, early start date, late finish date, late start date,andnetwork path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Network Path

A

A sequence of activities connected by logical relationships in a project schedule network diagram. See alsoearly finish date, early start date, late finish date, late start date,andnetwork logic.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Node

A

A point at which dependency lines connect on a schedule network diagram. See alsoprecedence diagramming method (PDM)andproject schedule network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Opportunity

A

A risk that would have a positive effect on one or more project objectives. See alsoissue, risk,andthreat.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Optimistic Duration

A

An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance. See alsomost likely durationandpessimistic duration.

76
Q

Organizational Breakdown Structure

A

A hierarchical representation of the project organization, which illustrates the relationship between project activities and the organizational units that will perform those activities. See alsoresource breakdown structure, risk breakdown structure,andwork breakdown structure (WBS).

77
Q

Organizational Enabler

A

A structural, cultural, technological, or human-resource practice that the performing organization can use to achieve strategic objectives. See alsoorganizational project management.

78
Q

Organizational Process Assets

A

Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization.

79
Q

Organizational Project Management

A

A framework in which portfolio, program, and project management are integrated with organizational enablers in order to achieve strategic objectives. See alsoorganizational enabler.

80
Q

Organizational Project Management Maturity

A

The level of an organization’s ability to deliver the desired strategic outcomes in a predictable, controllable, and reliable manner.

81
Q

Parametric Estimating

A

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters. See alsoanalogous estimating, bottom-up estimating, program evaluationand review technique (PERT),andthree-point estimating.

82
Q

Path Convergence

A

A relationship in which a schedule activity has more than one predecessor. See alsopath divergence, predecessor activity,andsuccessor activity.

83
Q

Path Divergence

A

A relationship in which a schedule activity has more than one successor. See alsopath convergence, predecessor activity,andsuccessor activity.

84
Q

Percent Complete

A

An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.

85
Q

Performance Measurement Baseline

A

Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution. See alsobaseline, cost baseline, schedule baseline,andscope baseline.

86
Q

Performing Organization

A

An enterprise whose personnel are the most directly involved in doing the work of the project or program.

87
Q

Pessimistic Duration

A

An estimate of the longest activity duration that takes into account all of the known variables that could affect performance. See alsomost likely duration,andoptimistic duration.

88
Q

Phase Gate

A

A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program. See alsoproject phase.

89
Q

Planned Value (PV)

A

The authorized budget assigned to scheduled work. See alsoactual cost (AC), budget at completion (BAC), earned value (EV), estimate at completion (EAC),andestimate to complete (ETC).

90
Q

Portfolio

A

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives. See alsoprogramandproject.

91
Q

Portfolio Balancing

A

The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.

92
Q

Portfolio Charter

A

A document issued by a sponsor that authorizes and specifies the portfolio structure and links the portfolio to the organization’s strategic objectives. See alsoprogram charterandproject charter.

93
Q

Portfolio Management

A

The centralized management of one or more portfolios to achieve strategic objectives. See alsoprogram managementandproject management.

94
Q

Portfolio Management Plan

A

A document that specifies how a portfolio will be organized, monitored, and controlled. See alsoprogram management planandproject management plan.

95
Q

Portfolio Manager

A

The person or group assigned by the performing organization to establish, balance, monitor, and control portfolio components in order to achieve strategic business objectives. See alsoprogram managerandproject manager.

96
Q

Precedence Diagramming Method

A

A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed. See alsonodeandproject schedule network diagram.

97
Q

Predecessor Activity

A

An activity that logically comes before a dependent activity in a schedule. See alsosuccessor activityandsummary activity.

98
Q

Preventive Action

A

An intentional activity that ensures the future performance of the project work is aligned with the project management plan. See alsocorrective action.

99
Q

Probability and Impact Matrix

A

A grid for mapping the probability of occurrence of each risk and its impact on project objectives if that risk occurs. See alsorisk.

100
Q

Procurement Management Plan

A

A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization. See alsoproject management plan.

101
Q

Product Life Cycle

A

The series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement. See alsoproject life cycle.

102
Q

Program

A

Related projects, subsidiary programs, and program activities managed in a coordinated manner to obtain benefits not available from managing them individually.

103
Q

Program Charter

A

A document issued by a sponsor that authorizes the program management team to use organizational resources to execute the program and links the program to the organization’s strategic objectives. See alsoportfolio charterandproject charter.

104
Q

Program Evaluation and Review Technique (PERT)

A

A technique used to estimate project duration through a weighted average of optimistic, pessimistic, and most likely activity durations when there is uncertainty with the individual activity estimates. See alsoanalogous estimating, bottom-up estimating, parametric estimating,andthree-point estimating.

105
Q

Program Management

A

The application of knowledge, skills, and principles to a program to achieve the program objectives and to obtain benefits and control not available by managing program components individually. See alsoportfolio managementandproject management.

106
Q

Program Management Office

A

A management structure that standardizes the program-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques. See alsoproject management office.

107
Q

Program Management Plan

A

A document that integrates the program’s subsidiary plans and establishes the management controls and overall plan for integrating and managing the program’s individual components. See alsoportfolio management planandproject management plan.

108
Q

Program Manager

A

The person authorized by the performing organization to lead the team or teams responsible for achieving program objectives. See alsoportfolio managerandproject manager.

109
Q

Progressive Elaboration

A

The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.

110
Q

Project

A

A temporary endeavor undertaken to create a unique product, service, or result. See alsoportfolioandprogram.

111
Q

Project Budget

A

The sum of work package cost estimates, contingency reserve, and management reserve. See alsocontingency reserveandmanagement reserve.

112
Q

Project Calendar

A

A calendar that identifies working days and shifts that are available for scheduled activities.

113
Q

Project Charter

A

A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. See alsoportfolio charterandprogram charter.

114
Q

Project Life Cycle

A

The series of phases that a project passes through from its start to its completion. See alsoproduct life cycle.

115
Q

Project Management

A

The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements. See alsoportfolio managementandprogram management.

116
Q

Project Management Office

A

A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques. See alsoprogram management office.

117
Q

Project Management Plan

A

The document that describes how the project will be executed, monitored and controlled, and closed. See alsoportfolio management plan, program management plan, communications management plan, cost management plan, resource management plan,andstaffing management plan.

118
Q

Project Manager

A

The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives. See alsoportfolio managerandprogram manager.

119
Q

Project Phase

A

A collection of logically related project activities that culminates in the completion of one or more deliverables. See alsophase gate.

120
Q

Project Schedule

A

An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.

121
Q

Project Schedule Network Diagram

A

A graphical representation of the logical relationships among the project schedule activities. See alsonodeandprecedence diagramming method (PDM).

122
Q

Project Scope

A

The work performed to deliver a product, service, or result with the specified features and functions.

123
Q

Project Scope Statement

A

The description of the project scope, major deliverables, assumptions, and constraints.

124
Q

Projectized Organization

A

An organizational structure in which the project manager has full authority to assign work and apply resources. See alsofunctional organizationandmatrix organization.

125
Q

Quality Management Plan

A

A component of the project or program management plan that describes how an organization’s policies, procedures, and guidelines will be implemented to achieve the quality objectives. See alsoproject management plan.

126
Q

Requirements Management Plan

A

A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed. See alsoproject management plan.

127
Q

Requirements Traceability Matrix

A

A grid that links product requirements from their origin to the deliverables that satisfy them.

128
Q

Residual Risk

A

The risk that remains after risk responses have been implemented. See alsosecondary risk.

129
Q

Resource Breakdown Structure

A

A hierarchical representation of resources by category and type. See alsoorganizational breakdown structure, risk breakdown structure,andwork breakdown structure (WBS).

130
Q

Resource Calendar

A

A calendar that identifies the working days and shifts upon which each specific resource is available.

131
Q

Resource Leveling

A

A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path. See alsoresource smoothingandresource optimization technique.

132
Q

Resource Management Plan

A

A component of the project management plan that describes how project resources are acquired, allocated, monitored, and controlled. See alsoproject management planandstaffing management plan.

133
Q

Resource Optimization Technique

A

A technique in which activity start and finish dates are adjusted to balance demand for resources with the available supply. See alsoresource levelingandresource smoothing.

134
Q

Resource Smoothing

A

A resource optimization technique in which free and total float are used without affecting the critical path. See alsoresource levelingandresource optimization technique.

135
Q

Responsibility Assignment Matrix

A

A grid that shows the project resources assigned to each work package.

136
Q

Risk

A

An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives. See alsoissue, opportunity,andthreat.

137
Q

Risk Acceptance

A

A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs. See alsorisk avoidance, risk enhancement, risk exploiting, risk mitigation, risk sharing,andrisk transference.

138
Q

Risk Appetite

A

The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward. See alsorisk thresholdandrisk tolerance.

139
Q

Risk Avoidance

A

A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact. See alsorisk acceptance, risk enhancement, risk exploiting, risk mitigation, risk sharing,andrisk transference.

140
Q

Risk Breakdown Structure

A

A hierarchical representation of potential sources of risk. See alsoorganizational breakdown structure, resource breakdown structure,andwork breakdown structure (WBS).

141
Q

Risk Category

A

A group of potential causes of risk.

142
Q

Risk Enhancement

A

A risk response strategy whereby the project team acts to increase the probability of occurrence or impact of an opportunity. See alsorisk acceptance, risk avoidance, risk exploiting, risk mitigation, risk sharing,andrisk transference.

143
Q

Risk Exploiting

A

A risk response strategy whereby the project team acts to ensure that an opportunity occurs. See alsorisk acceptance, risk avoidance, risk enhancement, risk mitigation, risk sharing,andrisk transference.

144
Q

Risk Exposure

A

An aggregate measure of the potential impact of all risks at any given point in time in a project, program, or portfolio.

145
Q

Risk Management Plan

A

A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed. See alsoproject management plan.

146
Q

Risk Mitigation

A

A risk response strategy whereby the project team acts to decrease the probability of occurrence or impact of a threat. See alsorisk acceptance, risk avoidance, risk enhancement, risk exploiting, risk sharing,andrisk transference.

147
Q

Risk Owner

A

The person responsible for monitoring the risk and for selecting and implementing an appropriate risk response strategy.

148
Q

Risk Register

A

A repository in which outputs of risk management processes are recorded.

149
Q

Risk Sharing

A

A risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best able to capture the benefit for the project. See alsorisk acceptance, risk avoidance, risk enhancement, risk exploiting, risk mitigation,andrisk transference.

150
Q

Risk Threshold

A

The measure of acceptable variation around an objective that reflects the risk appetite of the organization and stakeholders. See alsorisk appetiteandrisk tolerance.

151
Q

Risk Tolerance [deprecated]

A

The degree of uncertainty that an organization or individual is willing to withstand. See alsorisk appetiteandrisk threshold.

152
Q

Risk Transference

A

A risk response strategy whereby the project team shifts the impact of a threat to a third party, together with ownership of the response. See alsorisk acceptance, risk avoidance, risk enhancement, risk exploiting, risk mitigation,andrisk sharing.

153
Q

Rolling Wave Planning

A

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.

154
Q

Schedule Baseline

A

The approved version of a schedule model that can be changed using formal change control procedures and is used as the basis for comparison to actual results. See alsobaseline, cost baseline, performance measurement baseline,andscope baseline.

155
Q

Schedule Compression

A

A technique used to shorten the schedule duration without reducing the project scope. See alsocrashingandfast tracking.

156
Q

Schedule Management Plan

A

A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule. See alsoproject management plan.

157
Q

Schedule Model

A

A representation of the plan for executing the project’s activities, including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts. See alsoschedule model analysis.

158
Q

Schedule Model Analysis

A

A process used to investigate or analyze the output of the schedule model in order to optimize the schedule. See alsoschedule model.

159
Q

Schedule Network Analysis

A

A technique to identify early and late start dates, as well as early and late finish dates, for the uncompleted portions of project activities. See alsoearly finish date, early start date, late finish date,andlate start date.

160
Q

Schedule Performance Index (SPI)

A

A measure of schedule efficiency expressed as the ratio of earned value to planned value. See alsocost performance index (CPI).

161
Q

Schedule Variance (SV)

A

A measure of schedule performance expressed as the difference between the earned value and the planned value. See alsocost variance (CV).

162
Q

Scope Baseline

A

The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary that can be changed using formal change control procedures and is used as the basis for comparison to actual results. See alsobaseline, cost baseline, performance measurement baseline,andschedule baseline.

163
Q

Scope Creep

A

The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.

164
Q

Scope Management Plan

A

A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and validated. See alsoproject management plan.

165
Q

S-Curve Analysis

A

A technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.

166
Q

Secondary Risk

A

A risk that arises as a direct result of implementing a risk response. See alsoresidual risk.

167
Q

Sponsor

A

An individual or a group that provides resources and support for the project, program, or portfolio, and is accountable for enabling success. See alsostakeholder.

168
Q

Staffing Management Plan

A

A component of the resource management plan that describes when and how team members will be acquired and how long they will be needed. See alsoresource management plan.

169
Q

Stakeholder

A

An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio. See alsosponsor.

170
Q

Stakeholder Engagement Plan

A

A component of the project or program management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in project or program decision making and execution. See alsoproject management plan.

171
Q

Start-to-Finish

A

A logical relationship in which a successor activity cannot finish until a predecessor activity has started. See alsofinish-to-finish, finish-to-start, start-to-start,andlogical relationship.

172
Q

Start-to-Start

A

A logical relationship in which a successor activity cannot start until a predecessor activity has started. See alsofinish-to-finish, finish-to-start, start-to-finish,andlogical relationship.

173
Q

Successor Activity

A

A dependent activity that logically comes after another activity in a schedule. See alsopredecessor activityandsummary activity.

174
Q

Summary Activity

A

A group of related schedule activities aggregated and displayed as a single activity. See alsopredecessor activityandsuccessor activity.

175
Q

Threat

A

A risk that would have a negative effect on one or more project objectives. See alsoissue, opportunity,andrisk.

176
Q

Three-Point Estimating

A

A technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates. See alsoanalogous estimating, bottom-up estimating, parametric estimating,andprogram evaluation and review technique (PERT).

177
Q

To-Complete Performance Index (TCPI)

A

A measure of the cost performance that is achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget. See alsoactual cost (AC), budget at completion (BAC), earned value (EV),andestimate at completion (EAC).

178
Q

Total Float

A

The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint. See alsofree float, critical path, near-critical activity,andnear-critical path.

179
Q

Trigger Condition

A

An event or situation that indicates that a risk is about to occur.

180
Q

Variance Analysis

A

A technique for determining the cause and degree of difference between the baseline and actual performance. See alsocost variance (CV), schedule variance (SV),andvariance at completion.

181
Q

Variance at Completion (VAC)

A

A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion. See alsobudget at completion (BAC), cost variance (CV), estimate at completion (EAC),andvariance analysis.

182
Q

WBS Dictionary

A

A document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure. See alsowork breakdown structure (WBS).

183
Q

Weighted Milestone Method

A

A method of estimating earned value in which the budget value of a work package is divided into measurable segments, each ending with a milestone that is assigned a weighted budget value. See alsofixed formula method.

184
Q

What-If Scenario Analysis

A

The process of evaluating scenarios in order to predict their effect on project objectives.

185
Q

Work Breakdown Structure (WBS)

A

A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. See alsoorganizational breakdown structure, resource breakdown structure, risk breakdown structure,andWBS dictionary.

186
Q

Work Package

A

The work defined at the lowest level of the work breakdown structure for which cost and duration are estimated and managed.

187
Q

Workaround

A

An immediate and temporary response to an issue, for which a prior response had not been planned or was not effective. See alsorisk mitigation.