PNBOK Glossary Flashcards
Organizational Process Assets
Plans, processes, policies, procedures, and knowledge bases that are specific to and used by the performing organization.
Acceptance Criteria
A set of conditions that is required to be met before deliverables are accepted.
Accepted Deliverables
Products, results, or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria.
Accuracy
Within the quality management system, accuracy is an assessment of correctness.
Acquire Resources
The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.
Acquisition
Obtaining human and material resources necessary to perform project activities. Acquisition implies a cost of resources, and is not necessarily financial.
Activity
A distinct, scheduled portion of work performed during the course of a project.
Activity Attributes
Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
Activity Duration
The time in calendar units between the start and finished of a scheduked activity.
Activity Duration Estimates
the likely number of time periods that are required to complete The quantitative assessments of an activity.
Activity List
A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
Activity-on-Node (AON)
See precedence diagramming method (PDM).
Actual Cost (AC)
The realized cost incurred for the work performed on an activity during a specific time period.
Actual Duration
The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete.
Adaptive Life Cycle
A project life cycle that is iterative or incremental.
Affinity Diagrams
A technique that allows large numbers of ideas to be classified into groups for review and analysis.
Agreements
Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, e-mail, etc
Alternative Analysis
A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project.
Analogous Estimating
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
Analytical Techniques
Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables.
Assumption
A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.
Assumption Log
A project document used to record all assumptions and constraints throughout the project life cycle.
Attribute Sampling
Method of measuring quality that consists of noting the presence (or absence) of some characteristic (attribute) in each of the units under consideration.
Authority
The right to apply project resources, expend funds, make decisions, or give approvals.
Backward Pass
A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Bar Chart
A graphic display of schedule-related information. In the typical bar chart, schedule activities or work breakdown structure components are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars. See also Gantt chart.
Baseline
The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Basis of Estimates
Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.
Benchmarking
The comparison of actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.
Benefits Management Plan
The documented explanation defining the processes for creating, maximizing, and sustaining the benefits provided by a project or program.
Bid Documents
All documents used to solicit information, quotations, or proposals from prospective sellers.
Bidder Conference
The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences, or pre-bid conferences.
Bottom-Up Estimating
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Budget
The approved estimate for the project or any work breakdown structure component or any schedule activity.
Budget at Completion (BAC)
The sum of all budgets established for the work to be performed.
Buffer
See reserve.
Business Case
A documented economic feasibility study used to establish validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.
Business Value
The net quantifiable benefit derived from a business endeavor. The benefit may be tangible, intangible, or both.
Cause and Effect Diagram
A decomposition technique that helps trace an undesirable effect back to its root cause.
Change
A modification to any formally controlled deliverable, project management plan component, or project document.
Change Control
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected.
Change Control Board (CCB)
A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.
Change Control System
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Change Control Tools
Manual or automated tools to assist with change and/or configuration management. At a minimum, the tools should support the activities of the CCB.
Change Log
A comprehensive list of changes submitted during the project and their current status.
Change Management Plan
A component of the project management plan that establishes the change control board, documents the extent of its authority, and describes how the change control system will be implemented.
Change Request
A formal proposal to modify a document, deliverable, or baseline.
Checklist Analysis
A technique for systematically reviewing materials using a list for accuracy and completeness.
Check Sheet
A tally sheet that can be used as a checklist when gathering data.
Claim
A request, demand, or assertion of rights by a seller against a buyer, or vice versa, for consideration, compensation, or payment under the terms of a legally binding contract, such as for a disputed change.
Claims Administration
The process of processing, adjudicating, and communicating contract claims.
Close Project or Phase
The process of finalizing all activities for the project, phase, or contract.
Closing Process Group
The process(es) performed to formally complete or close a project, phase, or contract.
Code of Accounts
A numbering system used to uniquely identify each component of the work breakdown structure (WBS).
Collect Requirements
The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.
Colocation
An organizational placement strategy where the project team members are physically located close to one another in order to improve communication, working relationships, and productivity.
Communication Methods
A systematic procedure, technique, or process used to transfer information among project stakeholders.
Communication Models
A description, analogy, or schematic used to represent how the communication process will be performed for the project.
Communication Requirements Analysis
An analytical technique to determine the information needs of the project stakeholders through interviews, workshops, study of lessons learned from previous projects, etc.
Communications Management Plan
A component of the project, program, or portfolio management plan that describes how, when, and by whom information about the project will be administered and disseminated.
Communication Styles Assessment
A technique to identify the preferred communication method, format, and content for stakeholders for planned communication activities.
Communication Technology
Specific tools, systems, computer programs, etc., used to transfer information among project stakeholders.
Conduct Procurements
The process of obtaining seller responses, selecting a seller, and awarding a contract.
Configuration Management Plan
A component of the project management plan that describes how to identify and account for project artifacts under configuration control, and how to record and report changes to them.
Configuration Management System
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
Conformance
Within the quality management system, conformance is a general concept of delivering results that fall within the limits that define acceptable variation for a quality requirement.
Constraint
A limiting factor that affects the execution of a project, program, portfolio, or process.
Context Diagrams
A visual depiction of the product scope showing a business system (process, equipment, computer system, etc.), and how people and other systems (actors) interact with it.
Contingency
An event or occurrence that could affect the execution of the project that may be accounted for with a reserve.
Contingency Reserve
Time or money allocated in the schedule or cost baseline for known risks with active response strategies.
Contingent Response Strategies
Responses provided which may be used in the event that a specific trigger occurs.
Contract
a mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.
Contract Change Control System
The system used to collect, track, adjudicate, and communicate changes to a contract.
Control
Comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed.
Control Account
A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.
Control Chart
A graphic display of process data over time and against established control limits, which has a centerline that assists in detecting a trend of plotted values toward either control limit.
Control Scope
The process of monitoring the status of the project and product scope and managing changes to the scope baseline.
Corrective Action
An intentional activity that realigns the performance of the project work with the project management plan.
Cost Aggregation
Summing the lower-level cost estimates associated with the various work packages for a given level within the project’s WBS or for a given cost control account.
Cost Baseline
The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Cost-Benefit Analysis
A financial analysis tool used to determine the benefits provided by a project against its costs.
Cost Management Plan
A component of a project or program management plan that describes how costs will be planned, structured, and controlled.
Cost of Quality (CoQ)
All costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements.
Cost Performance Index (CPI)
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Plus Award Fee Contract (CPAF)
A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit.
Cost Plus Fixed Fee Contract (CPFF)
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).
Cost Plus Incentive Fee Contract (CPIF)
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.
Cost-Reimbursable Contract
A type of contract involving payment to the seller for the seller’s actual costs, plus a fee typically representing the seller’s profit.
Cost Variance (CV)
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
Crashing
A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Create WBS
The process of subdividing project deliverables and project work into smaller, more manageable components.
Criteria
Standards, rules, or tests on which a judgment or decision can be based or by which a product, service, result, or process can be evaluated.
Critical Path
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.
Critical Path Activity
Any activity on the critical path in a project schedule.
Critical Path Method (CPM)
A method used to estimate the minimum project duration and determine the amount of schedule flexibility on the logical network paths within the schedule model.
Data
Discrete, unorganized, unprocessed measurements or raw observations.
Data Analysis Techniques
Techniques used to organize, assess, and evaluate data and information.
Data Date
A point in time when the status of the project is recorded.
Data Gathering Techniques
Techniques used to collect data and information from a variety of sources.
Data Representation Techniques
Graphic representations or other methods used to convey data and information.
Decision-Making Techniques
Techniques used to select a course of action from different alternatives.
Decision Tree Analysis
A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decomposition
A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.
Defect
An imperfection or deficiency in a project component where that component does not meet its requirements or specifications and needs to be either repaired or replaced.
Defect Repair
An intentional activity to modify a nonconforming product or product component.
Define Activities
The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Define Scope
The process of developing a detailed description of the project and product.
Deliverable
Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.
Dependency
See logical relationship.
Determine Budget
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Development Approach
The method used to create and evolve the product, service, or result during the project life cycle, such as predictive, iterative, incremental, agile, or a hybrid method.
Develop Project Charter
The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Develop Project Management Plan
The process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan.
Develop Schedule
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.
Develop Team
The process of improving competences, team member interaction, and overall team environment to enhance project performance.
Diagramming Techniques
Approaches to presenting information with logical linkages that aid in understanding.
Direct and Manage Project Work
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives.
Discrete Effort
An activity that can be planned and measured and that yields a specific output. [Note: Discrete effort is one of three earned value management (EVM) types of activities used to measure work performance.]
Discretionary Dependency
A relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project where a specific sequence is desired.
Documentation Reviews
The process of gathering a corpus of information and reviewing it to determine accuracy and completeness.
Duration
The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks. Contrast with effort.
Early Finish Date (EF)
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints.
Early Start Date (ES)
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints.
Earned Value (EV)
The measure of work performed expressed in terms of the budget authorized for that work.
Earned Value Management
A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
Effort
The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks. Contrast with duration.
Emotional Intelligence
The ability to identify, assess, and manage the personal emotions of oneself and other people, as well as the collective emotions of groups of people.
Enterprise Environmental Factors
Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio.
Estimate
A quantitative assessment of the likely amount or outcome of a variable, such as project costs, resources, effort, or durations.
Estimate Activity Durations
The process of estimating the number of work periods needed to complete individual activities with the estimated resources.
Estimate Activity Resources
The process of estimating team resources and the type and quantities of material, equipment, and supplies necessary to perform project work.
Estimate at Completion (EAC)
The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate Costs
The process of developing an approximation of the monetary resources needed to complete project work.
Estimate to Complete (ETC)
The expected cost to finish all the remaining project work.
Execute
Directing, managing, performing, and accomplishing the project work; providing the deliverables; and providing work performance information.
Executing Process Group
Those processes performed to complete the work defined in the project management plan to satisfy the project requirements.
Expert Judgment
Judgment provided based upon expertise in an application area, knowledge area, discipline, industry, etc., as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training.
Explicit Knowledge
Knowledge that can be codified using symbols such as words, numbers, and pictures.
External Dependency
A relationship between project activities and non-project activities.
Fallback Plan
An alternative set of actions and tasks available in the event that the primary plan needs to be abandoned because of issues, risks, or other causes.
Fast Tracking
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Fee
Represents profit as a component of compensation to a seller.
Finish Date
A point in time associated with a schedule activity’s completion. Usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, baseline, target, or current.
Finish-to-Finish (FF)
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-Start (FS)
A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Firm Fixed Price Contract (FFP)
A type of fixed price contract where the buyer pays the seller a set amount (as defined by the contract), regardless of the seller’s costs.
Fishbone diagram
See Cause and Effect Diagram.
Fixed-Price Contract
An agreement that sets the fee that will be paid for a defined scope of work regardless of the cost or effort to deliver it.
Fixed Price Incentive Fee Contract (FPIF)
A type of contract where the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria.
Fixed Price with Economic Price Adjustment Contract (FPEPA)
A fixed-price contract, but with a special provision allowing for predefined final adjustments to the contract price due to changed conditions, such as inflation changes, or cost in- creases (or decreases) for specific commodities.
Float
Also called slack. See total float and free float.
Flowchart
The depiction in a diagram format of the inputs, process actions, and outputs of one or more processes within a system.
Focus Groups
An elicitation technique that brings together prequalified stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed prod- uct, service, or result.
Forecast
An estimate or prediction of conditions and events in the project’s future based on information and knowledge available at the time of the forecast.
Forward Pass
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Free Float
The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Functional Organization
An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resources.
Funding Limit Reconciliation
The process of comparing the planned expenditure of project funds against any limits on the commitment of funds for the project to identify any variances between the funding limits and the planned expenditures.
Gantt Chart
A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates.
Grade
A category or rank used to distinguish items that have the same functional use but do not share the same requirements for quality.
Ground Rules
Expectations regarding acceptable behavior by project team members.
Histogram
A bar chart that shows the graphical representation of numerical data.
Historical Information
Documents and data on prior projects including project files, records, correspondence, closed contracts, and closed projects.
Identify Risks
The process of identifying individual risks as well as sources of overall risk and documenting their characteristics.
Identify Stakeholders
The process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.
Implement Risk Responses
The process of implementing agreed-upon risk response plans.
Imposed Date
A fixed date imposed on a schedule activity or schedule milestone, usually in the form of a “start no earlier than” and “finish no later than” date.
Incentive Fee
A set of financial incentives related to cost, schedule, or technical performance of the seller.
Incremental Life Cycle
An adaptive project life cycle in which the deliverable is produced through a series of iterations that successively add functionality within a predetermined time frame. The deliverable contains the necessary and sufficient capability to be considered complete only after the final iteration.
Independent Estimates
A process of using a third party to obtain and analyze information to support prediction of cost, schedule, or other items.
Influence Diagram
A graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes.
Information
Organized or structured data, processed for a specific purpose to make it meaningful, valuable, and useful in specific contexts.
Information Management Systems
Facilities, processes, and procedures used to collect, store, and distribute information between producers and consumers of information in physical or electronic format.
Initiating Process Group
Those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase.
Input
Any item, whether internal or external to the project, which is required by a process before that process proceeds. May be an output from a predecessor process.
Inspection
Examination of a work product to determine whether it conforms to documented standards.
Interpersonal and Team Skills
Skills used to effectively lead and interact with team members and other stakeholders.
Interpersonal Skills
Skills used to establish and maintain relationships with other people.
Interviews
A formal or informal approach to elicit information from stakeholders by talking to them directly.
Invitation for Bid (IFB)
Generally, this term is equivalent to request for proposal. However, in some application areas, it may have a narrower or more specific meaning.
Issue
A current condition or situation that may have an impact on the project objectives.
Issue Log
A project document where information about issues is recorded and monitored.
Iterative Life Cycle
A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team’s understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product.
Knowledge
A mixture of experience, values and beliefs, contextual information, intuition, and insight that people use to make sense of new experiences and information.
Lag
The amount of time whereby a successor activity will be delayed with respect to a predecessor activity.
Late Finish Date (LF)
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network, the project completion date, and any schedule constraints.
Late Start Date (LS)
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints.
Lead
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lessons Learned
The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.
Lessons Learned Register
A project document used to record knowledge gained during a project so that it can be used in the current project and entered into the lessons learned repository.
Lessons Learned Repository
A store of historical information about lessons learned in projects.
Level of Effort (LOE)
An activity that does not produce defini- tive end products and is measured by the passage of time.
Log
A document used to record and describe or denote selected items identified during execution of a process or activity. Usu- ally used with a modifier, such as issue, change, or assumption.
Logical Relationship
A dependency between two activities, or between an activity and a milestone.
Make-or-Buy Analysis
The process of gathering and organizing data about product requirements and analyzing them against available alternatives including the purchase or internal manufacture of the product.
Make-or-Buy Decisions
Decisions made regarding the external purchase or internal manufacture of a product.
Make-or-Buy Decisions
Decisions made regarding the external purchase or internal manufacture of a product. Manage
Manage Communications
Manage Communications is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information.
Management Reserve
An amount of the project budget or project schedule held outside of the performance measurement baseline (PMB) for management control purposes, that is reserved for unforeseen work that is within scope of the project.
Management Skills
The ability to plan, organize, direct, and control individuals or groups of people to achieve specific goals.
Manage Project Knowledge
The process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning.
Manage Quality
The process of translating the quality management plan into executable quality activities that incorporate the organization’s quality policies into the project.
Manage Stakeholder Engagement
The process of communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement.
Manage Team
The process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance.
Mandatory Dependency
A relationship that is contractually required or inherent in the nature of the work.
Master Schedule
A summary-level project schedule that identifies the major deliverables and work breakdown structure components and key schedule milestones. See also milestone schedule.
Matrix Diagrams
A quality management and control tool used to perform data analysis within the organizational structure created in the matrix. The matrix diagram seeks to show the strength of relationships between factors, causes, and object- ives that exist between the rows and columns that form the matrix.
Matrix Organization
Any organizational structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing the work of persons assigned to the project.
Methodology
A system of practices, techniques, procedures, and rules used by those who work in a discipline.
Milestone
A significant point or event in a project, program, or portfolio.
Milestone Schedule
A type of schedule that presents milestones with planned dates. See also master schedule.
Mind-Mapping
A technique used to consolidate ideas created through individual brainstorming sessions into a single map to reflect commonality and differences in understanding and to generate new ideas.
Monitor
Collect project performance data, produce performance measures, and report and disseminate performance information.
Monitor and Control Project Work
The process of tracking, reviewing, and reporting overall progress to meet the performance objectives defined in the project management plan.
Monitor Communications
The process of ensuring that the information needs of the project and its stakeholders are met.
Monitoring and Controlling Process Group
Those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes.
Monitor Risks
The process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk pro- cess effectiveness throughout the project.
Monitor Stakeholder Engagement
The process of monitoring project stakeholder relationships, and tailoring strategies for engaging stakeholders through the modification of engagement strategies and plans.
Monte Carlo Simulation
An analysis technique where a computer model is iterated many times, with the input values chosen at random for each iteration driven by the input data, including probability distributions and probabilistic branches. Outputs are generated to represent the range of possible out- comes for the project.
Multi-criteria Decision Analysis
This technique utilizes a decision matrix to provide a systematic analytical approach for establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas.
Network Logic
All activity dependencies in a project schedule network diagram.
Network Path
A sequence of activities connected by logical relationships in a project schedule network diagram.
Networking
Establishing connections and relationships with other people from the same or other organizations.
Node
A point at which dependency lines connect on a schedule network diagram.
Nominal Group Technique
A technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization.
Objective
Something toward which work is to be directed, a strategic position to be attained, a purpose to be achieved, a result to be obtained, a product to be produced, or a service to be performed.
Opportunity
A risk that would have a positive effect on one or more project objectives.
Organizational Breakdown Structure (OBS)
A hierarchical representation of the project organization, which illustrates the relationship between project activities and the organizational units that will perform those activities.
Organizational Learning
A discipline concerned with the way individuals, groups, and organizations develop knowledge.
Output
A product, result, or service generated by a process. May be an input to a successor process.
Overall Project Risk
The effect of uncertainty on the project as a whole, arising from all sources of uncertainty including individual risks, representing the exposure of stakeholders to the implications of variations in project outcome, both positive and negative.
Parametric Estimating
An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Path Convergence
A relationship in which a schedule activity has more than one predecessor
Path Divergence
A relationship in which a schedule activity has more than one successor.
Percent Complete
An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Performance Measurement Baseline (PMB)
Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution.
Performance Reviews
A technique that is used to measure, compare, and analyze actual performance of work in progress on the project against the baseline.
Perform Integrated Change Control
The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating the decisions.
Perform Qualitative Risk Analysis
The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.
Perform Quantitative Risk Analysis
The process of numerically analyzing the combined effect of identified individual pr ject risks and other sources of uncertainty on overall project objectives.
Phase Gate
A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program.
Plan Communications Management
The process of developing an appropriate approach and plan for project communication activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project.
Plan Cost Management
The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.
Planned Value (PV)
The authorized budget assigned to scheduled work.
Planning Package.
A work breakdown structure component below the control account with known work content but with- out detailed schedule activities. See also control account.
Planning Process Group.
Those processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.
Plan Procurement Management.
The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.
Plan Quality Management.
The process of identifying quality requirements and/or standards for the project and its deliver- ables, and documenting how the project will demonstrate com- pliance with quality requirements and/or standards.
Plan Resource Management.
The process of defining how to estimate, acquire, manage, and utilize physical and team re- sources.
Plan Risk Management.
The process of defining how to con- duct risk management activities for a project.
Plan Risk Responses.
The process of developing options, select- ing strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.
Plan Schedule Management.
The process of establishing the policies, procedures, and documentation for planning, develop- ing, managing, executing, and controlling the project schedule.
Plan Scope Management.
The process of creating a scope man- agement plan that documents how the project and product scope will be defined, validated, and controlled.
Plan Stakeholder Engagement.
The process of developing ap- proaches to involve project stakeholders, based on their needs, expectations, interests, and potential impact on the project.
Plurality.
Decisions made by the largest block in a group, even if a majority is not achieved.
Policy.
A structured pattern of actions adopted by an organiza- tion such that the organization’s policy can be explained as a set of basic principles that govern the organization’s conduct.
Portfolio.
Projects, programs, subsidiary portfolios, and oper- ations managed as a group to achieve strategic objectives.
Portfolio Management.
The centralized management of one or more portfolios to achieve strategic objectives.
Practice.
A specific type of professional or management activity that contributes to the execution of a process and that may em- ploy one or more techniques and tools.
Precedence Diagramming Method (PDM).
A technique used for constructing a schedule model in which activities are rep- resented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activ- ities are to be performed.
Precedence Relationship.
A logical dependency used in the pre- cedence diagramming method.
Predecessor Activity.
An activity that logically comes before a dependent activity in a schedule.
Predictive Life Cycle.
A form of project life cycle in which the project scope, time, and cost are determined in the early phases of the life cycle.
Preventive Action.
An intentional activity that ensures the fu- ture performance of the project work is aligned with the project management plan.
Probability and Impact Matrix.
A grid for mapping the prob- ability of occurrence of each risk and its impact on project ob- jectives if that risk occurs.
Procedure.
An established method of accomplishing a consist- ent performance or result, a procedure typically can be de- scribed as the sequence of steps that will be used to execute a process.
Process.
A systematic series of activities directed towards caus- ing an end result such that one or more inputs will be acted upon to create one or more outputs.
Procurement Audits.
The review of contracts and contracting processes for completeness, accuracy, and effectiveness.
Procurement Documentation.
All documents used in signing, executing, and closing an agreement. Procurement documenta- tion may include documents predating the project.
Procurement Management Plan.
A component of the project or program management plan that describes how a project team will acquire goods and services from outside of the performing organization.
Procurement Statement of Work.
Describes the procurement item in sufficient detail to allow prospective sellers to deter- mine if they are capable of providing the products, services, or results.
Procurement Strategy.
The approach by the buyer to deter- mine the project delivery method and the type of legally bind- ing agreement(s) that should be used to deliver the desired results.
Product.
An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item. Additional words for products are material and goods. See also deliverable.
Product Analysis.
For projects that have a product as a deliver- able, it is a tool to define scope that generally means asking questions about a product and forming answers to describe the use, characteristics, and other relevant aspects of what is going to be manufactured.
Product Life Cycle.
The series of phases that represent the evo- lution of a product, from concept through delivery, growth, ma- turity, and to retirement.
Product Scope.
The features and functions that characterize a product, service, or result.
Product Scope Description.
The documented narrative de- scription of the product scope.
Program.
Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually.
Program Management.
The application of knowledge, skills, and principles to a program to achieve the program objectives and obtain benefits and control not available by managing program components individually.
Progressive Elaboration.
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Project.
A temporary endeavor undertaken to create a unique product, service, or result.
Project Calendar.
A calendar that identifies working days and shifts that are available for scheduled activities.
Project Charter.
A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organ- izational resources to project activities.
Project Communications Management.
Project Communica- tions Management includes the processes required to ensure timely and appropriate planning, collection, creation, distribu- tion, storage, retrieval, management, control, monitoring, and ultimate disposition of project information.
Project Cost Management.
Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so the pro- ject can be completed within the approved budget.
Project Funding Requirements.
Forecast project costs to be paid that are derived from the cost baseline for total or peri- odic requirements, including projected expenditures plus an- ticipated liabilities.
Project Governance.
The framework, functions, and processes that guide project management activities in order to create a unique product, service, or result to meet organizational, stra- tegic, and operational goals.
Project Initiation.
Launching a process that can result in the authorization of a new project.
Project Integration Management.
includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and pro- ject management activities within the Project Management Pro- cess Groups.
Project Life Cycle.
The series of phases that a project passes through from its start to its completion.
Project Management.
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
Project Management Body of Knowledge.
A term that de- scribes the knowledge within the profession of project man- agement. The project management body of knowledge includes proven traditional practices that are widely applied as well as innovative practices that are emerging in the profession.
Project Management Information System.
An information system consisting of the tools and techniques used to gather, integrate, and disseminate the outputs of project management processes.
Project Management Knowledge Area.
An identified area of project management defined by its knowledge requirements and described in terms of its component processes, practices, inputs, outputs, tools, and techniques.
Project Management Office (PMO).
A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.
Project Management Plan.
The document that describes how the project will be executed, monitored and controlled, and closed.
Project Management Process Group.
A logical grouping of project management inputs, tools and techniques, and outputs. The Project Management Process Groups include initiating processes, planning processes, executing processes, monitoring and controlling processes, and closing processes. Project Management Process Groups are not Project phases.
Project Management System.
The aggregation of the processes, tools, techniques, methodologies, resources, and procedures to manage a project.
Project Management Team.
The members of the project team who are directly involved in project management activities.
Project Manager (PM).
The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Project Organization Chart.
A document that graphically de- picts the project team members and their interrelationships for a specific project.
Project Phase.
A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Procurement Management.
Project Procurement Man- agement includes the processes necessary to purchase or ac- quire products, services, or results needed from outside the pro- ject team.
Project Quality Management.
Project Quality Management in- cludes the processes for incorporating the organization’s qual- ity policy regarding planning, managing, and controlling pro- ject and product quality requirements, in order to meet stake- holders’ expectations.
Project Resource Management.
Project Resource Management includes the processes to identify, acquire, and manage the re- sources needed for the successful completion of the project.
Project Risk Management.
Project Risk Management includes the processes of conducting risk management planning, iden- tification, analysis, response planning, response implementa- tion, and monitoring risk on a project.
Project Schedule.
An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.
Project Schedule Management.
Project Schedule Management includes the processes required to manage the timely comple- tion of the project.
Project Schedule Network Diagram.
A graphical representa- tion of the logical relationships among the project schedule activities.
Project Scope.
The work performed to deliver a product, ser- vice, or result with the specified features and functions.
Project Scope Management.
Project Scope Management in- cludes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
Project Scope Statement.
The description of the project scope, major deliverables, and exclusions.
Project Stakeholder Management.
Project Stakeholder Management includes the processes required to identify the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholders expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution.
Project Team.
A set of individuals who support the project manager in performing the work of the project to achieve its ob- jectives.
Project Team Directory.
A documented list of project team members, their project roles, and communication information.
Proposal Evaluation Techniques.
The process of reviewing proposals provided by suppliers to support contract award deci- sions.
Prototypes.
A method of obtaining early feedback on require- ments by providing a working model of the expected product before actually building it.
Quality.
The degree to which a set of inherent characteristics fulfills requirements.
Quality Audits.
A quality audit is a structured, independent process to determine if project activities comply with organiza- tional and project policies, processes, and procedures.
Quality Checklists.
A structured tool used to verify that a set of required steps has been performed.
Quality Control Measurements.
The documented results of control quality activities.
Quality Management Plan.
A component of the project or pro- gram management plan that describes how applicable policies, procedures, and guidelines will be implemented to achieve the quality objectives.
Quality Management System.
The organizational framework whose structure provides the policies, processes, procedures, and resources required to implement the quality management plan. The typical project quality management plan should be compatible to the organization’s quality management system.
Quality Metrics.
A description of a project or product attribute and how to measure it.
Quality Policy.
A policy specific to the Project Quality Manage- ment Knowledge Area, it establishes the basic principles that should govern the organization’s actions as it implements its system for quality management.
Quality Report.
A project document that includes quality man- agement issues, recommendations for corrective actions, and a summary of findings from quality control activities and may include recommendations for process, project, and product im- provements.
Quality Requirement.
A condition or capability that will be used to assess conformance by validating the acceptability of an attribute for the quality of a result.
Questionnaires.
Written sets of questions designed to quickly accumulate information from a large number of respondents.
RACI Chart.
A common type of responsibility assignment ma- trix that uses responsible, accountable, consult, and inform statuses to define the involvement of stakeholders in project activities.
Regression Analysis.
An analytical technique where a series of input variables are examined in relation to their corresponding output results in order to develop a mathematical or statistical relationship.
Regulations.
Requirements imposed by a governmental body. These requirements can establish product, process, or service characteristics, including applicable administrative provisions that have government-mandated compliance.
Request for Information (RFI).
A type of procurement docu- ment whereby the buyer requests a potential seller to provide various pieces of information related to a product or service or seller capability.
Request for Proposal (RFP).
A type of procurement document used to request proposals from prospective sellers of products or services. In some application areas, it may have a narrower more specific meaning.
Request for Quotation (RFQ).
(RFQ). A type of procurement docu- ment used to request price quotations from prospective sellers of common or standard products or services. Sometimes used in place of request for proposal and, in some application areas, it may have a narrower more specific meaning.
Requirement.
A condition or capability that is necessary to be present in a product, service, or result to satisfy a business need.
Requirements Documentation.
A description of how individ- ual requirements meet the business need for the project.
Requirements Management Plan.
A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed.
Requirements Traceability Matrix.
A grid that links product requirements from their origin to the deliverables that satisfy them.
Reserve.
A provision in the project management plan to miti- gate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated.
Reserve Analysis.
An analytical technique to determine the es- sential features and relationships of components in the project management plan to establish a reserve for the schedule dur- ation, budget, estimated cost, or funds for a project.
Residual Risk.
The risk that remains after risk responses have been implemented.
Resource.
A team member or any physical item needed to com- plete the project.
Resource Breakdown Structure.
A hierarchical representation of resources by category and type.
Resource Calendar.
A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Histogram.
A bar chart showing the amount of time that a resource is scheduled to work over a series of time periods.
Resource Leveling.
A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path.
Resource Management Plan.
A component of the project man- agement plan that describes how project resources are ac- quired, allocated, monitored, and controlled.
Resource Manager.
An individual with management authority over one or more resources.
Resource Optimization Technique.
A technique in which ac- tivity start and finish dates are adjusted to balance demand for resources with the available supply. See also resource leveling and resource smoothing.
Resource Requirements.
The types and quantities of resources required for each activity in a work package.
Resource Smoothing.
A resource optimization technique in which free and total float are used without affecting the crit- ical path.
Responsibility.
An assignment that can be delegated within a project management plan such that the assigned resource in- curs a duty to perform the requirements of the assignment.
Responsibility Assignment Matrix (RAM).
A grid that shows the project resources assigned to each work package.
Result.
An output from performing project management pro- cesses and activities. Results include outcomes (e.g., integrated systems, revised process, restructured organization, tests, trained personnel, etc.) and documents (e.g., policies, plans, studies, procedures, specifications, reports, etc.). See also de- liverable.
Rework.
Action taken to bring a defective or nonconforming component into compliance with requirements or specifica- tions.
Risk.
An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.
Risk Acceptance.
A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Risk Appetite.
The degree of uncertainty an organization or in- dividual is willing to accept in anticipation of a reward.
Risk Audit.
A type of audit used to consider the effectiveness of the risk management process.
Risk Avoidance.
A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Breakdown Structure (RBS).
A hierarchical representation of potential sources of risks.
Risk Categorization.
Organization by sources of risk (e.g., using the RBS), the area of the project affected (e.g., using the WBS), or other useful category (e.g., project phase) to determine the areas of the project most exposed to the effects of uncertainty.
Risk Category.
A group of potential causes of risk.
Risk Data Quality Assessment.
Technique to evaluate the de- gree to which the data about is useful for risk manage- ment.
Risk Enhancement.
A risk response strategy whereby the pro- ject team acts to increase the probability of occurrence or im- pact of an opportunity.
Risk Escalation.
A risk response strategy whereby the team ac- knowledges that a risk is outside of its sphere of influence and shifts the ownership of the risk to a higher level of the organiza- tion where it is more effectively managed.
Risk Exploiting.
A risk response strategy whereby the project team acts to ensure that an opportunity occurs.
Risk Exposure.
An aggregate measure of the potential impact of all risks at any given point in time in a project, program, or portfolio.
Risk Management Plan.
A component of the project, program, or portfolio management plan that describes how risk manage- ment activities will be structured and performed.
Risk Mitigation.
A risk response strategy whereby the project team acts to decrease the probability of occurrence or impact of threat.
Risk Owner.
The person responsible for monitoring the risks and for selecting and implementing an appropriate risk re- sponse strategy.
Risk Register.
A repository in which outputs of risk manage- ment processes are recorded.
Risk Report.
A project document developed progressively throughout the Project Risk Management processes, which summarizes information on individual project risks and the level of overall project risk.
Risk Review.
A meeting to examine and document the effect- iveness of risk responses in dealing with overall project risk and with identified individual project risks.
Risk Sharing.
A risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best able to capture the benefit of that opportunity.
Risk Threshold.
The measure of acceptable variation around an objective that reflects the risk appetite of the organization and stakeholders. See also risk appetite.
Risk Transference.
A risk response strategy whereby the pro- ject team shifts the impact of a threat to a third party, together with ownership of the response.
Role.
A defined function to be performed by a project team member, such as testing, filing, inspecting, or coding.
Rolling Wave Planning.
An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.
Root Cause Analysis.
An analytical technique used to deter- mine the basic underlying reason that causes a variance or a defect or a risk. A root cause may underlie more than one vari- ance or defect or risk.
Schedule.
See project schedule and schedule model.
Schedule Baseline.
The approved version of a schedule model that can be changed using formal change control procedures and is used as the basis for comparison to actual results.
Schedule Compression.
A technique used to shorten the sched- ule duration without reducing the project scope.
Schedule Data.
The collection of information for describing and controlling the schedule.
Schedule Forecasts.
Estimates or predictions of conditions and events in the project’s future based on information and know- ledge available at the time the schedule is calculated.
Schedule Management Plan.
A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.
Schedule Model.
A representation of the plan for executing the project’s activities including durations, dependencies, and other planning information, used to produce a project schedule along with other schedule artifacts.
Schedule Network Analysis.
A technique to identify early and late start dates, as well as early and late finish dates, for the un- completed portions of project activities.
Schedule Performance Index (SPI).
A measure of schedule effi- ciency expressed as the ratio of earned value to planned value.
Schedule Variance (SV).
A measure of schedule performance expressed as the difference between the earned value and the planned value.
Scheduling Tool.
A tool that provides schedule component names, definitions, structural relationships, and formats that support the application of a scheduling method.
Scope.
The sum of the products, services, and results to be pro- vided as a project. See also project scope and product scope.
Scope Baseline.
The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dic- tionary, that can be changed using formal change control pro- cedures and is used as a basis for comparison to actual results.
Scope Creep.
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.
Scope Management Plan.
A component of the project or pro- gram management plan that describes how the scope will be defined, developed, monitored, controlled, and validated.
Secondary Risk.
A risk that arises as a direct result of imple- menting a risk response.
Self-Organizing Teams.
A team formation where the team functions with an absence of centralized control.
Seller.
A provider or supplier of products, services, results to an organization.
Seller Proposals.
Formal responses from sellers to a request for proposal or other procurement document specifying the price, commercial terms of sale, and technical specifications or cap- abilities the seller will do for the requesting organization that, if accepted, would bind the seller to perform the resulting agree- ment.
Sensitivity Analysis.
An analysis technique to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes, by correl- ating variations in project outcomes with variations in elem- ents of a quantitative risk analysis model.
Sequence Activities.
The process of identifying and document- ing relationships among the project activities.
Service Level Agreement (SLA).
A contract between a service provider (either internal or external) and the end user that de- fines the level of service expected from the service provider.
Simulation.
An analytical technique that models the combined effect of uncertainties to evaluate their potential impact on ob- jectives.
Source Selection Criteria.
A set of attributes desired by the buyer which a seller is required to meet or exceed to be selected for a contract.
Specification.
A precise statement of the needs to be satisfied and the essential characteristics that are required.
Specification Limits.
The area, on either side of the centerline, or mean, of data plotted on a control chart that meets the cus- tomer’s requirements for a product or service. This area may be greater than or less than the area defined by the control limits. See also control limits.
Sponsor.
A person or group who provides resources and sup- port for the project, program, or portfolio and is accountable for enabling success.
Sponsoring Organization.
The entity responsible for providing the project’s sponsor and a conduit for project funding or other project resources.
Stakeholder.
An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a deci- sion, activity, or outcome of a project, program, or portfolio.
Stakeholder Analysis.
A technique of systematically gathering and analyzing quantitative and qualitative information to de- termine whose interests should be taken into account through- out the project.
Stakeholder Engagement Assessment Matrix.
A matrix that compares current and desired stakeholder engagement levels.
Stakeholder Engagement Plan.
A component of the project management plan that identifies the strategies and actions re- quired to promote productive involvement of stakeholders in project or program decision making and execution.
Stakeholder Register.
A project document including the identi- fication, assessment, and classification of project stakeholders.
Standard.
A document established by an authority, custom, or general consent as a model or example.
Start Date.
A point in time associated with a schedule activity’s start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current.
Start-to-Finish (SF).
A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Start (SS).
A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Statement of Work (SOW).
(SOW). A narrative description of products, services, or results to be delivered by the project.
Statistical Sampling.
Choosing part of a population of interest for inspection.
Successor Activity.
A dependent activity that logically comes after another activity in a schedule.
Summary Activity.
A group of related schedule activities ag- gregated and displayed as a single activity.
SWOT Analysis.
Analysis of strengths, weaknesses, opportun- ities, and threats of an organization, project, or option.
Tacit Knowledge.
Personal knowledge that can be difficult to articulate and share such as beliefs, experience, and insights.
Tailoring.
Determining the appropriate combination of pro- cesses, inputs, tools, techniques, outputs, and life cycle phases to manage a project.
Team Charter.
A document that records the team values, agree- ments, and operating guidelines, as well as establishing clear expectations regarding acceptable behavior by project team members.
Team Management Plan.
A component of the resource man- agement plan that describes when and how team members will be acquired and how long they will be needed.
Technique.
A defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service, and that may employ one or more tools.
Templates.
A partially complete document in a predefined for- mat that provides a defined structure for collecting, organizing, and presenting information and data.
Templates.
A partially complete document in a predefined for- mat that provides a defined structure for collecting, organizing, and presenting information and data.
Test and Evaluation Documents.
Project documents that de- scribe the activities used to determine if the product meets the quality objectives stated in the quality management plan.
Threat.
A risk that would have a negative effect on one or more project objectives.
Three-Point Estimating.
A technique used to estimate cost or duration by applying an average or weighted average of opti- mistic, pessimistic, and most likely estimates when there is un- certainty with the individual activity estimates.
Threshold.
A predetermined value of a measurable project vari- able that represents a limit that requires action to be taken if it is reached.
Time and Material Contract (T&M).
A type of contract that is a hybrid contractual arrangement containing aspects of both cost-reimbursable and fixed-price contracts.
To-Complete Performance Index (TCPI).
A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, ex- pressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Tolerance.
The quantified description of acceptable variation for a quality requirement.
Tool.
Something tangible, such as a template or software pro- gram, used in performing an activity to produce a product or result.
Tornado Diagram.
A special type of bar chart used in sensitiv- ity analysis for comparing the relative importance of the vari- ables.
Total Float.
The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Trend Analysis.
An analytical technique that uses mathem- atical models to forecast future outcomes based on historical results.
Trigger Condition.
An event or situation that indicates that a risk is about to occur.
Unanimity.
Agreement by everyone in the group on a single course of action.
Update.
A modification to any deliverable, project management plan component, or project document that is not under formal change control.
Validate Scope.
The process of formalizing acceptance of the completed project deliverables.
Validation.
The assurance that a product, service, or result meets the needs of the customer and other identified stake- holders. Contrast with verification.
Variance.
A quantifiable deviation, departure, or divergence away from a known baseline or expected value.
Variance Analysis.
A technique for determining the cause and degree of difference between the baseline and actual perform- ance.
Variance At Completion (VAC).
A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.
Variation.
An actual condition that is different from the ex- pected condition that is contained in the baseline plan.
Variation.
An actual condition that is different from the ex- pected condition that is contained in the baseline plan.
Verification.
The evaluation of whether or not a product, ser- vice, or result complies with a regulation, requirement, specifi- cation, or imposed condition. Contrast with validation.
Verified Deliverables.
Completed project deliverables that have been checked and confirmed for correctness through the Con- trol Quality process.
Virtual Teams.
Groups of people with a shared goal who fulfill their roles with little or no time spent meeting face to face.
Voice of the Customer.
A planning technique used to provide products, services, and results that truly reflect customer re- quirements by translating those customer requirements into the appropriate technical requirements for each phase of pro- ject product development.
WBS Dictionary.
A document that provides detailed deliver- able, activity, and scheduling information about each compo- nent in the work breakdown structure.
WBS Dictionary.
A document that provides detailed deliver- able, activity, and scheduling information about each compo- nent in the work breakdown structure.
What-If Scenario Analysis.
The process of evaluating scen- arios in order to predict their effect on project objectives.
Work Breakdown Structure (WBS).
A hierarchical decompos- ition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the re- quired deliverables.
Work Breakdown Structure Component.
An entry in the work breakdown structure that can be at any level.
Work Package.
The work defined at the lowest level of the work breakdown structure for which cost and duration are estimated and managed.
Work Performance Data.
The raw observations and measure- ments identified during activities being performed to carry out the project work.
Work Performance Information.
The performance data col- lected from controlling processes, analyzed in comparison with project management plan components, project documents, and other work performance information.
Work Performance Reports.
The physical or electronic repre- sentation of work performance information compiled in project documents, intended to generate decisions, actions, or aware- ness.
Chp 4: Project Integration Management processes (7)
- Develop Project Charter
- Develop Project Management Plan
- Direct and Manage Project Work
- Manage project knowledge
- monitor and control project work
- perform integrated change control
- close project or phase
4.1: develop project charter - inputs
- business case
- agreements
- EEFs
- OPAs
4.1: develop project charter - tools and techniques
- data gathering
- expert judgment
- brainstorming
- focus groups
- interviews
- interpersonal and team skills
- conflict mgt
- facilitation
- meetings mgt
- meetings