Formulas Flashcards

1
Q

Analogous Estimating

A

Described in section 6.4.2.2 uses value or attributes of a previous project that area similar to the current project values and attributes of the projects may include but are not limited to scope, cost, budget, duration, and measures of scale ( eg size, weight). Comparison of these project variables or attributes, become the basis for estimating the same parameter or measurement for the current project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Parametric Estimating

A

6.4.2.3 Parametric measuring uses a statistical relationship between relevant historical data and other variables ( eg square footage in a building construction) to calculate a cost estimate for project work. This technique can produce higher levels of accuracy depending on the sophistication and underlying data built in to the model. Parametric cost estimates can be applied to a total project or t osegments of a project, in conjunction with other estimating methods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Parametric

A

of relating to a parameter. A constant in an equation that vary in other equations in general form One set of measurable factors. such as temperature and pressure that define a system and determine its behavior and are varied in an experiment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

analogous

A

Similar or alike in such a way as to permit the drawing of an analogy, similar or corresponding in some respect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Bottom up estimating

A

6.4.2.5 Bottom up estimating is a method of estimating a component of work the cost of individual work packages or activities is estimated to be the greatest level of specified detail. The detailed cost is then summarized or rolled up to higher levels for subsequent reporting and tracking purposes. The cost and accuracy of bottom up cost estimating are typically influenced by the size or other attributes of the individual activity or work percentage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Three Point estimating

A

6.4.2.4 The accuracy of single point cost estimates may be improved by considering estimation uncertainty and risk using three estimates to define an approximate range for an activities cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Most likely (cM)

A

The cost of an activity, based on realistic effort assessment for the required work and any predicted expenses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Optimistic (cO)

A

The cost based on analysis on the best case scenario for the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Pessimistic

A

The cost based on analysis of the worst case scenario for the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Three point estimating finish sentence

A

Depending on the assumed distribution of values withing the range of the three estimates, the expected cost can be calculated using a formula. tow commonly used formulas are triangular and beta distributions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Expected Cost (cE)

A

(cE)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Optimistic

A

(cO)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Most likely

A

(cM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Triangular distribution

A

cE= (cO +cM+cP)/3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Triangular distribution in words

A

expected cost= (optimistic cost + most likely cost + pessimistic cost) /3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Beta distribution

A

cE= (cO + 4cM +cP)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

beta distribution in words

A

expected cost = optimistic + 4* most likely cost +pessimistic cost)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Cost estimate statement

A

Cost estimates based on three points with an assumed distribution provide an expected cost and clarify the range of uncertanty around the expected cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Data analysis

A

Data analysis techniques that can be used in the estimate costs process include but are not limited to Alternative analysis, Reserve analysis, cost of quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Alternative analysis

A

alternative analysis is a technique used to evaluate identified options in order to select which options or approaches to use to execute and perform the work of the project. An example would be evaluating the cost, schedule, resource and quality impacts of buying versus making a deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Reserve analysis

A

cost estimates may include contingency reserves or contingency allowances to account for cost uncertainty. Contingency reserves are the budget within the cost baseline that is allocated for identified risks. Contingency reserves are often viewed as part of the budget intended to address the known unknowns that can affect a project. Foe example, re work for some project deliverables could be anticipated, while the amount of this rework is unknown. Contingency reserves may be estimated to account for this unknown amount of re work. Contingency reserves can be provided at any level from the specified activity to the entire project. The contingency reserve may be a percentage of the estimated cost, a fixed number, or may be developed by using quantitative analysis methods. As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated. Contingency should be clearly identified in cost documentation. Contingency reserves are part of the cost baseline and the overall funding requirement for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Contingency reserves AKA

A

AKA contingency allowances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Contigency reserves

A

contingency reserves are the budget within the cost baseline that is allocated for identified risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Cost of quality

A

Assumptions about cost of quality (8.1.2.3) may be used to prepare the estimates. This included evaluating the cost impact of additional investment in conformance versus the cost of non conformance. It can also include looking at short -term cost reductions versus the implication of more frequent problems later on in the product life cycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

PV

A

Planned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

PV definition

A

The authorized budget assigned to scheduled work. The value of the work planned to be completed t oa point in time, usually the data table, or project completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

EV

A

Earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

EV definition

A

The measure of work performed expressed in terms of the budget authorized for that work,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

EV how it’s used

A

The planned value of all of the work completed (earned) to a point in time, usually the data date, without reference to actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

EV formula

A

Ev= sum of the planned value of completed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

AC

A

Actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

AC definition

A

The realized cost incurred for the work performed on an activity during a specified time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

AC how it’s used

A

The actual cost of all of the work completed to a point in time ,usually the data date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

BAC

A

Budget at comparison

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

BAC Definition

A

The sum of all budgets established for the work to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

BAC

A

The value of total planned work, the project baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

product baseline

A

BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

CV Definition

A

Cost variance

39
Q

CV definition

A

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost

40
Q

CV how its used

A

The difference between the work completed to a point in time usually the data date. and the actual costs at the same point in time

41
Q

CV equation

A

CV= EV-AC

42
Q

CV equation in words

A

Cost variance = earned value - actual cost

43
Q

CV interpretation of results

A

Positive- under planned costs, Neutral on planned costs, negative over planned cost

44
Q

SV

A

Schedule varience

45
Q

SV definition

A

The amount by which the project is ahead or behind the planned delivery date, at a given point in time, expressed as the difference between the budget at completion and the estimate at completion

46
Q

SV how is it used

A

The difference between the work completed to a point in time , usually the data date, and the work planned to be completed to the same point

47
Q

SV formula

A

SV=EV-PV

48
Q

SV formula in words

A

Schedule variance is = earned value- planned value

49
Q

SV interpretation of results

A

Positive= ahead of schedule, Neutral on schedule, Negative behind schedule

50
Q

VAC

A

Variance at completion

51
Q

VAC definition

A

A projection of the amount of budget defecit or surplus expressed as the difference between the budget at completion and the estimate at completion

52
Q

VAC how its used

A

The estimated difference in cost at the completion of a project

53
Q

VAC formula

A

VAC= BAC-EAC

54
Q

VAC formula in words

A

Variance at completion= budget at completion -estimate at completion

55
Q

VAC interpretation of results

A

Positive - under planned cost, Neutral - on planned cost, Negative - under planned cost

56
Q

CPI

A

Cost performance index

57
Q

CPI definition

A

A measure of the cost efficiency of budgeted resources expressed as the ration of earned value to actual cost

58
Q

CPI how it’s used

A

A CPI of 1.0 means the project is exactly on budget, that the work actually done so far is exactly done so far is exactly the same as the cost so far. Other values show the percentage of how much costs are over or under the budgeted amount of work accomplished

59
Q

CPI formula

A

CPI= EV/AC

60
Q

CPI formula in words

A

cost performance index= earned value/actual cost

61
Q

CPI Interpretation of result

A

Greater than 1.0 under planned cost, exactly 1.0 on planned cost. Less than 1.0 behind schedule

62
Q

SPI

A

Schedule Performance Index

63
Q

SPI definition

A

A measure of schedule efficiency expressed as the ratio of earned value to planned value

64
Q

SPI how its used

A

A SPi of 1.0 means that the project is exactly on schedule. that the work actually done so far is exactly the same as the work planned to be done so far. Other values show the percentage of how much costs are under or over the budgeted amount for work planned.

65
Q

SPI formula

A

SPI= EV/PV

66
Q

SPI formula in words

A

Schedule Performance index =Earned value/ Planned value

67
Q

SPI interpretation of results

A

Greater than 1.0 ahead of schedule, 1.0 on schedule, less than 1.0 behind schedule

68
Q

EAC

A

Estimate at completion

69
Q

EAC definition

A

The expected cost to finish all of the remaining project work

70
Q

EAC how its used

A

If the CPI is expected to be the same for the remainder of the project, EAC can be calculated using EAC= BAC/CPI

71
Q

EAC formula CPI the same for the rest of the project

A

EAC=BAC/CPI

72
Q

EAC formula CPI the same in words

A

estimate at completion = budget at completion/cost performance index

73
Q

EAC formula if future work will be accomplished at the planned rate

A

EAC= AC+BAC-EV

74
Q

EAC formula if future work will be accomplished at the planned rate in words

A

estimate at completion= Actual cost +budget at completion-earned value

75
Q

EAC formula if the initial plan is no longer valid

A

EAC= AC+ Bottom up ETC

76
Q

EAC if both the CPI and SPI influence the remaining work use this formula

A

EAC= AC +[(BAC-EV)/(CPI*SPI)]

77
Q

EAC if both the CPI and SPI influence the remaining work use formula in words

A

Estimate to completion = Actual cost +{(budget at completion-earned value)/(Cost Performance Index*Schedule Performance Index)]

78
Q

ETC

A

Estimate to complete

79
Q

ETC definition

A

The expected cost to finish all the remained work project

80
Q

ETC How it’s used

A

Assuming work is proceeding on plan, the cost of completing the remaining authorized work can be calculated using

81
Q

ETC Proceeding on plan formula

A

ETC= EAC-AC

82
Q

ETC proceeding on plan formula words

A

estimate at complete = Estimate at completion-Actual Cost

83
Q

ETC formula for re estimate the remaining work from the bottom up

A

ETC= re estimate

84
Q

TCPI

A

To complete performance index

85
Q

TCPI definition

A

A measure of the cost performance that must be achieved wit the remaining resources in order to meet a specified management goal., expressed as the ratio of the cost to finish the outstanding work to the budget available.

86
Q

TCPI how it’s used

A

The efficiency that must be maintained in order to complete on the plan

87
Q

TCPI formula the efficiency that must be maintained in order to complete on plan

A

TCPI= (BAC-EV)/(BAC-AC)

88
Q

TCPI formula the efficiency that must be maintained in order to complete on plan in words

A

To complete performance index = (Budget at completion- earned value)/(Budget at completion-Actual cost)

89
Q

TCPI the efficiency that must be maintained in order to complete on plan Interpretation of result

A

greater than 1.0= harder to complete/ exactly 1.0 same to complete- less than 1.0 easier to complete

90
Q

TCPI how it’s used part 2

A

the efficiency that must be maintained in order to complete the current EAC- (Estimate at Completion)

91
Q

TCPI the efficiency that must be maintained in order to complete the current EAC formula

A

TCPI=(BAC-EV)/EAC-AC)

92
Q

TCPI the efficiency that must be maintained in order to complete the current EAC formula in words

A

To complete performance index= (Budget at Completion-Earned value)/(estimate at completion-actual cost)

93
Q

TCPI the efficiency that must be maintained in order to complete the current EAC interpretation of results

A

Greater than 1.0 Harder to complete, exactly 1.0 same to complete, Less than 1.0 easier to complete

94
Q

Communication channels formula

A

N(n-1)/2