VE Change Proposals & Option Evaluation Flashcards

1
Q

How is influence of cost affected by the amount of time spent on an activity

A

Disproportionally

Spend a lot of time in construction phase with little ability to influence cost and vice versa

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2 objectives of VE

A

Attempts to mitigate the risk that contractors proposals will harm the project

Provides rigour to development of design revision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are VE change proposals (VECPs)

A

Provide a formalised process by which the contractor can suggest changes to add value

Should always increase (or at the least not reduce) functionality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the content of a VECP

A

Description of proposed change

Explanation as to benefits and drawbacks of proposal

Change may be to the design or contract form

List of changes to the contract required

Estimates of functionality and cost implications

Itemised costs incurred by the contractor in preparing VECP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How are VECPs produced

A

Scope is clarified of the technical problem within the wider project

Workshops with right stakeholders

Create an opportunity to examine functionality that the design element must provide

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are VE incentivisation clauses

A

An incentive clause provides a mechanism and a reward to the contractor for using VE thereby passing suggestions/savings to the client

Makes VE mutually beneficial

Pain/gain share in target cost contracts also act in a similar manner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is a preferred option identified

A

A systematic approach to option evaluation is required

Judgement is also required to finalise the systematic process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Three basic approaches to option evaluation

A

Evaluation by comparison (systematic)

Evaluation by simple rating (useful for listing)

Evaluation by value metrics (most rigorous but required model of value)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the Pareto 80/20 rule applied to VE

A

80% of a system trait is provided by 20% of the system elements

Most useful 20% of options can be identified to leave the remaining 80% for VE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly