Exam Last Bits Flashcards
BCIS Question
GIFA
Project indexation factor
Rebase building subtotal rate/m2 from analysis
Multiply rebased rate/m2 to get building works estimate
Multiply building works estimate by 113/100 (13% prelims) to get works cost estimation
Multiply works cost estimate by 103.5/100 to add project/design team fees
Exclude project development costs to get base cost estimate
Multiply by 105/100 (5% risk allowance) to get cost limit excluding inflation
What is included in sensitivity analysis
Everything but capital costs (but yearly occurring costs are not recalculated as they are unaffected)
Residual values are to be excluded as the sensitivity analysis makes the same assumptions for both projects/systems in the comparison. This means any errors in estimating calculations would cancel out hence residual value exclusion.
Are annually recurring costs affected by ESL variations
No