Unit 9 Flashcards
What are the steps in Plan to Produce Process
Perform planning
- Determine requirements
- Plan production
- Produce material
- Perform periodic processing
What planning tool will replace the SOP
IBP
SAP S/4HANA supports simplified sourcing in material planning. What possible sources of supply are available?
Production versions
Delivery schedule
Purchasing contracts
Purchasing info records
List the master data in the Plan to Produce Process.
3 types of material: Raw, Finished, Semi-Finished
· BOM
· Routing
· Work Center
Which material views are needed for material planning
MRP 1 to MRP 4
Describe the structure of the BOM.
Header and Items ( 4 category)
· Structured list of all the components required to produce a product
· BOM Header (Description, lot-size range, status, validity)
· ITEM (Item types, Description, Qty, Control Data)
What are item categories with reference to a BOM?
Stock item
The stock items are stored in the warehouse and used in production.
· Non-stock item
The system directly assigns non-stock items to a manufacturing order (not through the warehouse). Non-stock items are not kept in inventory, but procured specifically for the production order
· Variable-size item
Variable-size items contain variable-size data (for example, the surface area of a steel sheet).
· Document item
Document items contain a supplementary document that describes production using a design and construction diagram.
What is the purpose of a routing
Routings contain the steps that are necessary for production and these steps are called operations. Routings include the sequence in which the operations occur, and the work centers at which the operations are to be executed.
How are BOM’s and Routings connected?
Both describe production/ how a product can be made → production version (which component of the BOM is in which operation of a routing?). You can assign a BOM to a specific operation in the routing.
How are routings connected to work centers and what objectives does this serve? ( Examen)
Operations are assigned to work center
Work center help plan cost for operations and schedule operations
What is a production version
(réponse courte) Specific combination between BOM & Routing
What is the integration of a work center with CO
It is assigned to a cost center which is handled in CO & activity type
Explain the phases of Product Cost Accounting.
Product Cost Planning: creates Standard Cost Estimate
· Cost Object Controlling: Collects actual costs incurred during the production
· Actual Costing & Material Ledger: Provides Actual Cost of each material at the end of the period
What master data is used for product cost planning
BOM – Routing
What can you do with the standard cost estimate + where do you get the standard cost estimate? Examen
Standard cost estimate = cost estimate material
What you can do = Update prices, planifier les coûts de production
Where do you get it = product cost planning