UAP Doc 301 Flashcards

1
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

SECTION 1

A

Definitions and Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Contract documents

A

• Agreement
• General Conditions
• Special Provisions
• Specifications
• Drawings
• All additions, deletions, and modifications
incorporated before the execution of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The person or entity ordering the project for
execution, including duly appointed successors of
authorized representatives

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The architect commissioned by the owner acting
personally or through assistants duly authorized in
writing by the architect to act on his behalf

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The person so named in the Contract Documents
of his duly authorized representative

A

Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The full-time construction inspector hired by the
owner duly authorized in writing to assist the
architect and engineer in supervising the work

A

Project representative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The person or firm whose proposal has been
accepted and to whom the contract was awarded

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Anyone having a direct contact with the contractor
who acts for or in behalf of the contractor in
executing any part of the contract, not including one
who merely furnishes materials without labor

A

Subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The person, firm, or corporation who provides the
guarantee for the contractor’s bonds

A

Surety

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The offer of a bidder to perform the work described
by the contract documents when made out and
submitted on the prescribed Proposal Form,
properly signed and guaranteed

A

Proposal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The cashier’s check or surety bond accompanying
the proposal submitted by the bidder as a
guarantee that the bidder will enter into a contract
with the owner if the contract is awarded to him

A

Proposal bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Approved form of security furnished by the
contractor and his surety as a guarantee of good
faith on the part of the contractor to execute the
work in accordance with the terms of the contract

A

Performance bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The approved form of security furnished by the
contractor and his surety as a guarantee of good
faith on the part of the contractor to pay all
obligations arising from the contract

A

Payment bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The approved form of security furnished by the
contractor and his surety as a guarantee to the
quality of the materials and equipment installed and
the workmanship of the contractor

A

Guarantee bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The contract between the owner and the contractor
undertaking the project described in the contract
documents including all supplemental agreements
thereto and all general and special provisions
pertaining to the work or materials for the work

A

Agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The notice published by the owner or the invitations
issued to prospective bidders, giving information as
to the nature of the proposed project, conditions for
the issuance of contract documents, date of
bidding, and estimated cost or information that
would give the contractor a general idea of the
magnitude and extent of the project

A

Invitation to bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Additional information on Contract Documents
issued to bidders before the date of bidding

A

Bid bulletin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The list of instructions stipulating the manner on
how bids are to be prepared and conditions for the
award of the contract

A

Instructions to bidders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Graphical representations of the work involved in
the project. They include all supplementary details
and shop drawings

A

Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Printed documents stipulating the procedural and
the administrative aspects of the contract

A

General conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Instructions which may be issued prior to the
bidding, to supplement and/or modify drawings,
specs, and/or the general conditions of the contract

A

Special provisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Written or printed description of work to be done
describing the qualities of the materials and mode
of construction

A

Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Additional information which may be issued as an
addition or amendment to the provisions of the
specifications

A

Supplementary specs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
An outline specification enumerating the type or trade names of materials to be used
Schedule of matls/finishes
25
A listing of the different parts of the work indicating in each part the corresponding value in materials and labor, including an allowance for profit and overhead
Breakdown of work and corresponding value
26
Information, advice or notification pertinent to the project delivered in person or sent by registered mail to the individual, firm, or corporation at the last known business address of such individual, firm, or corporation
Written notice
27
A cataclysmic phenomenon (earthquake, flood, typhoon, cyclone, etc.) of nature and all misfortunes/accidents which human prudence could not foresee or prevent.
Act of God/Force majeure
28
Rain, wind, flood, or other natural phenomenon of inconsequential degree for the locality shall not be construed as an Act of God or Force Majeure and no reparation shall be made to the contractor for the damages to the work resulting therefrom
Act of God/Force Majeure
29
Time limit is the duration of time allowed by the contract for the completion of the prpoject in any stipulated portions thereof
Time limit
30
All laws, ordinances, and other governmental regulations applicable to the project
Local laws
31
This term includes labor or materials or both, as well as equipment, transportation, or other facilities necessary to commence and complete the construction called for in the contract
Work
32
This term means to purchase and/or fabricate and deliver to the jobsite or other location when so designated
Furnish
33
This term shall mean to build in, mount in positions, connect, or apply any object specified ready for the intended use
Install
34
This term shall mean to build in, mount in positions, connect, or apply any object specified ready for the intended use
Install
35
Means to furnish and install
Provide
36
Means as required or necessary for the complete execution of that portion of the work
Required/necessary
37
Shall mean approved, directed by, or acceptable to the architect unless otherwise stipulated in the contract
Approved, directed, or acceptable
38
Execution, Correlation, and Intent of Documents SIGNATURE ON DOCUMENTS ▪ The contract documents shall be signed in \_\_\_\_\_\_ by the owner and the contractor, **duly witnessed**
quintuplicate
39
INTENT OF CONTRACT DOCS ▪ The contract documents are \_\_\_\_\_\_and what is called for by any one shall be as binding as if called for by all ▪ The intention is to include **all labor and materials, equipment and transportation necessary for the proper execution of the work**
complementary
40
CONFORMITY TO CONTRACT DOCS ▪ If there are variances between the drawings and the specs, the provisions of the _____ shall prevail ▪ Any discrepancy found between the drawings and the specs and site conditions or any errors/omissions in the drawings or the specs **shall be immediately \_\_\_\_\_\_**
specs ## Footnote **reported to the architect or engineer who shall promptly correct said discrepancy**
41
CONFORMITY TO CONTRACT DOCS ▪ Responsibility for adequacy of the design and for sufficiency of drawings/specs shall be borne by the \_\_\_\_\_ ▪ The ______ shall furnish from time to time all additional detail drawings and instructions essential to the proper execution of the work
owner architect or engineer
42
CONFORMITY TO CONTRACT DOCS ▪ The ______ and ____ shall jointly prepare a schedule subject to change from time to time in accordance with the progress of the work
contractor and the architect/engineer
43
CONTRACTOR DOCUMENTS AT SITE OF WORK ▪ The contractor shall keep at the site, in good order, one copy each of the following:
▪ Drawings ▪ Specs ▪ Breakdown of work ▪ Schedule of construction ▪ All instructions and graphs available to the architect and his representatives
44
OWNERSHIP OF CONTRACT DOCS/MODELS ▪ The drawings, specs, and models including all additional instructions and copies thereof furnished for this work by the architect are the property of the \_\_\_\_\_
architect
45
COPIES OF DRAWINGS/SPECS ▪ The owner shall furnish the contractor **free of charge**\_\_\_\_ sets of drawings and specs
three
46
COORDINATION OF DRAWINGS/SPECS ▪ All drawings and models are intended to be coordinated with the \_\_\_\_, and also to form a part of the contract documents
specs
47
CLARIFICATION OF MEANING OF DRAWINGS AND SPECS ▪ The contractor shall **carefully examine,** compare and verify the date furnished by the drawings and specs ▪ Should a conflict occur between drawings, or a conflict between specs and drawings, the contractor shall be deemed to have estimated a more expensive way of doing work unless \_\_\_\_\_\_\_\_\_\_from the architect before submission of proposal as to which method or materials will be required
he shall have asked for and obtained a decision in writing
48
CLARIFICATION OF MEANING OF DRAWINGS AND SPECS ▪ If, after the award, the less expensive work is done, the contractor shall \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
credit the owner an amount equivalent to the difference between the more expensive and less expensive work
49
CLARIFICATION OF MEANING OF DRAWINGS AND SPECS ▪ If, in the contractor’s opinion, any work indicated in the drawings or specified in a manner will make it impossible to produce a first-class work, he shall \_\_\_\_\_\_\_\_\_\_ before proceeding with work. **If the contractor fails to make such a reference, no excuse will be entertained for failure to carry out work in the most satisfactory manner.**
refer the same to architect for interpretation
50
DISCREPANCIES IN DRAWINGS ▪ In case of In case of discrepancy in the figures or drawings, the \_\_\_\_\_\_\_\_\_\_\_, before any adjustment shall be made by the contractor save only at latter’s own risk and expense, the decision of the Architect on the adjustment of discrepancies so as to conform to the real intent of the drawings and specifications shall govern and shall be followed by the Contractor.
matter shall be submitted immediately to the Architect
51
SUPPLEMENTARY DRAWINGS AND INSTRUCTIONS ▪ The drawings referred to in these Specifications will be further supplemented by additional detail drawings and Instruction essential to the proper interpretation of the Drawings and the proper execution of the work. ▪ The Architect shall furnish with reasonable promptness such ____________ and \_\_\_\_
additional detail drawings and instructions.
52
SUPPLEMENTARY DRAWINGS AND INSTRUCTIONS ▪ All such additional detail drawings and Instructions shall be consistent with the contract documents, true developments thereof, and reasonably inferable wherefrom. ▪ All such additional drawings and Instructions are to be considered of equal force as those which originally accompany the specifications. The work shall be executed in conformity with such detail drawings and instructions, and the Contractor shall do no work without ________ and \_\_\_\_\_
proper drawings and instructions.
53
SCHEDULE FOR SUBMISSION OF SHOP DRAWINGS ▪ The contractor and the architect, if either one so requests, shall jointly prepare a schedule subject to change from time to time in accordance with the progress of the work, fixing the ____________ will be required, and the architect shall furnish them in accordance with that schedule
dates at which the various detail drawings
54
CONDITIONS FOR SHOP DRAWINGS ▪ The Contactor shall prepare at his own expense and submit with such promptness as to cause no delay in his own work or in that of any other contractor doing work on the same building, \_\_\_ copies of all shop or setting drawings, templates, patterns and models as well as schedule required for the work of the various trades
two
55
CONDITIONS FOR SHOP DRAWINGS ▪ The Architect shall pass upon them with reasonable promptness, making desired corrections. The Contractor shall make any corrections required by the Architect, file with him \_\_\_\_ corrected copies and furnish such other copies as may be needed.
two
56
CHECKING OF SHOP DRAWINGS ▪ Before submitting shop drawings for approval, the \_\_\_\_\_ shall check drawings of all subcontractors **for accuracy.** ▪ He shall see that all work contiguous with and having bearing on work indicated on shop drawings is accurately and distinctly illustrated and that work shown is in Conformity with Contract requirements
Contractor
57
IDENTIFICATION ▪ Shop drawings shall be numbered consecutively and represent:
▪ All working and erection dimensions. ▪ Arrangements and sectional views. ▪ Necessary details, including complete information for making connections with other work. ▪ Kinds of materials and finishes.
58
LETTER OF TRANSMITTAL ▪ Submission of shop drawings shall be accompanied by a __________ in duplicate, containing **name of project, contractor’s name, number of drawings, titles, and other pertinent data.**
letter of transmittal
59
CORRECTION, CHANGES, VARIATIONS ▪ The Contactor shall submit ____ sets of prints of shop drawings to the Architect for approval. ▪ Satisfactory shop drawings will be so identified by the Architect, dated and ____ copy thereof returned to the contractor. ▪ Should shop drawings be **disapproved** by the Architect, **one set of such shop drawings will be returned to the contractor with necessary corrections and changes to be made as indicated.**
three one
60
CORRECTION, CHANGES, VARIATIONS ▪ The _____ shall make required corrections and changes and resubmit shop drawings, in duplicate until the Architect’s approval is obtained. ▪ Upon receipt of approval the Contractor shall \_\_\_\_\_\_\_\_ on tracing and promptly furnish the Architect with ____ additional prints of approved drawings.
Contractor Insert date of approval three
61
CORRECTION, CHANGES, VARIATIONS ▪ No work called for by shop drawings shall be executed until the ______ approval is given. ▪ If shop drawings show variations from Contract requirements because of standard shop practice or other reasons, the\_\_\_\_\_\_ shall make specific mention of such variations in his letter of submittal.
Architect’s Contractor
62
RESPONSIBILITY FOR ACCURACY ▪ Approval of shop drawings will be general. It shall not relieve the ______ of responsibility for accuracy of such shop drawings, nor for Proper fitting and construction of work, nor for furnishing of materials or work required by the Contract and not indicated on shop drawings.
Contractor
63
RESPONSIBILITY FOR ACCURACY ▪ The Architect’s approval of such drawings or schedule shall not relieve Contractor from responsibility for deviations from Drawings or Specifications, unless he has in \_\_\_\_\_-, called the Architect’s attention to such deviations at the time of submission and secure his written approval, nor shall it relieve him from responsibility for errors of any sort in shop drawings or schedules
writing
64
SECTION 2
Laws, regulation, site conditions, permits, taxes
65
LAWS + REGULATIONS ▪ In general the ______ shall comply with all the laws, city and municipal ordinances , and all building Codes, rules and regulations, In so far as they are binding upon or affect the parties hereto, the work, or those engaged thereon. ▪ He shall also comply with regulations of firms furnishing utilities such as water, gas, telephone and electricity for the project.
contractor
66
LAWS + REGULATIONS ▪ If the Contractor performs any work contrary to such laws, ordinances rules and regulations, and without such notice to the Architect, he shall \_\_\_\_\_\_\_
bear all costs arising there from.
67
SITE CONDITIONS ▪ Before the bidding and the awarding f the contract, the Contractor is expected to \_\_\_\_\_\_\_\_\_\_\_\_\_\_, including local conditions and all other contingencies. ▪ **No extra compensation and extension of time** will be given due to negligence or inadvertence of the Contractor.
have visited the locality of the work and made his own estimates of the facilities and difficulties attending to the execution of the proposed contract
68
PERMIT + LICENSES ▪ All construction permits and licenses necessary for the execution of the work or of any temporary work and easements in relation thereto should be secured, and the corresponding required fees paid by the \_\_\_\_\_\_ ▪ The cost of such permits and licenses may, However be reimbursed by the _____ to the Contractor if specifically Stipulated in the prior Instructions of the Owner or the Architect.
Contractor. Owner
69
PERMIT + LICENSES ▪ The _____ shall solely responsible for the actions taken by him should the construction be started before acquiring the necessary permits and licenses. ▪ The Contractor shall also secure the \_\_\_\_\_\_\_\_but he shall not be responsible for the non-issuance or the delay in the Issuance thereof through no fault of the Contractor.
Contractor final occupancy permit
70
TAXES ▪ :Wherever the law of the place of building required sales, consumer, use, or other similar tax related or pertinent only to the construction of the project, the _____ shall pay such tax.
Contractor
71
STAKES/REFERENCE MARKS ▪ The ____ shall be responsible for the establishment of lot lines, boundary lines, easement, and benchmarks by a certified surveyor. ▪ The Owner may relegate this responsibility to the \_\_\_\_\_ provided the Owner shall pay for the cost of said services. ▪ All other grades, lines, levels and benchmarks necessary for the prosecution of the work shall be established and maintained by the \_\_\_\_\_\_
Owner Contractor Contractor.
72
STAKES/REFERENCE MARKS ▪ The _____ shall verify all grades, lines, levels and dimensions as indicated on the Drawings. **He shall report any error or in consistency to the \_\_\_\_\_\_ before commencing work.**
Contractor ## Footnote **Architect**
73
STAKES/REFERENCE MARKS ▪ The _____ shall provide and maintain wellbuilt batter boards at all corners. He shall establish benchmarks in not less that ____ widely separated places. As work progresses, he shall establish benchmarks at _____ giving exact levels of various floors. ▪ As work progresses the Contractor shall lay out exact location of all partitions as a guide to all trades.
contractor two each floor
74
LICENSED SURVEYOR ▪ The ______ shall pay for services of a licensed surveyor when so required to confirm and certify the location of column centers, piers, wall, pits, trenches, pipe work, culvert work, utility lines and work of similar nature required by the Contract. ▪ A copy of such certification shall be furnished the \_\_\_\_\_. It is the intention that the Surveyor’s Certification shall represent an Independent and disinterested verification of such lay-out.
Contractor Architect
75
LICENSED SURVEYOR ▪ It is the intention that the \_\_\_\_\_\_\_ shall represent an Independent and disinterested verification of such lay-out.
Surveyor’s Certification
76
FINAL CERTIFICATION ▪ Final certification shall be submitted upon \_\_\_\_\_\_\_, or upon completion of any section of work, if required by the Architect, and before \_\_\_\_\_\_is made.
completion of work final payment
77
FINAL CERTIFICATION ▪ Any exception or deviations from the Drawings shall be noted on \_\_\_\_\_\_\_\_, and there shall be included any maps, plots, notes, and the like necessary in the opinion of the Architect to constitute a full and complete report.
final certificate
78
SECTION III
Equipment and Materials
79
GENERAL ▪ All materials and equipment must conform to all laws, ordinances regulations and building codes now or hereafter may be in force and applicable during the period of construction ▪ the ______ shall obtain the necessary permits and pay the required fees therefore to the proper authorities.
contractor
80
GENERAL ▪ The _____ shall bear any and all damages by reason of any delay in the work arising from his failure to comply the provisions of his clause ▪ Note: should any revision or amendments to such laws, ordinances, regulations and building codes made during the construction period affect the cost or time of completion of the contract, **a corresponding adjustment shall made.**
Contractor
81
EQUIPMENT ▪ : In order to establish standards of quality, the \_\_\_\_\_ and _____ have in the detailed Specifications, referred to certain equipment by name and catalog number. ▪ This procedure is not to be construed as eliminating from competition other products of equal or better quality by other manufacturers where fully suitable in design.
Architect and the Engineer
82
EQUIPMENT ▪ The _____ shall furnish the complete list of proposed substitutions prior to the signing of the Contract, together with such engineering and catalog data as the Architect and the Engineer may require.
Contractor
83
EQUIPMENT ▪ The Contractor shall by abide by the Architect’s and the Engineer’s judgments when proposed substitute items of equipment are judged to be acceptable and shall furnish the specified item of equipment in such case. ▪ No substitute equipment shall be used unless approved in \_\_\_\_\_
writing.
84
EQUIPMENT ▪ The _____ and \_\_\_\_\_must review and approve the catalog data for all equipment before any equipment is ordered by the contractor ▪ The approval of the Architect and the Engineer shall not relieve the Contractor from responsibility for deviations from Drawings or Specifications, unless he has in _____ called their attention to such deviations at the time of submission
architect and the engineer writing
85
EQUIPMENT ▪ It shall be the responsibility of the _______ to insure that Items to be furnished fit the space available. He shall make necessary field measurements to ascertain space requirements, including those for connections
Contractor
86
MATERIALS, FIXTURES, FITTINGS FURNISHED BY THE CONTRACTOR ▪ Names of proposed manufacturers, material men, and dealers who are to furnish materials, fixtures, appliances or other fittings shall be submitted to the\_\_\_\_\_\_ for approval as early as possible, to afford proper investigation and checking.
Architect
87
MATERIALS, FIXTURES, FITTINGS FURNISHED BY THE CONTRACTOR ▪ No manufacturer will approved for any materials to be furnished under this Contract unless he shall be of good reputation, shall have a plant of ample capacity and adequate quality control and shall have successfully produced similar products. ▪ All transactions with manufacturers, or subcontractor, shall be through the \_\_\_\_\_.
Contractor
88
SAMPLES OF MATERIALS ▪ The \_\_\_\_\_\_shall furnish for approval, with such promptness as to cause no delay in work, samples as specified or required. Work shall be in accordance with approved samples. ▪ Unless otherwise specified, ____ samples shall be submitted, and of adequate size to show quality, type, colour, range, finish, and texture if material. ▪ Each sample shall be labeled, bearing material name and quality, the Contractor’s name, date project name, and other pertinent data.
Contractor three
89
SAMPLES OF MATERIALS ▪ Where specifications require manufacturer’s printed installation directions, such directions shall ____ submitted for approval. ▪ A letter of transmittal in _____ from the Contractor requesting approval shall accompany all sets of samples. ▪ Transportation charges to the Architect’s office must be prepaid on all samples forwarded. ▪ Materials shall not be ordered until approval is received in writing from the Architect. All materials shall be furnished substantially equal in every respect to approved samples.
accompany samples triplicate
90
TRADE NAMES AND SUBSTITUTES ▪ Whenever item or class of material is specified exclusively by trade name, by manufacturer’s name or by catalogue reference, only such item shall be used except as provided for in paragraph (b) hereof. ▪ No substitution shall be made for any material, article, or process required under Contract unless approved in written by the \_\_\_\_\_
Architect.
91
TRADE NAMES AND SUBSTITUTES ▪ Materials and articles installed or used without such approval shall be at the risk of subsequent \_\_\_\_\_ ▪ Samples of materials for use in reinforced concrete work such as steel bars cement, aggregates and their certificates of origin are to be approved by the \_\_\_\_
rejections. Architect.
92
TESTING SAMPLES OF MATERIALS ▪ The _____ shall submit to the Architect as many samples as may be needed for purposes of testing. Testing of all samples shall comply with the Specifications and government standards and shall be performed by competent entity or testing laboratory approved by the Architect. All cost for shipment, delivery, handling, and testing of samples are to be paid by the \_\_\_\_\_-
Contractor Contractor.
93
QUALITY OF MATERIALS ▪ Unless otherwise specified, all material shall be \_\_\_. The quality of materials shall be the best grade of their respective kinds for the purpose. The work shall be performed in the best and most acceptable manner in strict accordance with the requirements of the Drawings and Specifications. ▪ The decision of the _____ as to quality and quantity of work and material shall be final and precedent to the Contractor’s right to receive any money hereunder.
new. Architect
94
STORAGE AND STOCKPILING OF MATERIALS ▪ The ____ shall allot suitable space to sub-contractor for storage of their materials and for erection of their shed and tool houses. ▪ All cement, lime, and other materials affected by moisture shall be stored on platforms and protected from weather. Materials shall stored as to insure the preservation of their quality and fitness for the work. Stored materials shall be located so as to facilitate prompt inspection. ▪ Should it be necessary at any time to move materials, sheds, or storage platforms, **the Contractor shall do so at his own expense.**
Contractor
95
DEFECTIVE MATERIALS ▪ All materials not conforming to the requirements of these specifications shall be considered as defective. No defective materials, the d\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_, shall be used until approval has been given. Upon failure on the part of the Contractor to comply forthwith with any order of the Architect made pursuant to the provisions of this article, **the architect shall have authority to remove and replace defective materials**and to deduct the cost of removal and replacement from any money due or to become due the Contractor.
efects of which have subsequently corrected
96
DEFECTIVE MATERIALS ▪ The apparent silence of the Specifications, Drawings, Special Provisions and supplementary Specifications, as to any detail or description concerning any point shall be regarded as meaning that only the best general practice is to prevail and that only materials and workmanship of \_\_\_\_\_\_quality are to be used.
first class
97
DEFECTIVE MATERIALS ▪ Failure or neglect on the Architect, or any of his agents to condemn or reject bad or interior materials shall _________ if said bad or inferior materials are discovered at any time prior to the final acceptance f the work by the Owner and the release of the Contractor.
not be construed to imply an acceptance of the materials
98
IMPORTED MATERIALS, FIXTURES AND EQUIPMENT ▪ The _____ shall take cognizance of the in element of the Contract. He shall make early arrangements for the purchase and delivery of all specified imported materials, fixtures, appliances and equipment in order to avoid delay in the completion of the work. ▪ No extension of time or substitution of materials shall be allowed due to negligence or inadvertence of the Contractor.
Contractor
99
OWNER-SUPPLIED MATERIALS ▪ Materials, equipment, fixtures, appliances and fittings specifically indicated shall be furnished by the ____ in accordance with schedule of delivery agreed upon between the Owner and the Contractor. The fact that the Owner is to furnish material is conclusive evidence of its acceptability for the purpose intended and the Contractor may continue to use it until other directed.
Owner
100
OWNER-SUPPLIED MATERIALS ▪ If the Contractor discovers any defect in material furnished by the Owner, he shall notify the \_\_\_\_\_\_. The Contractor shall be responsible for material loss or damage after receipt of any material, equipment, fixture, and appliance or fitting unless the same has been installed and accepted for safe keeping by the Owner or his representative.
Architect
101
ROYALTIES AND PATENTS ▪ The ______ shall pay all royalties and license fees on all patented materials and processes furnished by him. He shall defend all suits or claims corresponding thereto for infringement of any patent rights and shall save the owner harmless from loss on account thereof.
Contractor
102
MANUFACTURER’S DIRECTIONS ▪ All manufactured articles, materials, equipment, appliances, fixtures and fittings shall be applied, installed, connected, erected, used, cleaned, and conditioned. In accordance with manufacturer’s printed directions, unless herein specified to the contrary, where reference is made to manufacturer’s directions. The _____ shall submit specified number of copies of such directions to the Architect
Contractor
103
SECTION IV
Premises and Temporary Structures
104
USE OF PREMISES ▪ The ___ shall confine his apparatus, the storage of materials, and the operations of his workmen to limits indicated by the law, ordinances, permits, or directions of the Architect and shall not unreasonably encumber the premises with his materials.
Contractor
105
USE OF PREMISES ▪ The ____ shall not load or permit any part of the structure to be loaded with a weight that will endanger its safety. The Contractor shall enforce the Architect’s Instructions regarding signs, advertisements, fires and smoking.
Contractor
106
Temporary structures and facilities TEMPORARY OFFICE AND CONTRACTOR’S BUILDING ▪ The\_\_\_\_\_ shall at all times provide and maintain adequate weather tight temporary office with water, light, telephone, and toilet facilities for the use of the Architect, resident engineers, Inspectors, contractor, and sub-contractors.
Contractor
107
TEMPORARY OFFICE AND CONTRACTOR’S BUILDING ▪ This office shall be provided with wooden floor raised above the ground, windows, doors and locks, tables, closet, blackboard, tack board, benches and racks for drawings. One room of approximately\_\_\_ square meters shall be provided for the Architect’s use.
12
108
TEMPORARY HOUSING FOR WORKERS ▪ The temporary buildings for housing men, or the erection of tents or other forms of protection will be permitted only at such places as the ____ or ____ shall designate: and the sanitary condition of the grounds I or about such structures shall at all times be maintained in a manner satisfactory to the owner and the Architect. Nobody shall be allowed to ____ or \_\_\_\_within the building line of the project under construction.
owner or Architect sleep or cook
109
TEMPORARY SANITARY FACILITIES / FIRST AID STATION ▪ The ____ shall provide construct and maintain for the duration of the contract, ample sanitary toilet accommodation and other necessary conveniences including water connections for the use of personnel and laborers on the work, properly secluded from public observation. In such manner and at such points as shall be approved by the Architect, and their use shall be strictly enforced. He shall keep such places clean and free from flies: remove all connections and appliances connected therewith prior to the completion of the contract and leave the premises perfectly clean.
Contractor
110
TEMPORARY BARRICAES AND GUARD LIGHTS ▪ The _____ shall furnish and put up all temporary barricades and guard light necessary for the, proper prosecution and completion of work. The guard lights at the top to the false work tower, barricades, railing, ET, shall be provided and maintained by the Contractor throughout the prosecution of the project.
Contractor
111
TEMPORARY WATER, POWER AND TELEPHONE FACILITIES ▪ The _____ shall make all necessary arrangements with the local utility companies in order that temporary facilities for water, power, and telephone are sufficiently provided till the completion of the work. All expenses incurred in connections therewith shall be paid by the \_\_\_\_\_
Contractor Contractor
112
TEMPORARY SIGNS ▪ No signs advertisements will allowed to be displayed without the ____ approval. The Contractor may erect one painted sign as approved by the Architect, giving names and addresses of the Architect. Contractor and various sub-contractors. The Architect shall approve size, colour, lettering, and sign locations.
Architect’s
113
TEMPORARY ROADWAYS ▪ The ____ shall construct and properly maintain temporary roadways within and adjacent to site in order to provide proper access to the building. Temporary roadways shall adequately sustain loads to be carried on them and be so constructed as not to endanger existing or newly installed underground structures.
Contractor
114
TEMPORARY STAIRS, LADDERS, RAMPS, AND RUNWAYS ▪ The ______ shall furnish and maintain all equipment such as temporary stairs, ladders, ramps, scaffolds, runways, derricks, chutes, and the like as required for proper execution of work by all trades. All such apparatus, equipment, and construction shall meet all requirements of _____ and other laws applicable thereto.
Contractor Labor Law
115
TEMPORARY ELEVATORS / HOISTS ▪ The _____ shall install and operate an adequate number of hoists and elevators. No hoists shall be constructed at such locations as will interfere with or affect construction of floor arches (or work of other Contractors). They may be located at exterior sides of structure and extend upward adjacent to line of window openings. They shall be located at a sufficient distance from exterior walls and be so protected as to prevent damage, staining or marring the permanent work.
Contractor
116
TEMPORARY ENCLOSURES ▪ The ______ shall provide temporary weather tight enclosure for all exterior openings as son as walls and roof are built so as to protect all work from. All exterior doors shall be equipped with self-closing hardware and padlocks. All exterior windows shall be provided with temporary sash frames securely fastened in place buy removable when required. Such sash frames shall be covered in approved manner.
Contractor
117
TEMPORARY / TRIAL USAGE ▪ Temporary or trial usage by the ____ of any mechanical device, machinery, apparatus, equipment, or any work or materials supplied under Contract before final completion and written acceptance y the Architect shall not be construed as evidence of the Architect’s acceptance of same.
Owner
118
TEMPORARY / TRIAL USAGE ▪ The _____ shall have privilege of such temporary or trial usage, for such reasonable length of time as the Architect shall deem to e proper. No claim for damage shall be made by the Contractor for injury to or breaking of any parts of such work which may be caused by weakness or inaccuracy of structural parts or by defective material or workmanship. ▪ If the Contractor so elects, he may, at his on expense, place persons satisfactory to the Architect to make such trial usage.
Owner
119
REMOVAL OF TEMPORARY STRUCTURES ▪ The _____ shall remove all temporary work from premises, erected by him and shall clean the premises as a condition for completing the work and before acceptance of the work by the Owner.
contractor
120
SECTION V
Protection of Work and Property
121
SAFEGUARD MEASURES ▪ The _____ shall put up ad continuously maintain adequate protection of all his work from damage and shall protect the Owner’s property, as well as all materials furnished and delivered to him by the Owner. He shall make good any such damage, injury or loss, except such as may caused by agents or employees of the Owner, or due to causes considered as Act of God.
Contractor
122
SAFEGUARD MEASURES ▪ The ____ shall provide reliable and competent watchmen to guard the site and premises, from commencement of operation until building is fully completed. Provide all doorways with locks under control of the Contractor, who shall lock doors at the close of each day’s work. In the event that the Architect at any time deems watchmen service inadequate or incompetent, the contractor shall increase or change the watchmen personnel to the _____ satisfaction.
Contractor Architect’s
123
SAFEGUARD MEASURES ▪ \_\_\_\_\_on premises shall be prohibited except in designated places and signs to this effect shall be posted conspicuously. Fires shall not be built on premises except by express consent of the Architect.
Smoking
124
SAFEGUARD MEASURES ▪ The _____ shall provide and maintain barrels of water and fire buckets on premises for fire protection. Such equipment shall not be used for other purpose. ▪ The Contractor shall provide and maintain in good working order and adequate number of fire extinguishers.
Contractor
125
OLD MATERIALS ▪ All old materials of value found the ____ upon the work, shall be carefully piled where designated by Owner or the Architect and the Contractor shall be responsible for the same until final acceptance of the work.
Contractor
126
TREES AND OTHER PLANTS ▪ Existing trees, plants, shrub, etc., which are to remain shall be ____ and otherwise protected from damage. No trees within site or located outside building lines shall be cut or removed without specific approval from the ____ and \_\_\_\_
boxed Owner and the Architect.
127
TREES AND OTHER PLANTS ▪ all trees and other plants that need to be transplanted elsewhere within _____ meters from the building lines shall be done by the contractor at his own expense in accordance with instructions from the Architect or from the authorities concerned.
fifty(50)
128
TREES AND OTHER PLANTS ▪ undue damage to trees, plants, shrub, streets, sidewalks, etc., resulting from and in connection with construction work shall be made good and /or replaced by the ____ his own expense to the satisfaction of the Owner and the architect.
Contractor
129
DRAINAGE ▪ If it is necessary in the prosecution of the work to interrupt or obstruct the natural flow of rivers or streams, the drainage of the surface, or flow of artificial drains, the _____ shall provide for the same during the progress of the work in such a way that no damage shall result to either public or private interest. For any neglect to provide for other natural or artificial drainage which he may have interrupted, he shall solely be held liable for all damages which may result there from during the progress of work.
Contractor
130
Protection of adjacent property and existing utilities CONTRACTOR’S SOLE RESPONSIBILITY ▪ The ____ shall adequately protect adjacent properly as provided by law and the contract Documents. The construction building or work, In addition to any neighboring properly or building which may be manner, must be thoroughly and substantially braced against winds, floods, settling, falling, or like similar occurrences, and when necessary, covered and protected from sun and rain at the Contractor’s expense. The _____ shall solely be liable and pay for all damages occasioned in any manner by his acts or neglect, or of his agents, employees, or workmen.
contractor Contractor
131
EXISTING UTILITIES ▪ Existing utilities, if damaged due to negligence or fault of the Contractor, shall be repaired by the \_\_\_\_\_ at his expense.
Contractor
132
Protection of life, work and property during an emergency AUTHORIZATION OF CONTRACTOR ▪ In an emergency affecting safety of life or of the work or of adjoining properly, the\_\_\_\_\_, without special instruction or authorization from the Architect or Owner, Is hereby permitted to act, at his discretion, to prevent such threatened loss or injury and he shall so act, at his discretion, to prevent such threatened loss or injury and he shall so act, without appeal, If so instructed or authorized. Any compensation claimed by the _____ on account of emergency work, shall be determined by agreement of arbitration.
Contractor, Contractor
133
SECTION VI
Labor, Work, and Payments
134
Labor CHARACTER OF WORKMEN ▪ The Contractor shall employ only competent and efficient engineers, superintendents, foremen, mechanics, laborers, or artisans. Whenever, in the opinion of the \_\_\_\_, any employee is careless or incompetent or obstructs the progress of the work or acts contrary to instructions or conducts himself improperly, the Contractor shall, upon written request of the Architect, discharge or otherwise remove him from work and not employ him again upon it.
Architect
135
CHARACTER OF WORKMEN ▪ Should the Contractor fail to remove unsatisfactory workmen or fail to furnish suitable and sufficient equipment or personnel for the proper prosecution of the work, the ____ may withhold payment which are or may become due, or may suspend the work until such orders are complied with.
Architect
136
SUPERINTENDENCE AND SUPERVISION ▪ The \_\_\_\_\_\_, if supervises the work personally, **must be a licensed engineer or architect** acceptable to the Architect who will supervise the work personally and inspect at least once a week. ▪ The Contractor shall keep in his project site, during the work’s progress, a competent engineer or Superintendent and any necessary assistants, all satisfactory to the Architect.
Contractor
137
SUPERINTENDENCE AND SUPERVISION ▪ The _______ or ____ shall represent the Contractor in his absence and all directions given to him shall be as binding as if given to the Contractor. He shall have full authority to execute the orders or directions of the Architect without delay and to prompt supply such materials, tools, paints, equipment, and labor as may be required.
Project engineer or Superintendent
138
Work METHODS AND APPLIANCES ▪ The ____ shall use such methods and appliances for the performance of all the operations connected with the work embraced under this Contract as will produce a satisfactory quality of work and rate of progress which, in the opinion of the Architect, will ensure the completion of the work within the contract time.
Contractor
139
METHODS AND APPLIANCES ▪ If, at any time before the commencement or during the progress of the work, such methods or appliances appear to the Architect to be inefficient or inappropriate for producing the quality of the work required, or insuring the required rate of progress, the ____ may order the Contractor to increase the rate of their efficiency or to improve their system of operation.
Architect
140
METHODS AND APPLIANCES ▪ The Contractor must comply with such order. Failure, however, of the Architect to demand such increase of efficiency or improvement of character of methods and appliances shall not relieve the _____ from his obligation to turn out such quality of work and rate of progress as are called for in t his contract.
Contractor
141
METHODS AND APPLIANCES ▪ The _____ shall, if required, furnish to the Architect for approval full information and satisfactory evidence as to the name of the manufacturer of machinery, or mechanical or other equipment which he contemplates using together with the performance capacities and other pertinent information.
Contractor
142
LAYING OUT THE WORK ▪ The Contractor shall lay out the lines and grades of the work as per conditions set forth under **Article 7.03 (Construction Stakes and Reference Mark) of the General Conditions.**
143
LAYING OUT THE WORK ▪ All stakes benchmarks, etc., placed by the Contractor in laying out the work, approve by the Architect, shall be ___________ by the Contractor. In case such stakes or marks are displaced or rendered useless through the carelessness or neglect of the Contractor or of his agents, employees, or workmen, they should be replaced by the \_\_\_\_\_\_\_ at his own expense.
carefully guarded and preserved Contractor
144
INSPECTION OF WORK ▪ The _____ \_\_\_\_\_\_ and their representatives shall at all times have access to the work wherever it is in preparation or progress and the Contractor shall provide proper facilities for such access and for inspection.
Owner, Architect
145
INSPECTION OF WORK ▪ a. If the specifications, the Architect’s Instructions, laws, ordinances or any public authority require any work to be specifically tested or approved, the ____ shall give the Architect and other parties required to make the inspection, timely notice of its readiness for inspection, and the date fixed for such inspection
Contractor
146
INSPECTION OF WORK ▪ Inspections by the Architect shall be promptly made and were practicable, at the source of supply. If any work should be covered up without approval or consent of the Architect, it must, if required by the Architect, be uncovered for examination at the _________ expense.
Contractor’s
147
INSPECTION OF WORK ▪ b. Re-examination of questioned work may be ordered by the Architect and is so ordered; the work must be uncovered by the \_\_\_\_\_\_. If such work be found not in accordance with the Contract Documents, the _____ shall pay the cost.
Contractor Contractor
148
INSPECTION OF WORK ▪ c. The _____ shall furnish promptly without additional charge all reasonable facilities, labor, and materials necessary for the safe and convenient inspection and tests that may be required by the inspectors. All inspection and tests shall be performed in such manner as not to unnecessarily delay the work.
Contractor
149
INSPECTION OF WORK ▪ d. If there are indications that the work done are not in accordance with plans and specification, the ____ may at any time before final acceptance of the entire work make an examination of the work already completed. By removing or tearing out same, the Contractor shall, on request, promptly furnish all necessary facilities, labor, and materials.
Architect
150
INSPECTION OF WORK ▪ If such work is found to be defective in any material respect due to fault of the Contractor, or his subcontractors, he shall defray all the expenses of such examination and of satisfactory reconstructions. If, however, such work is found to meet the requirements of the Contract, the actual cost of labor and materials necessary involved in the examination and replacement plus __ percent, shall be allowed the Contractor and shall in addition, if completion o the work has been delayed hereby, be granted a suitable extension of time on account of the additional work involved.
15
151
DEFECTIVE WORK ▪ Defective work may be condemned by the \_\_\_\_\_ at any time before the final acceptance of the work, and when such work has been condemned it shall be taken out immediately by the _____ and rebuilt in accordance with the Drawings and Specifications.
Architect Contractor
152
DEFECTIVE WORK ▪ Failure or neglect on the part of the Architect or any of his agents to condemn or reject bad or inferior work, shall not be _____ to imply an acceptance of the work of the same if such bad or inferior work is discovered at any time prior to the final acceptance of the work by the Owner and the release of the Contractor.
construed
153
WORK DURING EMERGENCY ▪ The ______ shall perform any work and shall furnish and install all materials and equipment necessary during an emergency endangering life or property. In all cases he shall notify the Architect and the Engineer of the emergency as soon as practicable, but he shall not wait for instructions before proceeding to properly protect both life and property.
Contractor
154
INCREASED OR DECREASED QUANTITIES OF WORK ▪ Adjustments of Drawings to suit field conditions which cannot be foreseen at the time of calling for bids may be necessary during construction. It is the essence of the Contract to recognize such changes in Drawings as constituting a normal and expected margin of adjustment, and not involving nor permitting change or modification of Contract Prices, provided only, that resulting overruns or under runs from the quantities in the Proposal do not exceed _____ percent. In case of discrepancy, the matter shall be submitted immediately to the Architect, before any adjustment shall be made by the Contractor, otherwise it shall be at his own risk and expense.
five
155
CHANGES ORDERED BY THE OWNER ▪ The ____ may at any time, without invalidating the Contract and without notice to the sureties, order extra work or make changes by altering, adding to or deducing from the work, as covered by the Drawings and Specifications of this Contract and within the general scope thereof. Such changes shall be ordered by the Owner in ___ , and no change or omission from the Drawings and Specifications shall be considered to have been authorized without written instructions signed by the Owner.
Owner writing
156
CHANGE OF SUB-SURFACE CONDITIONS ▪ If, during the progress of the work, sub-surface conditions at the site materially different from those shown on the Drawings or indicated in the Specifications are discovered or encountered, the attention of the _____ shall be called immediately to such conditions before they are disturbed. The Architect shall thereupon promptly investigate the conditions, and if he finds that they materially differ from those shown on the Drawings or indicated in the Specifications, he shall at once, with the approval of the Owner, make such changes I the Drawings and Specifications as he may find necessary.
Architect
157
ADJUSMENTS OF CONTRACT ▪ All such work shall be executed under the conditions of the original contract. If such changes cause an increase or decrease in the amount due under this Contract, or in the time required for its performance, an equitable adjustment shall be made and the contract shall be modified I writing accordingly. The express consent of the sureties shall be obtained in writing. In the event that the work involved is increased y such changes, the ______ shall furnish proportionate additional performance bond.
Contractor
158
VALUE OF EXTRA WORK ▪ The value of extra work or change shall be determined in any one or more of the following ways:
1. By estimate and acceptance in a lump sum 2. By unit price stipulated I the Contract or subsequently agreed upon, provided the extra or credit does not exceed 25% of original contract of the particular work involved. 3. By actual direct cost plus Fifteen Percent for contractor’s profit, overhead and contractor’s tax.
159
VALUE OF EXTRA WORK ▪ Under case (3), he shall keep and present such formats the ____ may direct, a correct account of the cost, together with vouchers. In any case, the Architect shall certify to the amount including the ____ Percent allowance for overhead and profit due the Contractor.
Architect Fifteen
160
PERIOD OF WHICH CLAIM FOR ADJUSTMENT HAS TO BE ASSERTED ▪ Any claim for adjustment involving questions of fact must be asserted fifteen days from the date of charge is ordered unless the ____ shall for proper cause extend such time. Except as otherwise specifically provided in this Contract, all disputes concerning questions of act arising under this Contract shall be decided by the Architect or his duly authorized representative. Nothing, however, as provided for in Article 20.07 shall excuse the \_\_\_\_\_ for proceeding with the prosecution of the work so changed.
Architect Contractor
161
CHANGES ORDERED BY THE ARCHITECT ▪ In giving instructions, the ____ shall have the authority to make **minor changes** in the work, not involving extra cost, and not inconsistent with the design concept of the building.
Architect
162
AWARD OF EXTRA WORK TO OTHER CONTRACTORS ▪ Incase any extra work shall be required in the proper performance of the work contemplated under this Contract, it is understood that if the Contractor and the Owner fail to arrive at any agreement as to the price of such extra work, the \_\_\_\_ reserves the right to have such extra work done by any other person, firm, or corporation that said Contractor.
Owner
163
CLAIMS FOR EXTRA COST ▪ If the Contractor claims that any Instructions by drawing or otherwise involve extra cost under this Contract, he shall give the Architect written notice thereof within _____ days after the receipt of such instruction, and, in any event, before proceeding to execute the work, except I emergency endangering life or property, and the procedure shall be as provided for in Article 20.05 (Work During an Emergency) of the General Conditions. No such claim shall b e valid unless so made.
fifteen
164
CLAIMS FOR EXTRA COST ▪ In like manner, if the Contractor incurs a delay in the mobilization and/or in the progress of his work for reasons attributable to the Owner, e.g., Ownersupplied materials not arriving on time, movements or work executed by the Owner which interfere with the progress of the Contractor’s work, delay decisions and other matters related thereto, he shall give the _____ written notice thereof within fifteen days after recognition of such delays. No such claim shall be valid unless such written notice has been executed.
Architect
165
CLEANUP AT COMPLETION OF WORK ▪ The Contractor shall at all times keep the premises free from accumulations of waste materials or rubbish caused by his employees or work. At the completion of the work, he shall \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
remove all his rubbish from and about the building and all his tools, scaffolding and surplus materials and turn over the work for occupancy with:
166
CLEANUP AT COMPLETION OF WORK ▪ All dirt, stains and the like on all finishing of floors, walls and ceiling, decorative work, finishing hardware and fixtures, removed; ▪ All woodwork, finishing hardware and all metal works, cleaned and polished.
167
CLEANUP AT COMPLETION OF WORK ▪ All glazing marble and tile work washed and polished. The ______ shall so clean the building site **as shown in the Drawings** and all areas which the Contractor used in the operation of the project. ▪ At no time shall any rubbish be thrown from windows or other parts of the building without the use of rubbish chutes.
Contractor
168
USE OF COMPLETED PORTIONS OF WORK ▪ The _____ shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding that the time for completing the entire work or such portions may not have expired; but such taking possessions and use shall not be deemed an acceptance of any work not completed in accordance with the Contract Documents.
Owner
169
USE OF COMPLETED PORTIONS OF WORK ▪ Neither shall it be deemed a waiver by the Owner of the rights to claim for damages due to delays in the completion of the work. If such prior use increase the cost of or delays the completion of uncompleted work, the ______ shall be entitled to such extra compensation, or extension of time or both, as agreed upon prior to the occupancy.
Contractor
170
CERTIFICATION OF COMPLETION OF WORK ▪ Upon due notice from the Contractor that he has substantially completed the work; the Architect shall make an inspection of the project. Substantial completion shall mean that the value of the work completed shall not be less than \_\_\_\_% of the contract amount and that the remaining unfinished work shall be of a minor nature only.
98%
171
CERTIFICATION OF COMPLETION OF WORK ▪ If the contract covers the furnishing and/or installation of equipment, fixtures and utilities, said equipment, fixtures and utilities, shall be fully \_\_\_\_\_\_\_\_\_in order that the work can be considered as substantially complete. However, should the Contractor, through no fault of his, be unable to test run in order that the work can be considered as substantially completed.
tested and test- run
172
CERTIFICATION OF COMPLETION OF WORK ▪ However, should the Contractor, through no fault of his be unable to test run the equipment at the time of substantial completion, he shall be given the necessary time extension for that portion of the work. As soon as, in the opinion of the \_\_\_\_\_\>the work shall have been substantial completed and shall have satisfactorily passed any final test of materials that may be prescribed by the Contract, the Architect shall issue a Certificate of Completion in respect to the work.
Architect,
173
CERTIFICATION OF COMPLETION OF WORK ▪ Even before the completion other whole work, upon written application of the Contractor, the \_\_\_\_\_\_ may likewise issue such a Certificate of Completion with respect to any substantial part of the work which has been completed to the satisfaction of the Architect and occupied or used by the Owner.
Architect
174
CERTIFICATION OF COMPLETION OF WORK ▪ In all cases, prior to the issue of sold Certificate of Completion, the ______ shall execute a written undertaking to finish any outstanding work during the Period off making Good of Known Defects or Faults as defined in Article 20.12 hereof.
Contractor
175
PERIOD OF MAKING GOOD OF KNOWN DEFECTS OR FAULTS ▪ The expression “Period of Making Good off Known Defects or Faults” shall mean a period of not more than ____ calendar days, unless otherwise expressly named in the contract, calculated from the date of issue of the Certificate of Completion of the whole work or of any part thereof, in accordance with Article 20.11.
sixty
176
MAKING GOOD OF KNOWN DEFECTS OR FAULTS ▪ The Contractor shall execute at his own expense all work necessary for making good of known defect, Imperfections or faults ( fair, wear and tear expected) within ____ days after its expiration as a result of an inspection made by or on behalf or the Architect prior to its expiration.
fifteen
177
MAKING GOOD OF KNOWN DEFECTS OR FAULTS ▪ If, in the opinion of the Architect, the defect or fault is due to the owner or Owner’s representative, the value of such work shall be _____________ . If the Contractor shall fail to do any work as aforesaid, the Owner shall upon written notice to the contractor be entitled o carry out such work u his own workmen or but other contractors, and if such work which the contractor should have carried out is at the Contractor’s cost, the Owner shall be entitled to recover from the Contractor the cost thereof, or may deduct the same from any monies due or may become due to the Contractor.
ascertained and paid for as it were additional work
178
SEARCH FOR CAUSES OF DEFECTS OR FAULTS ▪ The Contractor shall, if required by the Architect in writing, search for the cause of any defect, imperfection or fault under the directions of the Architect. Unless such defect, imperfection or fault shall be one for which the Contractor is not liable under the Contract, the cost of the work is carried out by the Contractor in searching for said defect shall be borne by the \_\_\_\_
Owner.
179
SEARCH FOR CAUSES OF DEFECTS OR FAULTS ▪ But if such defect, imperfection, or fault shall be one for which the Contractor is liable, the costs of the work carried out in searching said defects shall be ______ and he shall in such case, repair, rectify and make good such defect, imperfection or fault at his own expense, in accordance with the provisions of Article 20.13 hereof.
borne by the contractor
180
Time of completion of work NOTICE TO PROCEED ▪ Following the execution of the Contract Agreement but the Owner, written Notice to Proceed with the work shall be given to the contractor. The Contractor shall begin and shall prosecute the work regularly and uninterruptedly, thereafter (unless otherwise directed in writing by the \_\_\_\_)with such force as to secure the completion of the work within the time stated in the contract.
owner)
181
NOTICE TO PROCEED ▪ If the ______ undertakes actual construction on the proposed work including the delivery of equipment or materials (In the case for furnishing materials) or the performance of any other kind of work whatsoever, before he receives a copy of the duly executed Contract or Notice to Proceed, he does so in his own risk,
Contractor
182
NOTICE TO PROCEED ▪ The Contractor shall complete, in an acceptable manner, all of the work contracted for in the time stated in the Contract. Computation of Contract Time shall commence on the _____ day from receipt of Notice to proceed, unless otherwise stipulated in the contract, and every calendar following, shall be counted as a working day
seventh (7th)
183
SCHEDULE OF COMPLETION ▪ The Contractor shall submit, for approval, the Schedule of Construction Work in _________ form or any other form acceptable to the Architect indicating the approximate date each item will be started and completed, the equipment to be used and number of men to be employed to complete it, in accordance with his schedule.
Critical Path Method
184
SCHEDULE OF COMPLETION ▪ The progress of the work shall be at a rate sufficient to complete the Contract in an acceptable manner within the period of time specified. If it appears that the rate of progress is such that the Contract will not be completed within the time limit, the _____ may order the Contractor to take such steps as he considers necessary to complete the Contract within the period provided.
Architect
185
EXTENSION OF TIME ▪ The Contractor will be allowed an extension of time based on the following conditions: ▪ Should the Contractor be obstructed or delayed in the prosecution or completion of the work by the act, neglect, delay, or default the owner or any contractor employed by the Owner on the work; by strikes or lockouts, by and Act of God or Force Majeure as defined in Article 1.26; by delay authorized by the Architect pending arbitration; then the Contractor shall within _____ days from the occurrence of such delay file the necessary request for extension. The _____ may grant the request for extension for such period of time as he considers reasonable.
fifteen (15) Architect
186
EXTENSION OF TIME ▪ However, no such extension of time shall be granted for any alleged failure of the Owner to furnish materials or information unless they be required in the proper prosecution of the work in the order prescribed by the Architect and unless the Contractor shall have made written request for them at ____ \_days before they are actually needed.
ten (10)
187
EXTENSION OF TIME ▪ The ________ must be attached to any request of the Contractor for an extension of time and submitted to the Owner for consideration. ▪ If the satisfactory fulfillment of the Contract shall require the performance of work in greater quantities than those set forth in the Contract, the time allowed for performance shall be increased in the same ratio that the total cost of work actually performed shall be the total cost in Contract.
WRITTEN CONSENT OF THE BONDSMEN
188
EXTENSION OF TIME ▪ However, if in the opinion of the \_\_\_\_, the nature of the increased work is such that the new Con tract Time as computed approve is unreasonably short, the time allowance for any extension and increases shall be as agreed upon writing. ▪ If no schedule or agreement stating the dates upon which drawing shall be furnished is made, then no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and unless such claim be reasonable.
Architect,
189
EXTENSION OF TIME ▪ If the work is interrupted for any reason, it must be promptly resumed on the removal or cessation of the cause of delay. ▪ The Contractor shall give written notice to the Architect at least _____ days prior to beginning, suspending (Except in case of accident), or resuming the work to the end that the Architect may make the necessary preparations for inspection without delaying the work. All delays or losses resulting from failure of the Contractor to give such notice will be at the Contractor’s risk; and all extra costs to the Owner for such delay (said costs to be determined by the Architect) shall be deducted from the Final Payment.
ten (10)
190
LIQUIDATED DAMAGES ▪ It is understood that time is an essential feature of this contract and that upon failure to complete the said contract within the contract time, the Contractor shall be required to pay the Owner the liquidated damages in the amount stipulated in the Contract Agreement, the said payment to be made as liquidated damages, and not by way of penalty. The Owner may deduct from any sum due or to become due the Contractor any sums accruing for liquidated damages as herein stated. For purposes of calculating, the actual completion date shall be the \_\_\_\_\_\_\_\_\_\_\_
date certified by the Architect under Article 20.11 hereof.
191
Payments DETAILED BREAKDOWN OF CONTRACT AMOUNT ▪ Except in cases where unit prices from the basis for payment under the Contract the Contractor shall, within\_\_\_\_\_ days from the receipt of Notice to Proceed, submit a complete Breakdown of Work and Corresponding value of the Contract Amount showing the value assigned to each part of work, including the allowance for profit and overhead. Upon approval of the Breakdown of Work and Corresponding Value by the Architect, it shall be used as the bass for all Requests for Payment.
fifteen (15)
192
REQUESTS FOR PAYMENT ▪ the Contractor may submit periodically but not more than once each month a Request of Payment for work done. The Contractor shall furnish the Architect all reasonable facilities required for obtaining the necessary information relative to the progress and execution of the work. Each Request for Payment shall be computed from the work completed on all items listed in the Breakdown of Work and Corresponding Value, less the \_\_\_%retention unless otherwise agreed upon and less previous payments. When 50% of the Contract has been accomplished, no further retention shall be made on the balance of the Contract.
10%
193
REQUESTS FOR PAYMENT ▪ In general, no payment shall be made for materials or items not incorporated in the work. However, exception to this condition may be made in the case of materials or items which may require immediate acquisition and compensation du to shortages or import or transportation difficulties. In the event of such exceptions, payment shall be conditioned upon the submission by the Contractor of bills of sale or such other procedures as will establish the Owner’s title to such material or item or otherwise adequately protect the _____ Interest.
Owner’s
194
PROGRESS PHOTOS ▪ The Contractor at his own expense shall furnish the Architect progress photographs which shall be taken \_\_\_\_\_, starting when the work begins and continuing so long as the work is in progress in the outside of the building, from station points designated by the Architect.
monthly
195
PROGRESS PHOTOS ▪ The photographs shall be \_\_\_\_\_. At each period four exposures shall be taken, one on each side of the building. _____ prints dull finish, (2 copies for each exposure) shall be delivered to the Architect and all negatives shall bear the date of exposure and name of the work. ▪ No partial payment shall be considered for approval without the above mentioned prints accompanying the Request for Payment.
6”x8” Eight (8)
196
ARCHITECT’S ACTION ON A REQUEST FOR PAYMENT ▪ Within ____ days after receipt of any Request for Payment by the Contractor, the Architect shall either issue a Certificate of Payment or withhold the Request of Payment. When the Architect decides to withhold the Request for Payment, he shall inform the contractor in writing the reasons for withholding it. If the Contractor and Architect cannot agree on a revised amount, the Architect will issue a certificate of payment for the amount for which he is able to make representations to the owner.
fifteen
197
ARCHITECT’S ACTION ON A REQUEST FOR PAYMENT ▪ The _______ shall include the value of work accomplished by the Contractor during the period covered buy the certificate and recommendation to the Owner for payment in an amount the Architect decides to be properly due.
Certificate of Payment
198
APPROVAL WITHHELD ▪ The Architect may recommend withholding of payment in whole or in part on any approved Request for Payment on account of any of the following reasons:
▪ Defective work not remedied ▪ Claims filed or reasonable evidence indicating probable filing of claims ▪ Failure of the Contractor to make payments properly subcontractors or for material or labor. ▪ A reasonable doubt that the Contract can be completed for the balance then unpaid. ▪ Damage to another contractor,
199
APPROVAL WITHHELD ▪ When the above grounds are removed, payment shall be made for amounts withheld. (see number 198 of this flashcards)
200
CONDITIONS RELATIVE TO CERTIFICATES OF PAYMENTS ▪ The ______ shall estimate the value of work accomplished by the Contractor using as a basis the schedule stipulated in the breakdown of work and corresponding value. Such estimates of the Architect shall be final and conclusive evidence of the amount of work performed, and shall be taken as the basis for the full measure of compensation to be received at the time by the Contractor.
Architect
201
CONDITIONS RELATIVE TO CERTIFICATES OF PAYMENTS ▪ Such Preliminary estimates of amount and quantity shall not be required to be made by strict measurement or with exactness, but they may, at the option of the \_\_\_\_\_, be approximate only.
Architect
202
OWNER’S ACTION ON AN APPROVED REQUEST FOR PAYMENT ▪ Within _____ days from the date of approval of a Request for Payment or of issuance of a Certificate if Payment by the Architect, the Owner shall pay the amount as certified by the Architect or pay such other amount as he shall decide is due the Contractor, informing the Contractor and the Architect in writing of his reasons for paying the amended amount.
fifteen
203
OWNER’S ACTION ON AN APPROVED REQUEST FOR PAYMENT ▪ Owner’s failure to pay the amount involved would be subject to payment based on _______ prevailing at the time of the signing of the contracts
banking loan rates
204
PAYMENT OF CONTRACTOR’S OBLIGATIONS ▪ The ______ shall pay workmen employed by him on his project such rates as are provided by existing laws. He shall also pay promptly all materials and equipment used by him on his project, and all taxes due from him. He shall remit as required by law all amount withheld from the salaries or wages of his employees or workmen.
Contractor
205
PAYMENT OF CONTRACTOR’S OBLIGATIONS ▪ If required he shall furnish the Owner with a statement sworn to before an officer duly authorized to administer oath that all persons who have done work or furnished materials under this Contract have been duly paid. If such written evidence is not furnished before the final payment in under the Contract falls due, said Owner may after due notice to and clearance by the _____ pay such lawful claims in whole or in part to any person, firm, or corporation claiming the same, and charge the amount thus paid to said Contractor, who will accept the same as payment from the amount due on the Contract.
Contractor
206
PAYMENTS OVER 65 PERCENT ▪ No payment shall be made on contracts in excess \_\_\_\_\_\_\_%) of the Contract Price, unless a statement sworn before an officer duly authorized to administer oath is submitted by the Contractor to the effect that the bills for labor other than current wages, and all bills for materials have been duly paid by the Contractor and his Sub-contractor, if any, excepting only such bills as may be enumerated in such sworn statement.
sixty five percent (65%
207
PAYMENTS OVER 65 PERCENT ▪ Provided however, that should such sworn statement turn out false, the ____ and the work cover whereby shall not be liable for any claim or lien arising from the failure to pay and other causes, provided for in this clause the Contractor does hereby bind itself society answerable for any such lien should the same arise.
Owner
208
CORRECTION OF WORK BEFORE FINAL PAYMENT ▪ The ______ shall promptly remove the premises all work condemned by the Architect as failing to conform to the Contract, whether incorporated or not, and the Contractor shall promptly replace and re-execute his own work in accordance with the Contract and without expense to the owner and shall bear the expenses of making good all work of other contractors destroyed or damaged by such removal or replacement.
Contractor
209
CORRECTION OF WORK BEFORE FINAL PAYMENT ▪ If the _____ does not remove such condemned work within a reasonable time, fixed by written notice, the Owner may remove them and may store the material at the expense of the Contractor. If the Contractor does not ay the expenses of such removal within ten days time thereafter, the Owner may, upon ten days written notice, soil such materials at auction or at private sale and shall account for the net proceeds thereof, after deducting all the costs and expenses that should have been borne by the Contractor.
Contractor`
210
OTHER REQUIREMENTS BEFORE FINAL PAYMENT ▪ Certificate of ________ Occupancy unless such certificate cannot be obtained through no fault of the Contractor ▪ Certificate of Final Inspection of electrical, telephone, sanitary, mechanical, gas, safety and other utilities unless such certificate cannot be obtained through fault no Contractor.
Final Building
211
OTHER REQUIREMENTS BEFORE FINAL PAYMENT ▪ Original and ______ sets of prints of “As-Built Drawings” if electrical, sanitary, gas, telephone and mechanical works, if such works are within the scope of the contract “As-Built Drawings” are the working drawings showing the system and actual locations of outlets, fixtures, services, and equipment that were installed.
three (3)
212
OTHER REQUIREMENTS BEFORE FINAL PAYMENT ▪ ______ copies of Directory of Panel Boards and list of circuits ▪ _______ copies of instructions and manual for operating and maintaining of fixtures and equipment. ▪ _____ copies of keying Schedule
Three (3) Three (3) Three (3)
213
OTHER REQUIREMENTS BEFORE FINAL PAYMENT ▪ Guarantee bond equivalent to \_\_\_% of the Contract Price covering a period of one year after the final acceptance of the work which guarantees the quality if the contract works and materials installed. The Guaranteed bond shall be in the form of securities as approved by the Owner, The Guarantee Bond will be required only if the Owner, upon acceptance of the building, releases to the Contractor the Performance Bond and Payment Bond.
30%
214
ACCEPTANCE AND FINAL PAYMENT ▪ Whenever this Contract, in the opinion of the \_\_\_\_\_\_, shall be completely performed on the part of the Contractor, the Architect shall proceed to verify the work, shall make the final estimates, shall certify as to the completion of the work, and accept the same.
Architect
215
ACCEPTANCE AND FINAL PAYMENT ▪ a. The Owner shall then, excepting for causes herein specified, pay to the Contractor promptly, after the execution of said certificate, the remainder which shall be bound due, excepting there from such sum or sums as may be lawfully retained under any of the provision of this Contract PROVIDED THAT FINAL PAYMENT ON THE CONTRACT SHALL NOT BE MADE UNTIL THE CONTRACTOR HAS SUBMITTED A STATEMENT SWORN TO BEFORE AN OFFICER DULY AUTHORIZED TO ADMINISTER OATH, SHOWING THAT ALL TAZES DUE FROM HIM, AND ALL OBLIGATIONS FOR MATERIALS USED AND LABOR EMPLOYED IN CONNECTION WITH THIS CONTRACT HAVE BEEN DULY PAID; AND PROVIDED, FURTHER that nothing here in contained shall be construes to waive the right of the\_\_\_\_\_ hereby reserved to reject the whole or any portion of the aforesaid work, should the same be found to have been constructed in violation of the drawings and specifications or of any of the conditions or covenants of this Contract within the guarantee period.
Architect
216
ACCEPTANCE AND FINAL PAYMENT ▪ The making and acceptance of the final payment shall constitute a waiver of all claims by the \_\_\_\_\_
Contractor
217
CORRECTION OF WORK AFTER FINAL PAYMENT ▪ Neither the final certificate nor payment nor any provision in the Contract Documents shall relieve the _____ of responsibility for faulty materials or workmanship and, he shall remedy any defects due thereto and pay for any damage to other work resulting there from, which shall appear within a period of one year from the date of acceptance of work.
Contractor
218
CORRECTION OF WORK AFTER FINAL PAYMENT ▪ Neither the foregoing nor any provision in the contract documents, nor any special guarantee limit, shall be held to limit the _____ liability for defects and damages and the right of the Owner under the provisions of the New Civil Code, and all laws, regulations and ordinance applicable to the plans and construction of the building.
Contractor’s
219
CORRECTION OF WORK AFTER FINAL PAYMENT ▪ The ____ shall give notice of observed defects with reasonable promptness. All questions arising under this article shall be decided by the Architect whose decision shall be subject to arbitration.
Owner
220
RELEASE OF RETENTION ▪ The amount retained by the Owner under the provision of the contract shall be released within \_\_\_\_ months after the date of final payment.
three
221
SECTION VII
Contractor-separate Contractors- Sub-contractors Relations
222
OWNERS RIGHT TO LET OTHER CONTRACTS ▪ The ____ reserves the right to let other contracts in connection with this work.
Owner
223
Contractor-separate contractors relations STORAGE OF MATERIALS AND WORK COORDINATION ▪ The _____ under this Contract shall afford other contractors reasonable opportunity for the introduction and storage of their materials and the execution of their work, and shall property connect and coordinate his work with theirs so as to minimize interferences or obstruction in the progress of the work.
Contractor
224
CUTTING, PATCHING AND DIGGING ▪ The ____ shall do all cutting, fitting or patching of his work that may be required to make its several parts come together property and fit it to receive or be received by work of other contractors shown upon, or reasonably implied by, the Drawings and Specifications for the completed structure, and he shall make good after them as the Architect may direct.
Contractor
225
CUTTING, PATCHING AND DIGGING ▪ Any cost caused by defective or ill-timed work shall be borne by the party responsible therefore. ▪ The ____ shall not endanger any work by cutting, digging or otherwise and shall not cut or alter the work of any other contractor save with the consent to the \_\_\_\_
Contractor Architect.
226
DEFECTIVE WORK BY SEPARATE CONTRACTORS ▪ If any part of the Contractor’s work depends for proper execution or results upon the work of any other contractor shall inspect and promptly report to the ____ any defect in such work that renders it unsuitable for such proper execution and result. His failure to inspect and report shall constitute an acceptance of the other contractors work as fit and proper for the reception of his work, except as to defect which may develop in the other contractor’s work after the execution of his work.
Architect
227
DEFECTIVE WORK BY SEPARATE CONTRACTORS ▪ To insure the proper execution of his subsequent work the contractor shall verify work already in place and shall at once report to the ____ any discrepancy between the executed work and drawings.
Architect
228
DAMAGE CAUSED BY CONTRACTOR TO SEPARATE CONTRACTORS ▪ Should the _____ cause damage to any separate contractor on the work, the Contractor agrees, upon due notice, to settle with such contractor by agreement or arbitration and to relieve the Owner of any liability which may arise there from.
Contractor
229
SUBCONTRACTS ▪ It is understood and agreed that the entire work called for by this Contract shall not be sublet or sub-contracted. However, any part thereof or any specialty work therein, may be sublet or subcontracted. Subject to the provision of Article 25.02. Nothing contained in the Contract Documents shall create any contractual relation between any sub-contractor and the \_\_\_\_
Owner.
230
COMPETECY OF SUBCONTRACTOR ▪ At least _____ days prior to the date of bidding, the Contractor shall seek the Architects clarification as to the particular areas or parts of the work for which the competence of the subcontractor shall be subject to evaluation by the \_\_\_\_\_. Immediately thereafter, the Contractor shall submit to the Architect a list of his prospective sub-contractors for approval.
fifteen (15) Architect.
231
CONTRACTOR’S RESPONSIBILITY ▪ The ___ agrees that he is as fully responsible to the Owner for the acts and omission of his subcontractors and the persons either directly or indirectly employed by them, as he is for the acts and omissions of persons directly employed by him.
Contractor
232
SECTION VII
Suspension of Work and Termination of Contract
233
CONTRACTOR’S RIGHT TO SUSPEND WORK/TERMINATE CONTRACT ▪ The contractor may suspend work or terminate contract upon _____ days’ written notice to the owner and the Architect for any of the following reasons: ▪ If an order of any court or other public authority caused the work to be stopped or suspended for a period of _____ ) days through no act or fault of the contractor or his employees. ▪ If the Architect should fall to act upon any Request for payment within _____ after it is presented in accordance with the general Conditions of the Contract.
fifteen (15) ninety (90 (15) days
234
CONTRACTOR’S RIGHT TO SUSPEND WORK/TERMINATE CONTRACT ▪ If the owner should fall to act upon any request for payment or certificate of payment within ____ days after its certification by the Architect. ▪ If the Owner should fail to pay the contractor any sum within ___ days after its award by arbitration.
(15) | (30)
235
CONTRACTOR’S RIGHT TO SUSPEND WORK/TERMINATE CONTRACT ▪ If the ____ is compelled you suspend work due to hardships or difficulties under b, c, and d above, then the contract sum shall be increased by the amount of the contractor’s reasonable costs of shutdown delay and start up, which shall be effected by appropriate change order.
Contractor
236
OWNER’S RIGHT TO TERMINATE CONTRACT ▪ The Owner, upon the certificate of the Architect that sufficient cause exists to justify his action, may without prejudice to any other right or remedy and after giving the Contractor and his surely if any, \_\_\_\_\_\_ days’ written notice, terminate the contract with the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish work by whatever method he may, deem expedient. Sufficient cause to justify termination of the contract shall deem to exist whenever the Contractor does any of the following:
fifteen (15) ▪ Declare bankruptcy become insolvent or assign his assets for the benefit of his creditors. ▪ Disregard or violate provisions of the Contract Documents or Architect’s Instructions, or fail to prosecute the work according to the agreed schedule of Completion, Including extensions thereof. ▪ Fail to provide a qualified superintendent, competent workmen or sub-contractors, or proper materials. ▪ fail to make prompt payment to sub-contractors, workmen or material dealers.
237
USE OF MATERIALS AND EQUIPMENT AT SITE ▪ The Contractor, upon receiving notice of the termination of contract, shall vacate possession and deliver the said work, or the parts thereof specified in said notice, peaceable to the owner. All materials, plant, appliances and other essential equipment as may be needed by the construction of the project shall, at the option of the \_\_\_\_, remain on the work until completed, at such rental as may be considered reasonable.
Architect
238
USE OF MATERIALS AND EQUIPMENT AT SITE ▪ In case such materials and/or equipment do not belong to the contractor, then the ____ shall have the option to retain them for use in the project at the cost of the failing Contractor, or pay reasonable rent for the use, chargeable against the Contractor.
Architect
239
OWNER TO COMPLETE WORK ▪ The ____ shall then take over the work and proceed to complete the same by administration or otherwise, and use such tools, appliances and materials of every description as may be found upon the line of said work, or at point where materials are built or framed for the work and also procure such other tools and materials for the completion of the work as may be required.
Owner
240
EVALUATION OF COST OF WORK ▪ It is agreed and understood that, upon such termination of this Contract, the _____ will ascertain and fix the value of the work completed by the Conductor and not paid for by the owner and of all usable materials on the line of the work taken over by the Owner at the time of said termination.
Architect
241
EVALUATION OF COST OF WORK ▪ In the event that the total expenditures of the \_\_\_\_ on completion of the work, Including all charges against the project prior to termination of the contract and compensation for additional architectural managerial and administrative services, are not in excess of the Contract Price, then the difference between the said total expenditures of the Owner and the Contract price may be applied to settle claims filed, and the balance, If any, may be paid to the Contractor.
Owner
242
EVALUATION OF COST OF WORK ▪ No amount in excess of the combined value of the unpaid completed work, retained percentage and usable materials taken over by the ____ at the time of the Termination of the Contract shall be paid, nor shall any claim for prospective profits on the work done after termination of the Contract be considered or allowed.
Owner
243
EVALUATION OF COST OF WORK ▪ In case of suspension of work, all unpaid work executed including expenses incurred during suspension shall be evaluated by the architect and charged to the \_\_\_\_
owner.
244
OWNER’S RIGHT TO RECOVER LIQUIDATED DAMAGES ▪ Neither the taking over by the Owner of the work for completion by administration nor the re-letting of the same to another Contractor shall be construed as a waiver of the Owner’s rights to recover damages against the original ____ and/or his sureties for the failure to complete the work as stipulated.
Contractor
245
OWNER’S RIGHT TO RECOVER LIQUIDATED DAMAGES ▪ In such case, the full extent of the damages for which the Contractor and/or his sureties shall be liable shall be: ▪ The total daily liquidated damages up to and including the day immediately before the date the Owner effectively takes over the work. ▪ The excess cost incurred by the ____ in the completion of the project over the Contract Price. This excess cost includes cost of architectural managerial and administrative services, supervision and inspection from the time the owner effectively took over the work by administration or by re-letting same.
Owner
246
SECTION IX
Responsibilities and Liabilities of Contractor and of Owner
247
Contractor’s responsibility for accidents and damage SAFEGUARDS TO BE UNDERTAKEN BY CONTRACTOR ▪ The ____ shall take all necessary precautions for the safety of employees and workmen on the work, and the comply with all applicable provisions of city, municipal and national safety laws and building codes and all government rules and regulations, to prevent injury to persons on about or adjacent to the premises where work being performed.
Contractor
248
SAFEGUARDS TO BE UNDERTAKEN BY CONTRACTOR ▪ The ____ shall erect and properly maintain at all times, as required by the conditions and progress of the work, such barriers, shoring, supports, braces lights, danger signs and necessary safeguards, as will protect workmen and the public and as well effectually prevent any accident and damage to properly in consequence of his work.
Contractor
249
CONTRACTOR’S RESPONSIBILITY ▪ The ____ shall not be responsible for the death of disease contracted, or injury received by the Contractor or any employee or laborers of the Contractor; for the contractor’s plant or materials, for any damage done by or to them from any source or cause; and damages caused by the Contractor or his employees to any property of the Owner and adjoining property. All damages shall be the responsibility of the \_\_\_\_
owner Contractor
250
INDEMNITY ▪ The ____ shall indemnify and save harmless the Owner from and against all losses and all claims, demands, payments, suits, actions, recoveries, and judgment of every nature and description brought or recovered against him, by reason of any act or omission of said Contractor, his agents or employees, in the execution of the work or the guarding of it.
Contractor
251
\_\_\_\_\_ is a contractual obligation of one party to compensate the loss occurred to the other party due to the act of the indemnitor or any other party. The duty to indemnify is usually, but not always, coextensive with the contractual duty to "hold harmless" or "save harmless".
Indemnity
252
INDEMNITY ▪ Claims for payment and repairs for damages shall be settled by the _____ at his own expense and to the satisfaction of the Architect and the parties concerned. In the event of failure of the Contractor to repair at once such damages, and pay other claims, the owner may repair the same and pay the claims, and deduct the entire cost of such repairs and claims from the payments due the contractor.
Contractor
253
Contractor’s insurance and bonds CONTRACTOR’S LIABILITY INSURANCE ▪ The Contractor shall secure and maintain such Insurance from an Insurance company acceptable to the _____ as will protect himself, his subcontractors, and the Owner from claims for bodily Injury, death or properly damage which may arise from operations under his Contract.
Owner
254
CONTRACTOR’S LIABILITY INSURANCE ▪ The Contractor shall not commence work under his Contract until he has obtained all insurance required under this section and shall have filed the certificate of Insurance or the certified copy of the insurance policy with the Owner. Such insurance policy shall contain a clause providing that it shall not be cancelled by the insurance company without ____ days’ written notice to the Owner of intention to cancel. The amounts of such shall be as agreed-upon.
ten (10)
255
CONTRACTOR’S FIRE INSURANCE ▪ In addition to such fire insurance as the Contractor elects to carry for his work protection, he shall secure and maintain in the name of the \_\_\_\_ policies upon such structures and materials and in such amount as shall be designated. These policies shall be secured from a company which is satisfactory to the Owner and delivered to the Owner.
Owner
256
CONTRACTOR’S PERFORMANCE AND PAYMENT BONDS ▪ The Contractor, prior to signing the Contract, shall furnish a Performance Bond equal to \_\_\_% of the Contract amount for the faithful performance of his work and \_\_\_% Payment Bond covering payments and obligations arising from his Contract. Such bonds shall be in the forms of sureties as approved by the Owner. Such bonds shall remain in effect untill replaced by the Contractor’s Guarantee Bond.
15% 15%
257
CONTRACTOR’S GUARANTEE BOND ▪ The performance and Payment Bonds will be released by the Owner after the expiration of\_\_\_\_ months from the final acceptance of the work and only after the Contractor has furnished the Owner, a Guarantee Bond In the amount of 30% of the total Contract cost. The Guarantee Bond shall be for a period of _____ year commencing from the date of acceptance as a guarantee that all materials and workmanship installed under Contract are of good quality.
two one (1) | (2)
258
CONTRACTOR’S GUARANTYWARRANTY ▪ The _____ shall, in case of work performed by his sub-contractors and where guarantees are required, secure warranties from said subcontractors and deliver copies of same to the Owner upon completion of work. ▪ The ____ shall and thereby warrants all work performed by him directly and for which guarantee are required.
Contractor Contractor
259
CONTRACTOR’S GUARANTYWARRANTY ▪ The Contractor shall and thereby warrants and/or guarantees for a period of one year, or for longer periods where so provided in Specifications, as evidenced by date of final certificate Issued by the \_\_\_\_, all materials and workmanship Installed under Contract to be of good quality in every respect and to remain so for periods described herein.
Architect
260
CONTRACTOR’S GUARANTYWARRANTY ▪ Should any defects develop in aforesaid work, within the specified-periods, due to faults in material and/or workmanship, the Contractor thereby agrees to make all repairs and do all necessary work to correct defective work to the Architect’s satisfaction. Such repairs and corrective works shall be done without cost to the Owner and at entire cost and expense of the Contractor within _____ days after written notice to the Contractor by the Owner.
five (5)
261
CONTRACTOR’S GUARANTYWARRANTY ▪ In case the Contractor fails to do the work, so ordered, the ____ may have the work done and change the cost thereof against monies retained as provided for in the Agreement and, if said retained monies shall be insufficient to pay such cost, or it no money is available, the Contractor and his sureties agree to pay to the Owner the cost of such work.
owner
262
CONTRACTOR’S GUARANTYWARRANTY ▪ The entire foregoing are without prejudice to the right of the Owner under the \_\_\_\_\_, and other laws now or hereafter that may be applicable.
new Civil Code
263
Owner’s responsibilities and liabilities PROTECTION OF EMPLOYEES AND PROFESSIONALS PERFORMING SERVICES FOR THE OWNER ▪ The ____ shall be responsible for and shall maintain such insurance as will protect him for personal injury including disease and death of persons under his employ or services, temporary or permanent in status, that are assigned for the project.
Owner
264
PROTECTION OF EMPLOYEES AND PROFESSIONALS PERFORMING SERVICES FOR THE OWNER ▪ The ____ shall be responsible for and shall maintain such insurance as will protect him for personal injury including disease and death of persons under his employ or services, temporary or permanent in status, that are assigned for the project.
Owner
265
PROTECTION OF EMPLOYEES AND PROFESSIONALS PERFORMING SERVICES FOR THE OWNER ▪ Prior to the start of the construction, the ____ and ____ shall give a list of personnel assigned to the project who need to be covered by insurance and with the corresponding amount of coverage.
Owner and the Architect
266
OWNER’S OPTIONAL INSURANCE ▪ The ____ at his option may maintain such Insurance as will protect him from his contingent liability for damages, for personal injury, including death, which may arise from the operations under this contract, and any other liability for damages which the contractor is required to insure under any provision of this contract.
Owner
267
LIENS ▪ Neither the final payment nor any part of the retained percentage shall become due until the Contractor, if required, shall deliver to the \_\_\_\_a complete release of all liens arising out of this Contract, or receipts in full in lieu thereof ▪ if required in either case of affidavit that so far as he has knowledge or information the release and receipts include all the labor and materials for which a lien could be filed
Owner
268
\_\_\_\_ is a form of security interest granted over an item of property to secure the payment of a debt or performance of some other obligation.
lien The owner of the property, who grants the lien, is referred to as the lienee and the person who has the benefit of the lien is referred to as the lienor or lien holder.
269
LIENS ▪ but the Contractor may, if any sub-contractor refuses to furnish a release or receipt in full, furnish a bond satisfactory to the \_\_\_\_, to indemnity him against any lien. If any lien remain unsatisfied after all payments are made, the \_\_\_\_ shall refund to the Owner all monies that the latter may be compelled to pay in discharging such lien, including all cost and a reasonable attorney’s fee.
Owner Contractor
270
ASSIGNMENT ▪ This Contract shall not be assigned In whole or in part by the contractor nor shall any part of the work be sublet by the ____ without the prior written consent of the Owner and such consent shall not relieve the Contractor from full responsibility and liability for the work hereunder and for the due performance of all the terms and conditions of the Contract.
Contractor
271
ASSIGNMENT ▪ The Owner’s consent to any subletting of work hereunder shall not be granted in any event until the Contractor has furnished the ____ with satisfactory evidence that the sub-contractor is carrying ample insurance to the same extent and in the same manner as is herein provided to be the contractor.
Owner
272
ASSIGNMENT ▪ If the Contract is assigned or any part thereof is sublet, the Contractor shall exonerate, indemnify and save harmless the _____ from and against any and all loss or expense caused thereby.
Owner
273
ASSIGNMENT ▪ In case of any such transfer without the previous written consent of the Owner, the ____ may refuse to carry out the Contract either with the transferor or transferee; but all rights of action breach of this Contract by the Contractor shall be reserved to and remain within said Owner.
Owner
274
DAMAGES ▪ Should either party to this Contract suffer damages because of any wrongful act or neglect of the other party or of anyone employed by him, claim shall be made in writing to the party liable within a reasonable time to the first observance of such damage and not later than the \_\_\_\_\_, except as expressly stipulated otherwise in the case of faulty or materials, and shall be adjusted by agreement or arbitration.
final payment
275
DISPUTES ▪ The ______ shall, within a reasonable time, make a decision on all claims of the Owner or Contractor and on all matters relating to the execution and progress of the work or the Interpretation of the Contract Documents.
Architect
276
DISPUTES ▪ Except as otherwise specifically provided in the Contract, all disputes concerning questions of fact arising under the Contract shall be decided by the \_\_\_\_\_, whose decision shall be final and conclusive upon the parties thereto as to questions of fact. ▪ The _____ decisions shall be final, if within the terms of the Contract
Architect Architect’s
277
DISPUTES ▪ If however, the Architect fails to render a decision within f\_\_\_\_ days after the parties have presented their evidence, either party may then demand arbitration. If the Architect renders a decision after arbitration proceedings have been initiated, such decision may be entered as evidence but shall not disturb or interrupt such proceedings except where such decision acceptable to the parties concerned.
ifteen
278
ARBITRATION ▪ All disputes, claims or questions subject to arbitration under this contract shall be settled in accordance with the provisions of this article.
279
ARBITRATION ▪ Notice of the demand for arbitration of a dispute shall be filled in writing with me other party to the contract, and a copy filed with the \_\_\_\_\_. The demand for arbitration shall be made within a reasonable time after the dispute arisen; In no case however, shall the demand be made later than the time of the final payment except as otherwise expressly stipulated in the contract.
Architect
280
ARBITRATION ▪ When formal arbitration is requested, a Board of arbitration shall be formed in the following manner. The ____ and \_\_\_\_\_shall each appoint one member of his board and these members shall appoint a third member who shall act as chairman. No one with a financial interest in the subject under arbitration will be permitted to serve on this board.
Owner and the Contractor
281
ARBITRATION ▪ This ____ may engage experts to act in an advisory capacity. Minutes shall be kept off all meetings and signed by all members of the board. Decisions of the board shall require only a simple majority and all interested parties shall be informed thereof. Expenses of the Board shall be paid in accordance with the agreement set forth \_\_\_\_\_\_
Board before the proceedings of the board.
282
ARBITRATION ▪ It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right of legal action that either party may have against the other. The Contractor shall not cause a delay of the work during any arbitration proceedings, except by agreement within the \_\_\_\_\_.
Owner
283
SECTION X
Authority of Architect, Engineers And Project Representatives
284
ARCHITECT STATUS ▪ The _____ shall be the Owner’s representative during the construction period and he shall observe the work in the process on behalf of the Owner. He shall have authority to act on behalf of the Owner only to the extent expressly provided in the Contract Documents or otherwise in writing, which shall be shown to the Contractor
Architect
285
ARCHITECT STATUS ▪ He shall have authority to stop the work whenever such stoppage may be necessary in his reasonable opinion to insure the proper execution of the Contract. The _____ failure of not ordering the stopping of the work, does not relieve the Contractor from the responsibility of complying with the Contract Documents and the sole responsibility of protecting persons, on, about, or adjacent to the premises where work is being performed against injury and death, and of protecting the Owner’s property and adjoining properly against damage.
Architect’s
286
ARCHITECT STATUS ▪ The ____ shall decide any and all questions which may arise as to the quality and acceptability of materials furnished and work performed and as to the manner of performance and rate of progress of work, and shall decide all questions which may arise as to the interpretation of the Drawings and Specifications, and all questions as to the acceptable fulfillment of the terms of the Contract .
Architect
287
ARCHITECT STATUS ▪ As the Architect is, in the first Instance, the Interpreter of the conditions of the contract and the judge of its performance, he shall side neither with the Owner nor with the Contractor, but shall use his powers and under the _____ to enforce its faithful performance by both.
Contract
288
ARCHITECT STATUS ▪ In case of the termination of the employment of the Architect, the ______ shall appoint a capable and reputable Architect against whom the Contract makes no reasonable objection, whose status under the Contract shall be that of the former Architect; any dispute in connection with such appointment shall be subject to arbitration.
Owner
289
AUTHORITY AND RESPONSIBILITIES OF THE ENGINEERS ▪ The _____ shall be solely responsible for their respective designs, computations and other professional services they rendered in connection with the preparation of Drawings and Specifications. They shall assist the Architects in the general supervision and direction of the particular portion of the work where their professional services are concerned.
Engineers
290
AUTHORITY AND RESPONSIBILITIES OF THE ENGINEERS ▪ The Engineers shall inspect the work for conformance with the approved Drawings and Specifications and shall report to the ____ any discrepancy between such work and said Drawings and Specifications. They shall make recommendations when necessary and as required consistent with the ethics of the profession.
Architect
291
AUTHORITY AND RESPONSIBILITIES OF THE ENGINEERS ▪ The Engineers shall perform any professional service necessary for the accomplishment of the work subject to the terms and conditions of the Inter-professional agreement between the \_\_\_\_ and _____ or any existing contract affecting or relative to the project
Architect and the Engineers
292
Authority and duties of the project representaives EMPLOYED BY THE OWNER ▪ Technically qualified men referred to as \_\_\_\_\_\_by the Architect and employed by the Owner may be stationed on the Project to assist the Architect and the Engineers in the general supervision and direction of the Work.
Project Representatives, resident Architects, Resident Engineers or Construction Inspectors recommended
293
DUTIES ▪ The duties of the Project Representatives, Resident Architects, Resident Engineers and Construction Inspectors are stipulated in the \_\_\_\_\_\_\_
Special Provision of the Contract.
294
DISPUTES ▪ : In case of any dispute arising between the Project Representative, Resident Architect, Resident Engineer, or Construction Inspector, and the Contractor, they shall have authority to r\_\_\_\_\_\_\_\_\_ until the question at issue can be referred to and decide by the Architect.
eject materials or suspend the work
295
DISPUTES ▪ Nothing in the provisions of this article will relieve the _____ from the responsibility of performing the work in accordance with the Drawings, Specifications and other Contract Documents.
Contractor
296
SECTION XI
Schedule of Time Limits
297
Contract time CONTRACT TIME RECKONING ▪ To commence on the ____ day from receipt of notice to Proceed
7th
298
REQUEST FOR TIME EXTENSION ▪ To be filed within _____ days from occurrence of delay (item a. par.1)
15
299
BEGINNING, SUSPENDING OR RESUMING OF WORK ▪ Written notice to be given to Architect at least ____ days prior to beginning, suspending (except in case of accident), or resuming the work. (item f).
10
300
REQUEST FOR SUPPLY OF OWNERFURNISHED MATERIALS ▪ Written request to be made ____ days before they are actually needed (item a. Par.2).
10
301
REQUEST FOR DRAWINGS ▪ No claim for delay shall be allowed on account of failure to furnish drawings until ____ weeks after demand for such drawings (item d.)
two
302
Contract sum CONTRACT SUM BREAKDOWN ▪ To be submitted within ___ days from the receipt of Notice to Proceed
15
303
CLAIM FOR EXTRA COST ▪ Notice to be given to Architect within ____ days ▪ after receipt of instruction involving extra cost, or ▪ after recognition of delay due to Owner’s fault
15
304
Progress payments ARCHITECT’S ACTION ON PAYMENT REQUEST ▪ To be made within ____ days after receipt of request for payment.
15
305
OWNER’S ACTION ON PAYMENT REQUEST ▪ To act within ____ days from date of Architect’s approval of the payment request.
15
306
RELEASE OF RETENTION ▪ To be released within ___ months after date of final payment.
3
307
Correction of work CORRECTION BEFORE FINAL PAYMENT ▪ Contractor to promptly remove from premises all work condemned by ____ as failing to confirm to the Contract, whether incorporated or not, and promptly replace and re-execute his own work in accordance with the contract without expense to the Owner.
Architect
308
CORRECTION BEFORE FINAL PAYMENT ▪ If Contractor fails to remove condemned work within a reasonable time from notice, ____ may remove and store the same at Contractor’s expense. ▪ Contractor must pay expenses within 10 days from removal by the owner; In default thereof, Owner may sell the materials after 10 days, from written notice of intent to sell.
Owner
309
CORRECTION AFTER FINAL PAYMENT ▪ Contractor should remedy any defects due to faulty materials or workmanship, which may appear within a period of __ year from date of acceptance of work by Owner (item a). ▪ Repairs and corrective work at the expense and cost of Contractor should be done within ___ days after written notice by owner (item d).
one 5
310
Sub-contractors claim for extra cost SUB-CONTRACTORS CLAIM FOR EXTRA COST ▪ Sub-contractor may make all claims for extras, for extension of time and for damages, for delays of otherwise to the ____ in the manner provided in the General Conditions of the Contract for the claims by the Contractor upon the Owner except that the time for making claims for extra cost is one week (item c).
Contractor
311
Contractor’s right to suspend work or terminate contract CONTRACTOR’S RIGHT TO SUSPEND WORK OR TERMINATE CONTRACT ▪ Contractor may suspend work or terminate Contract upon ___ days written notice to Owner and Architect, for any of the following reasons: ▪ If any court or other public authority orders work to be stopped or suspended for ___ days through no fault of the Contractor or his employees; ▪ If Architect fails to act upon request for payment within ____ days after presentation;
15 90 15
312
CONTRACTOR’S RIGHT TO SUSPEND WORK OR TERMINATE CONTRACT ▪ If Owner fails to act upon request for payment within \_\_\_ days after Architect’s certification; ▪ If Owners fails to pay Contractor the agreed sum within ___ days after its award by arbitrators.
15 30
313
OWNER’S RIGHT TO TERMINATE CONTRACT ▪ May be done after giving ___ days written notice to the Contractor or his Surety if Contractor should:
15 ▪ Declare bankruptcy, become insolvent or assign his assets for the benefit of his creditors ▪ Disregard or violate provisions of the Contract Documents or Architect’s Instructions. ▪ Fail to provide superintendent, workmen or subcontractors or proper materials. ▪ fail to make prompt payment to sub-contractors, workmen or material dealers.
314
DISPUTES ▪ If the Architect fails to render a decision within ___ days after parties have presented their evidence, either party may demand arbitration (item d).
15
315
Bonds and isnsurances CONTRACTOR’S LIABILITY INSURANCE ▪ Insurance policy shall not cancelled by insurance company without ___ days written notice to Owner of Intention to cancel.
10
316
CONTRACTOR’S PERFORMANCE AND PAYMENT BOND ▪ Such bonds shall remain in effect until replaced by the \_\_\_\_\_\_\_\_\_
Contractor’s Guarantee Bond
317
CONTRACTOR’S GUARANTEE BOND ▪ To be furnished the ___ after expiration of Performance and Payment Bonds and shall be effective for a period of one year commencing from the date of acceptance as a guarantee that all materials and workmanship installed are of good quality.
Owner
318