Time Mgmt Flashcards

1
Q

What is the process of time mgmt?

A
  • Define activities
  • Sequence activities
  • Estimate activity resources
  • Estimate activity durations
  • Develop schedule
  • Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In which process is the schedule management plan created?

A

The schedule mgmt plan is created in integration mgmt, as a part of the Develop Project Mgmt Plan process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key outputs of the Define Activities process?

A

Activity list

Activity attributes

Milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are key outputs of the Sequence Activities process?

A

Network diagrams

Project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are key outputs of the Estimate Activity Resources process?

A

Activity resource requirements

Resource breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are key outputs of the Estimate Activity Durations process?

A

Activity duration estimates

Project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Develop Schedule process?

What are its key outputs?

A

The actions and tools necessary to create a bought into, approved, realistic, and formal project schedule

Outputs:

  • Project schedule
  • Schedule baseline
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are key outputs of the Control Schedule process?

A

Work performance measurements

Change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are mandatory dependencies and discretionary dependencies?

A

Mandatory: One activity MUST be done after or before another; may also be called hard logic

Discretionary: When you PREFER activities to be accomplished in a certain order; may also be called preferred, preferential, or soft logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are external dependencies?

A

Dependencies base on the needs of a party OUTSIDE the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a resource breakdown structure?

A

An organizational chart or table showing idenfied resources by category

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the critical path?

How does it help the project?

A

The longest path through the network diagram

It shows the project mgmr the shortest time in which the project can be completed

It shows the project mgr where to focus his or her time

It is used in compressing or adjusting the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the near-critical path?

A

The path closest in length to the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Define lag

A

Watiting time inserted into the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define total float and the formula for total float

A

The amount of time an activity can be delayed without delaying the project

Formula:

Late start-Early Start

OR

Late finish-Early finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Define free float and project float

A

Free Float: The amt of time an activity can be delayed without delaying the early start date of its successor

Project Float: The amount of time the project can be delayed without affecting the project’s required end date; the desired project end date minus the actual end date

17
Q

What are methods to compress a schedule?

A

Crashing

Fast tracking

18
Q

What is crashing

A

Schedule compression through analyzing cost & schedule trade-offs to obtain the greatest compression for the least cost while maintaining scope

19
Q

What is fast tracking?

A

Schedule compression by doing more critical path activities in parallel

20
Q

What is the critical chain method?

A

A schedule network analysis tool that makes use of buffers

21
Q

What is reestimating

A

Estimating the project again after planning to make sure you can still meet the end date, budget, or other objectives

22
Q

What is resource leveling?

A

Keeping the amount of resources used for each time period constant, thus affecting the project duration

23
Q

What is a schedule baseline?

A

The approved schedule with any approved changes, used to measure project schedule performance

24
Q

What are main tools for displaying schedule?

A

Network Diagrams

Bar charts

Milestone charts

25
Q

What do network diagrams show?

A

Interdependencies between activities

How project activities will flow from beginning to end

Network diagrams may also be used to determine critical path

26
Q

What do simple bar charts show?

A

Project schedule or project status

27
Q

What do milestone charts show?

A

High level project status

28
Q

What is Monte Carol analysis?

A

A schedule network analysis technique

It is used to simulate the project to determine how likely you are to get the project completed by any specific date or for any specific cost

It is also used in the Perform Quantitative Risk Analysis process to determine an overall level of risk on the project

29
Q

What are the following rules?

50/50 rule

20/80 rule

0/100 rule

A

Methods of progress reporting

50% (or 20% or 0%) of the effort is reported complete when an activity begins.

The balance (50%, 80% or 100%) is recorded only when an activity is finished.