Time Mgmt Flashcards
What is the process of time mgmt?
- Define activities
- Sequence activities
- Estimate activity resources
- Estimate activity durations
- Develop schedule
- Control schedule
In which process is the schedule management plan created?
The schedule mgmt plan is created in integration mgmt, as a part of the Develop Project Mgmt Plan process
What are the key outputs of the Define Activities process?
Activity list
Activity attributes
Milestone list
What are key outputs of the Sequence Activities process?
Network diagrams
Project document updates
What are key outputs of the Estimate Activity Resources process?
Activity resource requirements
Resource breakdown structure
What are key outputs of the Estimate Activity Durations process?
Activity duration estimates
Project document updates
What is the Develop Schedule process?
What are its key outputs?
The actions and tools necessary to create a bought into, approved, realistic, and formal project schedule
Outputs:
- Project schedule
- Schedule baseline
What are key outputs of the Control Schedule process?
Work performance measurements
Change requests
What are mandatory dependencies and discretionary dependencies?
Mandatory: One activity MUST be done after or before another; may also be called hard logic
Discretionary: When you PREFER activities to be accomplished in a certain order; may also be called preferred, preferential, or soft logic
What are external dependencies?
Dependencies base on the needs of a party OUTSIDE the project
What is a resource breakdown structure?
An organizational chart or table showing idenfied resources by category
What is the critical path?
How does it help the project?
The longest path through the network diagram
It shows the project mgmr the shortest time in which the project can be completed
It shows the project mgr where to focus his or her time
It is used in compressing or adjusting the schedule
What is the near-critical path?
The path closest in length to the critical path
Define lag
Watiting time inserted into the schedule.
Define total float and the formula for total float
The amount of time an activity can be delayed without delaying the project
Formula:
Late start-Early Start
OR
Late finish-Early finish